Data Centers in Ellis County

Under construction

Ellis County hosts 10 Comptroller-certified sites and 32 TDLR construction filings Projects touch 4 school districts (Ferris Independent School District, Midlothian Independent School District, Red Oak Independent School District, and Waxahachie Independent School District). U.S. House seats in the record: District 6. Free brief: power, water, and politics from those records. Annual unlocks school-district tax-base fields (top taxpayers, M&O, per-pupil) and who governs a specific pin on the map.

Power

Ellis County power records from Comptroller certificates and TDLR filings. Certified names in the public record include Rise Data Center, Cinco Data Center, Alamo Data Center, Sharka Data Center, Thelma Data Center, Meitner Data Center, DFW 12, DFW 9, and 2 more. TDLR project names include Databank Red Oak - DFW12, DFW III-II Building 2 Tenant Fit Out, DFW III-II Building 1 (Roadrunner), DFW III-II Building 3 Tenant Fit Out, Vallies ELT-1, DataBank Red Oak - DFW11 TFO, and 26 more. Sharka Data Center - Building 5 lists an estimated cost of $491,727,252. Nearby ERCOT queue capacity summarized by fuel includes 2,982 MW Other; 1,505 MW Solar; 54 MW Gas. Approximate sites stay county-level when geocode quality does not support a precise city.

Water

Water at project locations (not whole-county coverage). Known sites name PRAIRIELANDS GROUNDWATER CONSERVATION DISTRICT. District boundaries do not follow county lines.

Politics

Ellis County siting records (not a full voter guide). School districts appearing on certified or filed sites include Ferris Independent School District, Midlothian Independent School District, Red Oak Independent School District, and Waxahachie Independent School District. U.S. House districts in the record: District 6 — Jake Ellzey (R). State House: District 10 — Brian Harrison (R). State Senate: District 2 — Bob Hall (R); District 22 — Brian Birdwell (R). Tax-base fields (top taxpayers, M&O, per-pupil) stay annual-only. Pin-level “who governs this parcel” is annual on the map.

