Stargate Stalls at 1.2 GW While Iren Quietly Builds 2.75

Oracle and OpenAI's 2 GW Abilene expansion is dead, killed by financing fractures that cut OpenAI's projected compute spend from $1.4 trillion to $600 billion. While Stargate's stalled at 1.2 GW, Iren's already got 2.75 GW under development across Childress and Sweetwater, and it's just getting started.

Today's Lead

Oracle and OpenAI have killed expansion plans for their flagship Stargate campus in Abilene, Texas, capping the site at its original 1.2 GW footprint and abandoning the planned 2 GW second phase. The cancellation exposes financing fractures across the $500 billion Stargate joint venture: OpenAI's projected compute spend through 2030 has dropped to roughly $600 billion, down from $1.4 trillion; Oracle is straining under debt and planning layoffs; and SoftBank is scrambling for $40 billion in loans. Nvidia has stepped in with a reported $150 million deposit to Crusoe Energy to secure remaining Abilene capacity and is negotiating with Meta to absorb the excess, a move designed to block rival chips from occupying the infrastructure.

Power

Iren's 2.75 GW Texas Buildout Quietly Dwarfs Stargate's Stalled Ambitions

While Stargate grabs headlines for shrinking, Iren (formerly Iris Energy) is scaling aggressively. The company has secured 50,000+ Nvidia B300 GPUs, tripling its fleet to 150,000 units by year-end, backed by a $9.7 billion Microsoft cloud capacity deal signed in November 2025. Iren's Texas footprint alone is massive: a completed 750 MW facility in Childress plus a 2 GW project under construction in Sweetwater, totaling 2.75 GW across two West Texas sites.

Add a 1.6 GW Oklahoma project planned nearby, and Iren is quietly assembling one of the largest datacenter power portfolios in the country. The company raised $9.3 billion in eight months through customer prepayments, convertible notes, and GPU financing. But the capital structure carries real execution risk: $2 billion in convertible bond issuance and heavy dependence on Microsoft prepayments create vulnerability if AI demand softens. ERCOT interconnection status for neither Texas project has been disclosed, a critical gap given the batch study process now managing 200+ GW of requests.

Politics

White House Ratepayer Pledge, Big Signatures, No Teeth

Amazon, Google, Meta, Microsoft, OpenAI, Oracle, and xAI signed Trump's Ratepayer Protection Pledge this week, committing to fund their own power generation, cover grid upgrade costs, and negotiate separate rate structures with utilities. The political framing is clear: remove community opposition to datacenter siting by promising residents won't foot the bill. Nationwide utility bills have already risen an average of 8%, and MIT projects datacenter consumption will hit 1,050 terawatt-hours in 2026.

The pledge is non-binding. No enforcement mechanism, no capacity commitments, no timelines, no fuel restrictions. Companies are already building captive gas generation regardless of any White House agreement; JLL documented four central Ohio operators planning dedicated gas plants or fuel cells as of August 2025. Memphis Light, Gas and Water CEO Doug McGowen endorsed the pledge's alignment with existing MLGW practices, but the real test comes when state utility commissions scrutinize microgrid siting and rate structures. xAI's Memphis-Southaven footprint alone already exceeds 1 GW and is projected to double by year-end, fed by a gas plant at the former Duke Energy site.

Bottom line: the pledge is political cover, not policy. Watch state regulatory filings for whether any utility commission converts these voluntary commitments into binding conditions.

Water

Abilene's Closed-Loop Claims Need Scrutiny, Montana Draws 5M Gallon Projections

Crusoe Energy SVP Jamie McGrath told Abilene leaders the Stargate One campus operates a closed-loop cooling system: water filled once, then recirculated with "relatively no loss." That language warrants skepticism. No permit details, daily consumption figures, or aquifer impact assessments have been disclosed for a site operating in semi-arid West Texas.

