Only 22 GW Clear Section 9.5 Under Senate Bill 6 Batch Zero
Section 9.5 cleared 22 GW as banks hold $130B for local approvals and 321 GW of ERCOT applications lack studies. Developers who don't lock Meta's El Paso water offsets and community terms into the stack will carry idle debt past the Nov. 3 ballot.
Today's Lead
Batch Zero, approved by the Public Utility Commission of Texas in June under Senate Bill 6, now studies loads of 75 MW and above together, prices transmission upgrades against real grid headroom, and treats unfinished models and missing site control as stall signals, not queue progress. ERCOT President and CEO Pablo Vegas called it a fundamental shift in how the ISO manages large-load growth.
NATIONAL CONTEXT
Virginia's pipeline is already taking casualties: Balico withdrew an $8.85B Pittsylvania rezoning under organized opposition, and developers abandoned the Prince William Digital Gateway after court invalidation of the supervisory vote. Georgia Power finalized Project Camelot with OpenAI at 3.2 GW on 1,400 acres in Effingham County, the state's largest single-user power deal, while the Public Service Commission stretched staff review 13 days and left the contract redacted until a September 3 summary; U.S. Senator Raphael Warnock called for a construction moratorium pending water, air, and incentive transparency. Heatmap and Embold polling shows local project support collapsing from 43% to 15%, with more than 500 jurisdictions adding severe constraints since the start of 2025 and contested projects hitting a 50% cancellation rate in the first half of 2026. Capital still flows to jurisdictions that keep process open and self-supplied paths viable; Texas remains that destination when developers treat community and ratepayer architecture as sequencing work, not afterthoughts.
Politics
NEW: Hinojosa presses special session as banks gate capital on local approval
Lenders are tightening the same political gate. Seventy-five projects worth $130B were blocked or delayed in Q1 2025, and the six largest banks now require permits and community agreements before construction funding triggers, leaving capital idle until both sides close. A Wisconsin resident's August 31 public comment in PUCT Control No. 58317 Item 60 urged a 3-mile residential buffer, independent review, and binding benefit agreements for three North Richland Hills Iron Horse sites, a signal of friction even though land use sits with the city and Tarrant County, not the Commission.
Bottom line: price community benefit, water offsets, and permit timing into the capital stack before the next local hearing or warehouse draw, or carry idle debt through the Nov. 3, 2026 ballot window.
Power
NEW: Flexible load and private generation buy time while thermal and modular race the queue
SLB's $4.1B Kelvion purchase targets heat rejection and waterless options as racks climb past 100 kW, with combined 2026 revenue aimed at $2B and 2 GW-plus cumulative delivered capacity. QumulusAI tripled GPUs to 3,088 and signed $169.7M in new contracts, yet CEO Michael Maniscalco says the bind is powered space ready on customer clocks, not chips or capital; modular 1 to 3 MW blocks and Crusoe-style prefab are the speed answer.
Bottom line: pair curtailment contracts, private generation, and thermal integration to the same milestone dates as interconnection filings, or miss batches while carrying unenergized GPUs.
Water
UPDATE: El Paso Meta draw meets campaign nullify threat; cooling design is now a siting gate
SLB's Kelvion package adds waterless and hybrid rejection gear aimed at water-constrained counties where open towers draw opposition. Rural conversion pressure continues: Texas Agriculture Commissioner Sid Miller warns paved farmland does not return, with Project Matador, Project Pacifico, and Project Meta cited at 16,000-plus acres combined; that collision stays political for operators who skip offset and benefit terms at filing.
Bottom line: lock closed-loop or waterless design, metered caps, and written offsets before the next county vote, or inherit contract and campaign risk on the same site.
Sources we cited
13 articles across 12 publishers · 549 reviewed today
- ERCOT Puts Texas AI Megawatts to the TestAug 31, 2026·Texas has no shortage of proposed data center megawatts. The harder question is how many of them are real. That distinction is becoming cent…
- [2]CryptoSlateAI data centers are learning the power trick Bitcoin miners mastered firstAug 31, 2026·One of the most promising answers to AI’s electricity problem begins with an almost heretical idea for the tech industry: sometimes the comp…
- The Month in Infrastructure: Going around the gridSep 1, 2026·Texas froze its data center interconnection queue. The Army committed $2.2 billion to reactors that skip the commercial grid entirely. Inves…
- [4]vox.comThe data centers are winningSep 1, 2026·Why the AI buildout (probably) can’t be stopped. In the United States, building a data center now polls roughly as well as abolishing the p…
- Utah planned the world’s biggest data center. Then came the bipartisan pushback.Sep 1, 2026·Sept. 01, 2026, 5:00 a.m. ET | Hansel Valley, Utah As data centers proliferate across the country, amassing space in both …
- Will public backlash kill Virginia’s data center boom?Aug 31, 2026·Virginia has most data centers of any state but support is waning Jim Morrison August 30, 2026// AI-assisted illustration by Miriam Fo…
- Georgia Power drops more details about OpenAI contract. PSC meeting heats up - Columbus Ledger-EnquirerAug 31, 2026·The largest single-user of power in Georgia history will be OpenAI’s 1,400-acre, 3.2-gigawatt Project Camellia data center in Effingham Coun…
- How banks are navigating the AI data center backlashAug 31, 2026·Power-plant engineers like to tell an apocryphal story about going door to door, asking people if it would be OK to put a wind or solar farm…
- Texas governor candidate Hinojosa calls for special session on data centers during El Paso campaign stopAug 31, 2026·Democratic gubernatorial candidate Gina Hinojosa used a Monday campaign stop in El Paso to call for an emergency legislative session to addr…
- PUCT Control No. 58317 Item 60: Concerns about Data Centers planned and in-progress in North Richland HillsAug 31, 2026·Filed with the Public Utility Commission of Texas on 2026-08-31. Control Number: 58317 Item Number: 60 Item Type: PC Utility Type: O Filing …
- SLB’s $4.1B Kelvion Deal Expands AI Data Center PushAug 31, 2026·SLB’s $4.1B Kelvion deal expands its data center business into thermal management as AI drives higher power densities and cooling demands. …
- QumulusAI Scales GPUs, but Powered Capacity Sets the PaceAug 27, 2026·The neocloud’s second-quarter expansion shows how available power, deployable data center space and capital determine whether AI-compute con…
- [13]MyParisTexasAfter years of hardship, Texas agriculture faces a new threat: data centersAug 31, 2026·Data centers and agriculture depend on many of the same resources, such as water, land and electricity, which has some in the industry worri…