Loading map…

Power records

Full power records (public feeds)
Certified site
Rise Data Center
Occupant
Google LLC
Owner
Platon Investments LLC
Operator
Design, LLC Google Energy LLC
Facility
LD107696
Certificate type
large
City
Red Oak
Certified site
Cinco Data Center
Occupant
Google (Design LLC)
Owner
Rowan Digital Infrastructure (Rowan Cinco LLC)
Operator
Google LLC
Facility
LD107783
Certificate type
large
City
Red Oak
Certified site
Alamo Data Center
Occupant
Google (Design LLC)
Owner
Alamo Mission LLC
Operator
Google LLC
Facility
LD543087
Certificate type
large
City
Red Oak
Certified site
Sharka Data Center
Occupant
Google (Design LLC)
Owner
Sharka LLC
Operator
Google LLC
Facility
LD693418
Certificate type
large
City
Midlothian
Certified site
Thelma Data Center
Occupant
Google LLC
Owner
Homebound Group LLC
Operator
Google LLC Design, LLC
Facility
LD721172
Certificate type
large
City
Red Oak
Certified site
Meitner Data Center
Occupant
Google LLC
Owner
IP Meitner DTC, LLC
Operator
IP Meitner, LLC Design, LLC Google LLC
Facility
LD893305
Certificate type
large
City
Red Oak
Certified site
DFW 12
Occupant
Oracle America Cloud Services LLC
Owner
DataBank (DB Data Center Red Oak, LLC)
Operator
Databank Holdings LTD Oracle America, Inc.
Facility
DC
Certificate type
qualifying
City
Red Oak
Certified site
DFW 9
Occupant
Oracle America Cloud Services LLC
Owner
DataBank (DB Data Center Red Oak, LLC)
Operator
Databank Holdings LTD Oracle America, Inc.
Facility
DC047213
Certificate type
qualifying
City
Red Oak
Certified site
SDC DFW VIII, L.P.
Occupant
GOOGLE LLC
Owner
Stream Data Centers (SDC DFW VIII, L.P.)
Operator
Stream Data Centers (SDC DFW VIII, L.P. Jones Lang La Salle Amercias, Inc. Design, LLC)
Facility
DC496068
Certificate type
qualifying
City
Red Oak
Certified site
DFW 10
Occupant
Oracle America Cloud Services LLC
Owner
DataBank (DB Data Center Red Oak, LLC)
Operator
Databank Holdings LTD Oracle America, Inc.
Facility
DC961212
Certificate type
qualifying
City
Red Oak
TDLR project
Databank Red Oak - DFW12
Facility
DFW12
Owner
Databank
Estimated cost
$325,000,000
Square footage
425,170
Type of work
New Construction
Scope
New construction, two story data center with office component. 425,170 SF
Status
Project Registered
Design firm
817-929-6997
Location
Stainback Rd, Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 2 Tenant Fit Out
Facility
DFW III-II Building 2
Owner
Compass Datacenters
Estimated cost
$57,000,000
Square footage
195,000
Type of work
Renovation/Alteration
Scope
Tenant fit out of approximately 195,000 sf of administrative and data hall spaces including renovations to existing building entrance and loading docks, office spaces, data hall computer rack and technology and electrical distribution.
Status
Review Complete
Design firm
(972) 934-8888
Location
481 Austin Blvd, Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 1 (Roadrunner)
Facility
Roadrunner Bldg 1
Owner
Compass Datacenters
Estimated cost
$100,000,000
Square footage
250,000
Type of work
New Construction
Scope
New Data Center Building
Status
Project Closed
Design firm
617-430-7192
Location
300 Houston School Road N of E Ovilla Rd 1 mile W of I-35E, Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 3 Tenant Fit Out
Facility
DFW III-II Building 3
Owner
Compass Datacenters
Estimated cost
$57,000,000
Square footage
195,000
Type of work
Renovation/Alteration
Scope
Tenant fit out of approximately 195,000 sf of administrative and data hall spaces including renovations to existing building entrance and loading docks, office spaces, data hall computer rack and technology and electrical distribution.
Status
Review Complete
Design firm
(972) 934-8888
Location
501 Austin Blvd, Ellis County, Texas
County
Ellis
TDLR project
Vallies ELT-1
Facility
Compass Data Center
Owner
Vallies LLC
Estimated cost
$64,000,000
Square footage
5,000
Type of work
Renovation/Alteration
Scope
tenant fit out of data hall space, supporting infrastructure spaces, and tenant office space
Status
Project Registered
Design firm
(214) 969-5599
Location
441 N. Austin Blvd, Ellis County, Texas
County
Ellis
TDLR project
DataBank Red Oak - DFW11 TFO
Facility
DFW11 TFO
Owner
DB Data Center Red Oak, LLC
Estimated cost
$315,000,000
Square footage
221,434
Type of work
Additions to Existing Building
Scope
Interior level 01 & 02 data hall tenant fit out including data rack containment along with tenant storage, and interior level 02 tenant office fit out, along with of level 02 tenant office fit out, along with level 02 tenant storage. 221,434 SF
Status
Project Registered
Design firm
(214) 628-1062
Location
Stainback Rd., Ellis County, Texas
County
Ellis
TDLR project
Sharka Data Center - Phase 2
Facility
Sharka Data Center
Owner
Sharka LLC c/o Corporation Services Co
Estimated cost
$300,000,000
Square footage
300,000
Type of work
New Construction
Scope
2-story Data Center (approx. 281,792 s/f) with associated central utility buildings.
