Data Centers in Armstrong County

Under construction

Armstrong County hosts 1 Comptroller-certified site and 10 TDLR construction filings Projects touch 1 school district (Claude Independent School District). U.S. House seats in the record: District 13. Free brief: power, water, and politics from those records. Annual unlocks school-district tax-base fields (top taxpayers, M&O, per-pupil) and who governs a specific pin on the map.

Power

Armstrong County power records from Comptroller certificates and TDLR filings. Certified names in the public record include Project Goodnight. TDLR project names include Llano Building 1, Project Llano, Project Llano, Llano Building 2, Project Llano, Project Llano, and 4 more. Project Llano lists an estimated cost of $500,000,000. Nearby ERCOT queue capacity summarized by fuel includes 1,703 MW Wind; 1,043 MW Other; 504 MW Solar. Approximate sites stay county-level when geocode quality does not support a precise city.

Water

Water at project locations (not whole-county coverage). Known sites name PANHANDLE GROUNDWATER CONSERVATION DISTRICT. District boundaries do not follow county lines.

Politics

Armstrong County siting records (not a full voter guide). School districts appearing on certified or filed sites include Claude Independent School District. U.S. House districts in the record: District 13 — Ronny Jackson (R). State House: District 86 — John T. Smithee (R). State Senate: District 31 — Kevin Sparks (R). Commissioners court agendas run via custom (2nd Monday 9:00 a.m. — Armstrong County Courthouse, 101 Trice St., Claude). Tax-base fields (top taxpayers, M&O, per-pupil) stay annual-only. Pin-level “who governs this parcel” is annual on the map.

Loading map…

Power records

Full power records (public feeds)
Certified site
Project Goodnight
Occupant
GN DC1, LLC
Certificate type
large
Nearest city
Claude
TDLR project
Llano Building 1
Facility
Llano Building 1
Owner
GN DC1 LLC
Estimated cost
$292,000,000
Square footage
484,954
Type of work
New Construction
Scope
New approx. 484,954 SF 1 story Data Center. New approx. 300 SF Guard House. New approx. 2,400 SF Fire Pump building. Various mechanical and electrical enclosures on the site.
Status
Review Complete
Design firm
(714) 639-9860
Location
10001 Lima Rd, Armstrong County, Texas
County
Armstrong
TDLR project
Project Llano
Facility
Building 1 TI
Owner
GN DC1 LLC
Estimated cost
$500,000,000
Square footage
484,965
Type of work
New Construction
Scope
Single-story data center. The architectural interior build-out will include four data halls and associated office support spaces.
Status
Review Complete
Design firm
(214) 969-3065
Location
10001 Lima Road, Armstrong County, Texas
County
Armstrong
TDLR project
Project Llano
Facility
Building 4
Owner
GN DC1, LLC
Estimated cost
$500,000,000
Square footage
805,380
Type of work
New Construction
Scope
Single story Data Center approximately 805,380 sf, constructed of structural steel columns, beams and framing, insulated metal panels, and glazed curtain wall. It will include office space, multiple data halls and associated support spaces.
Status
Review Complete
Design firm
(241)969-3065
Location
10001 Lima Road, Armstrong County, Texas
County
Armstrong
TDLR project
Llano Building 2
Facility
Llano Building 2
Owner
GN DC1 LLC
Estimated cost
$292,000,000
Square footage
484,954
Type of work
New Construction
Scope
New approx. 484,954 SF 1 story Data Center.
Status
Project Registered
Design firm
(714) 639-9860
Location
10001 Lima Rd, Armstrong County, Texas
County
Armstrong
TDLR project
Project Llano
Facility
Building 5
Owner
GN DC1, LLC
Estimated cost
$500,000,000
Square footage
805,380
Type of work
New Construction
Scope
Single story Data Center approximately 805,380 sf, constructed of structural steel columns, beams and framing, insulated metal panels, and glazed curtain wall. It will include office space, multiple data halls and associated support spaces.
Status
Project Registered
Design firm
(214)969-3065
Location
10001 Lima Road, Armstrong County, Texas
County
Armstrong
TDLR project
Project Llano
Facility
Building 6
Owner
GN DC1, LLC
Estimated cost
$500,000,000
Square footage
805,380
Type of work
New Construction
Scope
Single story Data Center approximately 805,380 sf, constructed of structural steel columns, beams and framing, insulated metal panels, and glazed curtain wall. It will include office space, multiple data halls and associated support spaces.
Status
Project Registered
Design firm
(214)969-3065
Location
10001 Lima Road, Armstrong County, Texas
County
Armstrong
TDLR project
Llano Building 3
Facility
Llano Building 3
Owner
GN DC1 LLC
Estimated cost
$500,000,000
Square footage
805,308
Type of work
New Construction
Scope
An approximately 805,380 square foot single story data center constructed with structural steel columns, beams and framing. It will contain office space, multiple data halls and associated support spaces.
Status
Project Registered
Location
10001 Lima Rd, Armstrong County, Texas
County
Armstrong
TDLR project
Llano Building 4
Facility
Llano Building 4
Owner
GN DC1 LLC
Estimated cost
$500,000,000
Square footage
805,308
Type of work
New Construction
Scope
New construction of approximately 805,380 square feet single story data center constructed of steel columns, beams and framing and containing office space, data halls and associated support area.
Status
Project Registered
Location
10001 Lima Rd, Armstrong County, Texas
County
Armstrong
TDLR project
Project Llano
Facility
Building 2 TI
Owner
GN DC1 LLC
Estimated cost
$500,000,000
Square footage
484,954
Type of work
New Construction
Scope
Single-story data center. The architectural interior build-out will include four data halls and associated office support spaces.
Status
Review Complete
Design firm
(214) 969-3065
Location
10001 Lima Road, Armstrong County, Texas
County
Armstrong
TDLR project
Project Llano
Facility
Building 3
Owner
GN DC1, LLC
Estimated cost
$500,000,000
Square footage
805,380
Type of work
New Construction
Scope
Single story Data Center approximately 805,380 sf, constructed of structural steel columns, beams and framing, insulated metal panels, and glazed curtain wall. It will include office space, multiple data halls and associated support spaces.
Status
Review Complete
Design firm
(241)969-3065
Location
10001 Lima Road, Armstrong County, Texas
County
Armstrong
Queue capacity (Other)
1,043.08 MW
Queue capacity (Solar)
503.56 MW
Queue capacity (Wind)
1,703.2 MW