Meanwhile, in Jefferson County, Montana, Thunderhead Energy Solutions is pursuing Clean Air Act exemptions for a 500 MW behind-the-meter datacenter targeting classified government AI workloads. At a March 4 Helena forum attended by 80+ residents, Boulder resident Mary Eder cited projections of five million gallons daily for some datacenter facilities. The Michigan story adds another data point: Solstice Data's proposed 26 MW Allen Park facility would consume over 3 million gallons annually, and the Allen Park Planning Commission has now delayed twice over municipal water capacity concerns.

Three states, three water fights, all at different scales. Texas operators should note: community opposition is increasingly anchored in specific water consumption data, not abstract concern. The absence of publicly disclosed water figures for major Texas sites like Abilene, Childress, and Sweetwater creates an information vacuum that opponents will fill.

Bottom line: operators who don't proactively disclose water data are handing ammunition to organized opposition.

Politics

Community Opposition Is Professionalizing Fast

The Coalition to Protect Prince William County, Virginia, founded by Elena Schlossberg and Karen Sheehan, has spent a decade building a playbook that grassroots groups nationwide are now replicating. Prince William County alone hosts 44 active datacenters with 15 more under construction. The coalition's tactics: document actual water use, employment, and tax revenue versus marketing claims, then organize around the gaps.

The resistance is widespread. Michigan's state legislature is considering moratorium bills. Ohio lawmakers are moving to eliminate datacenter tax breaks. Allen Park residents called for a local six-month moratorium at Thursday's planning commission hearing.

Sheehan says the resistance cycle is compressing: "Getting into the fight that much quicker, that much more effectively." For Texas operators, the takeaway is that permitting timelines now carry community opposition risk that didn't exist two years ago. Transparency and early engagement aren't optional; they're the difference between a 12-month approval and a 36-month fight.

Sources we cited

9 articles across 8 publishers · 184 reviewed today

  • Oracle/OpenAI drop plans to expand flagship Abilene Stargate site, Meta in talks to pick up Crusoe capacity with Nvidia's help
    Mar 6, 2026·Financing challenges and Stargate's changing scope end Texas data center expansion plans Oracle and OpenAI have canceled plans to expand th
  • [2]KTXS
    Construction on Stargate One data center campus set to run through early 2027
    Mar 5, 2026·ABILENE, Texas — Abilene leaders received an update on the Stargate One data center campus, a project described as the city’s largest single
  • AI cloud Iren purchases 50,000 Nvidia B300 GPUs
    Mar 6, 2026·AI cloud company Iren has entered into purchase agreements for more than 50,000 Nvidia B300 GPUs. The new acquisition will bring Iren's fle
  • Will Trump's Ratepayer Protection Pledge lower utility bills?
    Mar 6, 2026·On March 4, President Donald Trump signed a pledge aimed at keeping Americans' utility costs down amid record-setting hyperscale data center
  • Trump pushes tech giants to bear the cost for data center electricity
    Mar 5, 2026·(Reuters) - Google, Microsoft, Meta, Amazon and several artificial intelligence companies signed a pledge at the White House this month to b
  • Factor This finance and project development roundup: Avantus, Pivot, PFIFFNER, Qnetic, Recurrent
    Mar 6, 2026·In this week's roundup of power project financing and development: Avantus secures $300M for solar and storage, Pivot and Microsoft finance
  • Government-linked data center eyes county
    Mar 6, 2026·Digital rendering of a natural gas turbine-powered AI data center, from the website of Thunderhead Energy Solutions. The AI data center wav
  • Data center answers will come from Lansing or Washington: Allen Park official
    Mar 6, 2026·Join more than 7,000+ of your neighbors who already receive our informative, independent reporting on climate, health and the environment in
  • Resisting the Data Center Boom
    Mar 5, 2026·A pattern is unfolding across the United States. Proposals for hyperscale data centers paid for by massive technology companies to support a

Search across 25,000+ tracked articles → coming with paid