Data Centers in Bell County

Under construction

Bell County hosts 5 Comptroller-certified sites and 11 TDLR construction filings Projects touch 3 school districts (Belton Independent School District, Killeen Independent School District, and Temple Independent School District). U.S. House seats in the record: District 11 and District 31. Free brief: power, water, and politics from those records. Annual unlocks school-district tax-base fields (top taxpayers, M&O, per-pupil) and who governs a specific pin on the map.

Power

Bell County power records from Comptroller certificates and TDLR filings. Certified names in the public record include Stampede Data Center, Polmer LLC Data Center, Temple Data Center, Temple Green Data Center, and Rhodium Temple. TDLR project names include 5MW Temple Data Center, Project Bell, Project Pasca, Temple Data Center NCB, TTX Data Center, BSW STC Renovation-Universal Care Unit, and 5 more. Project Pasca lists an estimated cost of $880,000,000. Nearby ERCOT queue capacity summarized by fuel includes 1,539 MW Other; 942 MW Gas; 922 MW Solar. Approximate sites stay county-level when geocode quality does not support a precise city.

Water

Water at project locations (not whole-county coverage). Known sites name CLEARWATER UNDERGROUND WATER CONSERVATION DISTRICT. For some sites, enrichment has not yet determined GCD status. District boundaries do not follow county lines.

Politics

Bell County siting records (not a full voter guide). School districts appearing on certified or filed sites include Belton Independent School District, Killeen Independent School District, and Temple Independent School District. U.S. House districts in the record: District 11 — August Pfluger (R); District 31 — John Carter (R). State House: District 54 — Brad Buckley (R); District 55 — Hillary Hickland (R). State Senate: District 24 — Pete Flores (R). Tax-base fields (top taxpayers, M&O, per-pupil) stay annual-only. Pin-level “who governs this parcel” is annual on the map.

Loading map…

Power records

Full power records (public feeds)
Certified site
Stampede Data Center
Occupant
Polmer LLC
Certificate type
large
City
Temple
Certified site
Polmer LLC Data Center
Occupant
Polmer LLC
Certificate type
large
City
Temple
Certified site
Temple Data Center
Occupant
Polmer LLC
Certificate type
large
City
Temple
Certified site
Temple Green Data Center
Occupant
Rhodium Renewables LLC
Certificate type
qualifying
City
Temple
Certified site
Rhodium Temple
Opening year
2021
TDLR project
5MW Temple Data Center
Facility
5MW Data Center
Owner
Oppidan
Estimated cost
$31,000,000
Square footage
61,554
Type of work
New Construction
Scope
A new 61,5191 MW data center including construction of new exterior and interior partitions, ceilings, finishes, mechanical, electrical, plumbing, and fire protection. Also, includes site work, data hall #1, admin. area, and tilt-wall panels.
Status
Review Complete
Design firm
206-294-7536
Location
2313 Eberhardt Road, Bell County, Texas
County
Bell
TDLR project
Project Bell
Facility
Project Bell
Owner
Amazon.com Services, LLC
Estimated cost
$25,000,000
Square footage
135,000
Type of work
New Construction
Scope
New Concrete Tilt-Up Delivery Station w/ Supporting Offices and On-Site Ancillary Structures
Status
Inspection Complete
Design firm
216-491-9300
Location
849 Elm Grove Spur, Bell County, Texas
County
Bell
TDLR project
Project Pasca
Facility
Project Pasca
Owner
Meta
Estimated cost
$880,000,000
Square footage
701,631
Type of work
New Construction
Scope
Data Center
Status
Inspection Complete
Design firm
(682) 990-8825
Location
3101 Industrial Blvd., Building A, Bell County, Texas
County
Bell
TDLR project
Temple Data Center NCB
Facility
Temple Data Center NCB
Owner
Polmer LLC
Estimated cost
$300,000
Square footage
40,000
Type of work
New Construction
Scope
New Project Consisting of Pre-Engineered Metal Building for Construction Administrative Service.
Status
Project Closed
Design firm
(512) 804-1210
Location
3101 Industrial Blvd, Bell County, Texas
County
Bell
TDLR project
TTX Data Center
Facility
Guard House
Owner
Polmer, LLC
Estimated cost
$500,000
Square footage
312
Type of work
Additions to Existing Building
Scope
Construction of a new pre-cast concrete guardhouse with slab-on-grade foundation.
Status
Project Closed
Design firm
(512) 472-1111
Location
3101 Industrial Boulevard, Bell County, Texas
County
Bell
TDLR project
BSW STC Renovation-Universal Care Unit
Facility
Baylor Scott and White Medical Center - Temple
Owner
Deborah Arizmendi
Estimated cost
$6,000,000
Square footage
15,000
Type of work
Renovation/Alteration
Scope
2 phases including Level 1 renovation for an Inpatient Universal Care wing and Level G electrical transfer switch room.
Status
Project Closed
Design firm
(512) 472-6721
Location
2401 South 31st Street, Bell County, Texas
County
Bell
TDLR project
COMPUTER ROOM MODIFICATION AND HVAC SYSTEM UPGRADE
Facility
BAYLOR SCOTT & WHITE HOSPITAL
Owner
Baylor Scott & White
Estimated cost
$7,100,000
Square footage
6,407
Type of work
Renovation/Alteration
Scope
Renovation of interior space to accommodate data room expansion. Renovation includes removing non load bearing walls, install new walls, doors, electrical equipment and hvac equipment.
Status
Project Closed
Location
2401 S.31ST STREET, Bell County, Texas
County
Bell
TDLR project
Temple Data Center
Facility
TTX03
Owner
Polmer LLC
Estimated cost
$197,000,000
Square footage
145,000
Type of work
New Construction
Scope
145,177SF Single Story Data Center Building
Status
Project Registered
Location
2230 Eberhardt Rd, Bell County, Texas
County
Bell
TDLR project
T5 - Killeen, TX
Facility
Take 5 Oil Change
Owner
Take 5 Oil Change
Estimated cost
$400,000
Square footage
1,430
Type of work
New Construction
Scope
New Construction of a Take 5 Oil Change
Status
Project Closed
Design firm
(972) 750-0493
Location
3600 W. Stan Schlueter Loop, Bell County, Texas
County
Bell
TDLR project
Temple Data Center
Facility
Temple Data Center
Owner
Temple Green Data LLC
Estimated cost
$70,000,000
Square footage
133,274
Type of work
New Construction
Scope
Development includes three interconnected Powered Shells primarily intended to store miners equipment equipped with immersion cooling system.
Status
Project Closed
Design firm
(469) 659-7194
Location
2810 Bob White Road, Bell County, Texas
County
Bell
TDLR project
AUS02
Facility
AUS02 (Building 2)
Owner
Rowan Digital Infrastructure
Estimated cost
$780,000,000
Square footage
500,000
Type of work
New Construction
Scope
New construction of a 1 story steel frame and non-loading precast with low slope membrane roof system to support and house data center storage and facility support spaces.
Status
Project Registered
Location
1855 Bob White Road, Bell County, Texas
County
Bell
Queue capacity (Gas)
941.8 MW
Queue capacity (Other)
1,539.42 MW
Queue capacity (Solar)
921.51 MW
  • Approximate location — county level.

