Data Centers in Childress County

Under construction

Childress County hosts 3 Comptroller-certified sites and 2 TDLR construction filings Projects touch 1 school district (Childress Independent School District). U.S. House seats in the record: District 13. Free brief: power, water, and politics from those records. Annual unlocks school-district tax-base fields (top taxpayers, M&O, per-pupil) and who governs a specific pin on the map.

Power

Childress County power records from Comptroller certificates and TDLR filings. Certified names in the public record include Lancium Clean Campus - Childress 1, Childress Data Center, and IREN / Iris Energy Childress. TDLR project names include Childress Data Center Campus Upgrades and Iris - Childress Data Center. Childress Data Center Campus Upgrades lists an estimated cost of $15,000,000. Nearby ERCOT queue capacity summarized by fuel includes 503 MW Solar; 100 MW Other. Approximate sites stay county-level when geocode quality does not support a precise city.

Water

Water at project locations (not whole-county coverage). Known sites name GATEWAY GROUNDWATER CONSERVATION DISTRICT. For some sites, enrichment has not yet determined GCD status. District boundaries do not follow county lines.

Politics

Childress County siting records (not a full voter guide). School districts appearing on certified or filed sites include Childress Independent School District. U.S. House districts in the record: District 13 — Ronny Jackson (R). State House: District 88 — Ken King (R). State Senate: District 28 — Charles Perry (R). Tax-base fields (top taxpayers, M&O, per-pupil) stay annual-only. Pin-level “who governs this parcel” is annual on the map.

Loading map…

Power records

Full power records (public feeds)
Certified site
Lancium Clean Campus - Childress 1
Occupant
Lancium LLC
Certificate type
large
Certified site
Childress Data Center
Occupant
IE US Hardware 4 Inc.
Certificate type
large
Certified site
IREN / Iris Energy Childress
Opening year
2023
TDLR project
Childress Data Center Campus Upgrades
Facility
Childress Operations Building
Owner
IE US Development Holdings 3 Inc
Estimated cost
$15,000,000
Square footage
29,000
Type of work
New Construction
Scope
29,000 SF office building
Status
Review Complete
Design firm
512-658-0205
Location
620 FM 1033, Childress County, Texas
County
Childress
TDLR project
Iris - Childress Data Center
Facility
Office Building
Owner
IE US Development Holdings 3 Inc.
Estimated cost
$3,863,400
Square footage
14,964
Type of work
New Construction
Scope
Ground up construction of 14,964 SF one story pre-engineered metal building. The use will comprise of Group B occupancy for office, professional or service-type transactions, including storage of records and accounts.
Status
Inspection Complete
Design firm
(832) 299-4844
Location
620 FM 1033, Childress County, Texas
County
Childress
Queue capacity (Other)
100 MW
Queue capacity (Solar)
502.58 MW
  • Approximate location — county level.

Water records

Full water records (public feeds)
Groundwater conservation district
GATEWAY GROUNDWATER CONSERVATION DISTRICT
Groundwater conservation district
Not determined.

Politics records

School district
Childress Independent School District
Students
976
Assessed value
$796,093,757
State House
District 88 — Ken King (R)
State Senate
District 28 — Charles Perry (R)
Congressional
District 13 — Ronny Jackson (R)
Top taxpayers
Subscribe to see
M&O collections
Subscribe to see
Per-student spend
Subscribe to see
Median household income
Subscribe to see
Top industries
Subscribe to see
Population
Subscribe to see

Sources: Texas Geographic Information Office · Texas Comptroller · Texas Department of Licensing and Regulation · Texas Water Development Board · ERCOT

Frequently asked questions

How many data center projects does Childress County have in public records?

Childress County has 3 Comptroller-certified data-center sites and 2 TDLR construction filings in the public feeds this atlas tracks.

What is the largest TDLR data-center filing cost on record in Childress County?

Childress Data Center Campus Upgrades lists an estimated cost of $15,000,000 in TDLR public records for Childress County.

Which groundwater districts appear at known Childress County data-center sites?

Public records for known project locations name GATEWAY GROUNDWATER CONSERVATION DISTRICT. District boundaries do not follow county lines, so this is point-derived, not whole-county coverage.

Annual subscriber data

Childress County — locked fields

The free brief and map above name public projects and county-level jurisdictions. Annual access unlocks who governs a specific pin on the map and fills the tax-base fields below.

School district

  • Top taxpayersAnnual
  • M&O collectionsAnnual
  • Per-student spendAnnual

County

  • Median household incomeAnnual
  • Top industriesAnnual
  • PopulationAnnual

Subscribe annually for pin-level jurisdictions on the county map (who governs a specific site) plus school-district tax-base fields (top taxpayers, M&O, per-pupil)

View annual plans