Water records

Full water records (public feeds)
Groundwater conservation district
PANHANDLE GROUNDWATER CONSERVATION DISTRICT

Politics records

School district
Claude Independent School District
Students
319
Assessed value
$633,231,090
State House
District 86 — John T. Smithee (R)
State Senate
District 31 — Kevin Sparks (R)
Congressional
District 13 — Ronny Jackson (R)
Portal platform
custom
Agenda portal
https://www.co.armstrong.tx.us/page/armstrong.Commissioners.Court
Meeting schedule
2nd Monday 9:00 a.m. — Armstrong County Courthouse, 101 Trice St., Claude
Top taxpayers
Subscribe to see
M&O collections
Subscribe to see
Per-student spend
Subscribe to see
Median household income
Subscribe to see
Top industries
Subscribe to see
Population
Subscribe to see

Sources: Texas Geographic Information Office · Texas Comptroller · Texas Department of Licensing and Regulation · Texas Water Development Board · ERCOT

Frequently asked questions

How many data center projects does Armstrong County have in public records?

Armstrong County has 1 Comptroller-certified data-center site and 10 TDLR construction filings in the public feeds this atlas tracks.

What is the largest TDLR data-center filing cost on record in Armstrong County?

Project Llano lists an estimated cost of $500,000,000 in TDLR public records for Armstrong County.

Which groundwater districts appear at known Armstrong County data-center sites?

Public records for known project locations name PANHANDLE GROUNDWATER CONSERVATION DISTRICT. District boundaries do not follow county lines, so this is point-derived, not whole-county coverage.

When does Armstrong County Commissioners Court meet?

Armstrong County Commissioners Court schedule in this atlas: 2nd Monday 9:00 a.m. — Armstrong County Courthouse, 101 Trice St., Claude Agendas via custom.

Annual subscriber data

Armstrong County — locked fields

The free brief and map above name public projects and county-level jurisdictions. Annual access unlocks who governs a specific pin on the map and fills the tax-base fields below.

School district

  • Top taxpayersAnnual
  • M&O collectionsAnnual
  • Per-student spendAnnual

County

  • Median household incomeAnnual
  • Top industriesAnnual
  • PopulationAnnual

Subscribe annually for pin-level jurisdictions on the county map (who governs a specific site) plus school-district tax-base fields (top taxpayers, M&O, per-pupil)

View annual plans