Status
Project Closed
Design firm
(972) 960-4000
Location
3441 Railport Parkway, Ellis County, Texas
County
Ellis
TDLR project
Databank Red Oak - DFW13
Facility
DFW13
Owner
DB Data Center Red Oak, LLC
Estimated cost
$325,000,000
Square footage
425,170
Type of work
New Construction
Scope
New construction, two story data center with office component. 425,170 SF
Status
Project Registered
Design firm
214 628 1062
Location
Stainback Rd,, Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 4 Tenant Fit Out
Facility
DFW III-II Building 4
Owner
Compass Datacenters
Estimated cost
$57,000,000
Square footage
195,000
Type of work
Renovation/Alteration
Scope
Tenant fit out of approximately 195,000 sf of administrative and data hall spaces including renovations to existing building entrance and loading docks, office spaces, data hall computer rack and technology and electrical distribution.
Status
Review Complete
Design firm
(972) 934-8888
Location
541 Austin Blvd, Ellis County, Texas
County
Ellis
TDLR project
DFW III-III Building 6
Facility
Building 6
Owner
COMPASS DATACENTERS DFW IIIF LLC
Estimated cost
$100,000,000
Square footage
251,815
Type of work
New Construction
Scope
Construction of a new data center on a datacenter campus.
Status
Review Complete
Location
500 Austin Bvld, Ellis County, Texas
County
Ellis
TDLR project
MDN Sharka Data Center - Building 3
Facility
Sharka Data Center
Owner
Sharka LLC c/o Corporation Services Co
Estimated cost
$300,000,000
Square footage
288,000
Type of work
New Construction
Scope
New one-story Data Center (approx. 288K sf). Data Center will include Core, Shell and interior FO. Foundations and Pads for remainder of the central utly plant will be installed with this project.
Status
Project Closed
Design firm
(972) 960-4000
Location
3441 Railport Parkway, Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 5
Facility
Building 5
Owner
Compass Datacenters
Estimated cost
$100,000,000
Square footage
251,815
Type of work
New Construction
Scope
Construction of a new data center on a datacenter campus.
Status
Inspection Complete
Location
581 Austin Bvld, Ellis County, Texas
County
Ellis
TDLR project
DFW III-I-1 Thunderball 6000
Facility
DFW III Red Oak, TX
Owner
Compass Datacenters
Estimated cost
$45,000,000
Square footage
40,150
Type of work
New Construction
Scope
New Data Center Building.
Status
Review Complete
Design firm
(617) 430-7192
Location
Houston School Rd N of E Ovilla Rd 1 mile W of I-35E, Ellis County, Texas
County
Ellis
TDLR project
Databank Red Oak - DFW9 TFO
Facility
DFW9
Owner
DB Data Center Red Oak, LLC
Estimated cost
$200,000,000
Square footage
5,500
Type of work
Renovation/Alteration
Scope
Interior data hall tenant fit out including data bank containment and support infrastructure, as well as 5,500 SF of tenant office fit out.
Status
Project Registered
Design firm
(214) 628-1062
Location
Stainback Rd, Ellis County, Texas
County
Ellis
TDLR project
Sharka Data Center - Building 4
Facility
Sharka Data Center
Owner
Sharka LLC c/o Corporation Services Co.
Estimated cost
$350,000,000
Square footage
170,600
Type of work
New Construction
Scope
1-story Data Center with associated central utility buildings.
Status
Project Closed
Design firm
(469) 261-0827
Location
3441 Railport Parkway, Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 3
Facility
Building 3
Owner
Compass Datacenters
Estimated cost
$100,000,000
Square footage
251,815
Type of work
New Construction
Scope
Construction of new data center on a datacenter campus.
Status
Inspection Complete
Location
501 Austin Bvld, Ellis County, Texas
County
Ellis
TDLR project
DFW III-III Building 7
Facility
Building 7
Owner
COMPASS DATACENTERS DFW IIIG LLC
Estimated cost
$100,000,000
Square footage
251,815
Type of work
New Construction
Scope
Construction of a new data center on a datacenter campus.
Status
Review Complete
Location
540 Austin Bvld, Ellis County, Texas
County
Ellis
TDLR project
Compass - Schneider Electric Manufacturing Facility
Facility
Schneider Electric
Owner
Compass Datacenters
Estimated cost
$32,000,000
Square footage
103,200
Type of work
New Construction
Scope
103, 200sf Manufacturing Facility including approx. 10,000sf of built out Office Space.
Status
Inspection Complete
Design firm
(520) 806-0903
Location
371 Tater Brown Road, Ellis County, Texas
County
Ellis
TDLR project
Compass Datacenters DFW III-I, LLC
Facility
DFW III-I
Owner
Compass Datacenters
Estimated cost
$5,000,000
Square footage
980,849
Type of work
New Construction
Scope
Datacenter
Status
Project Closed
Design firm
(214) 801-4936
Location
300 Houston School Road, Ellis County, Texas
County
Ellis
TDLR project
Databank Red Oak - DFW10
Facility
DFW10
Owner
Databank
Estimated cost
$256,000,000
Square footage
425,170
Type of work
New Construction
Scope
New construction, two story data center with office component. 425,170 SF
Status
Project Registered
Design firm
817-929-6997