Water records

Full water records (public feeds)
Groundwater conservation district
CLEARWATER UNDERGROUND WATER CONSERVATION DISTRICT
Groundwater conservation district
Not determined.

Politics records

School district
Belton Independent School District
Students
13,808
Assessed value
$9,848,993,144
School district
Killeen Independent School District
Students
43,864
Assessed value
$20,095,581,247
School district
Temple Independent School District
Students
8,784
Assessed value
$9,182,756,683
State House
District 54 — Brad Buckley (R)
State House
District 55 — Hillary Hickland (R)
State Senate
District 24 — Pete Flores (R)
Congressional
District 11 — August Pfluger (R)
Congressional
District 31 — John Carter (R)
Top taxpayers
Subscribe to see
M&O collections
Subscribe to see
Per-student spend
Subscribe to see
Median household income
Subscribe to see
Top industries
Subscribe to see
Population
Subscribe to see
  • School-district economics (annual) are shown for Temple Independent School District (most cert sites); 2 other districts on record.

Sources: Texas Geographic Information Office · Texas Comptroller · Texas Department of Licensing and Regulation · Texas Water Development Board · ERCOT

Frequently asked questions

How many data center projects does Bell County have in public records?

Bell County has 5 Comptroller-certified data-center sites and 11 TDLR construction filings in the public feeds this atlas tracks.

What is the largest TDLR data-center filing cost on record in Bell County?

Project Pasca lists an estimated cost of $880,000,000 in TDLR public records for Bell County.

Which groundwater districts appear at known Bell County data-center sites?

Public records for known project locations name CLEARWATER UNDERGROUND WATER CONSERVATION DISTRICT. District boundaries do not follow county lines, so this is point-derived, not whole-county coverage.

Annual subscriber data

Bell County — locked fields

The free brief and map above name public projects and county-level jurisdictions. Annual access unlocks who governs a specific pin on the map and fills the tax-base fields below.

School district

  • Top taxpayersAnnual
  • M&O collectionsAnnual
  • Per-student spendAnnual

County

  • Median household incomeAnnual
  • Top industriesAnnual
  • PopulationAnnual

Subscribe annually for pin-level jurisdictions on the county map (who governs a specific site) plus school-district tax-base fields (top taxpayers, M&O, per-pupil)

View annual plans