Location
Stainback Rd, Ellis County, Texas
County
Ellis
TDLR project
Databank Red Oak - DFW9
Facility
DFW9
Owner
Databank
Estimated cost
$256,000,000
Square footage
425,170
Type of work
New Construction
Scope
New construction, two story data center with office component. 425,170 SF
Status
Project Registered
Design firm
(817) 929-6997
Location
Stainback Rd, Ellis County, Texas
County
Ellis
TDLR project
Sharka Data Center - Building 5
Facility
Sharka Data Center - Building 5
Owner
Sharka LLC
Estimated cost
$491,727,252
Square footage
288,000
Type of work
New Construction
Scope
New one-story Data Center: core, shell and interior finish-out with site improvements.
Status
Project Registered
Location
3411 Railport Parkway, Ellis County, Texas
County
Ellis
TDLR project
Databank Red Oak - DFW10 TFO
Facility
DFW10 TFO
Owner
DB Data Center Red Oak, LLC
Estimated cost
$301,000,000
Square footage
221,434
Type of work
Additions to Existing Building
Scope
Interior level 01 & 02 data hall tenant fit out including data rack containment along with tenant storage, and interior level 02 tenant office fit out, along with of level 02 tenant office fit out, along with level 02 tenant storage. 221,434 SF
Status
Project Registered
Design firm
214 628 1062
Location
Stainback Rd, Ellis County, Texas
County
Ellis
TDLR project
Compass Operations Facility
Facility
Compass Operations Facility
Owner
Compass Datacenters DFW III LLC
Estimated cost
$16,925,000
Square footage
50,000
Type of work
New Construction
Scope
A 50,000sqft operations facility that will service the adjacent data centers.
Status
Inspection Complete
Design firm
(770) 712-9873
Location
300 Houston School Rd, Ellis County, Texas
County
Ellis
TDLR project
DataBank Red Oak - DFW12 TFO
Facility
DFW12 TFO
Owner
DB Data Center Red Oak 12, LLC
Estimated cost
$155,000,000
Square footage
221,434
Type of work
Additions to Existing Building
Scope
Interior level 01 & 02 data hall tenant fit out including data rack containment along with tenant storage, and interior level 02 tenant office fit out, along with level 02 tenant storage. 221,434 SF
Status
Project Registered
Design firm
(214) 628-1062
Location
Stainback Rd, Ellis County, Texas
County
Ellis
TDLR project
Databank Red Oak - DFW11
Facility
DFW11
Owner
Databank
Estimated cost
$325,000,000
Square footage
425,170
Type of work
New Construction
Scope
New construction, two story data center with office component. 425,170 SF
Status
Project Registered
Design firm
817-929-6997
Location
Stainback Rd, Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 2 (Roadrunner)
Facility
Roadrunner Bldg 2
Owner
Compass Datacenters
Estimated cost
$100,000,000
Square footage
251,815
Type of work
New Construction
Scope
Construction of a new datacenter on a data center campus
Status
Inspection Complete
Design firm
(617) 548-2334
Location
481 Austin Blvd, Ellis County, Texas
County
Ellis
TDLR project
AREP Power House Grand Prairie
Facility
Data Center Building 1
Owner
Prairie Ridge Phase 1 Owner LP
Estimated cost
$72,590,278
Square footage
224,152
Type of work
New Construction
Scope
224,152 sf two story single tenant computer data center core and shell build out.
Status
Project Registered
Design firm
908 723 8666
Location
881 Miller Road, Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 4
Facility
Building 4
Owner
Compass Datacenters
Estimated cost
$100,000,000
Square footage
251,815
Type of work
New Construction
Scope
Construction of a new data center building on a datacenter campus.
Status
Review Complete
Location
541 Austin Bvld, Ellis County, Texas
County
Ellis
TDLR project
RED1A
Facility
RED1A
Owner
Google
Estimated cost
$176,000,000
Square footage
170,594
Type of work
New Construction
Scope
New ground-up data center project. 170,594.00 sq ft
Status
Review Complete
Design firm
214-757-1613
Location
330 N. Austin Blvd., Ellis County, Texas
County
Ellis
TDLR project
DFW III-II Building 1 Tenant Fit Out
Facility
DFW III-II Building 1
Owner
Compass Data Centers
Estimated cost
$57,000,000
Square footage
195,000
Type of work
Renovation/Alteration
Scope
Tenant fit out of administrative and data hall spaces including renovations to existing building entrance and loading docks, office spaces, data hall computer rack and technology and electrical distribution.
Status
Review Complete
Design firm
(972) 934-8888
Location
441 Austin Blvd., Ellis County, Texas
County
Ellis
TDLR project
DataBank Red Oak - DFW14 Base Building
Facility
DB DFW14
Owner
DB Data Center Red Oak, LLC
Estimated cost
$325,000,000
Square footage
443,679
Type of work
New Construction
Scope
New Construction, two story data center with office component. 443,679 SF
Status
Project Registered
Design firm
(214) 628-1062
Location
3600 Batchler Rd, Ellis County, Texas
County
Ellis
Queue capacity (Gas)
54 MW
Queue capacity (Other)
2,982.22 MW
Queue capacity (Solar)
1,505.07 MW
  • Tax-program registration, not operating status.

Water records

Full water records (public feeds)
Groundwater conservation district
PRAIRIELANDS GROUNDWATER CONSERVATION DISTRICT

Politics records

School district
Ferris Independent School District
Students
2,877
Assessed value
$1,525,068,655
School district
Midlothian Independent School District
Students
11,103
Assessed value
$14,387,075,117
School district
Red Oak Independent School District
Students
6,592
Assessed value
$5,794,440,489
School district
Waxahachie Independent School District
Students
11,052
Assessed value
$11,294,840,302
State House
District 10 — Brian Harrison (R)
State Senate
District 2 — Bob Hall (R)
State Senate
District 22 — Brian Birdwell (R)
Congressional
District 6 — Jake Ellzey (R)
Top taxpayers
Subscribe to see
M&O collections
Subscribe to see
Per-student spend
Subscribe to see
Median household income
Subscribe to see
Top industries
Subscribe to see
Population
Subscribe to see
  • School-district economics (annual) are shown for Red Oak Independent School District (most cert sites); 3 other districts on record.

Sources: Texas Geographic Information Office · Texas Comptroller · Texas Department of Licensing and Regulation · Texas Water Development Board · ERCOT

Frequently asked questions

How many data center projects does Ellis County have in public records?

Ellis County has 10 Comptroller-certified data-center sites and 32 TDLR construction filings in the public feeds this atlas tracks.

What is the largest TDLR data-center filing cost on record in Ellis County?

Sharka Data Center - Building 5 lists an estimated cost of $491,727,252 in TDLR public records for Ellis County.

Which groundwater districts appear at known Ellis County data-center sites?

Public records for known project locations name PRAIRIELANDS GROUNDWATER CONSERVATION DISTRICT. District boundaries do not follow county lines, so this is point-derived, not whole-county coverage.

Annual subscriber data

Ellis County — locked fields

The free brief and map above name public projects and county-level jurisdictions. Annual access unlocks who governs a specific pin on the map and fills the tax-base fields below.

School district

  • Top taxpayersAnnual
  • M&O collectionsAnnual
  • Per-student spendAnnual

County

  • Median household incomeAnnual
  • Top industriesAnnual
  • PopulationAnnual

Subscribe annually for pin-level jurisdictions on the county map (who governs a specific site) plus school-district tax-base fields (top taxpayers, M&O, per-pupil)

View annual plans