Aligned Breaks Ground on $10B, 2 GW Private Power in Shippingport

Aligned's $10B fuel cells put 2 GW on private generation while Maryland's 14 moratoriums and $198B in blocked projects push capital south. Developers locking private generation early, as Crusoe did with 531 MW for Google in Armstrong County, keep schedules others won't once capital sits idle.

Today's Lead

Aligned Data Centers broke ground September 10, 2026 on Project Phoenix, a $10 billion, 2 GW campus on the former Bruce Mansfield coal site in Shippingport, Beaver County, Pennsylvania. The three-facility build runs on dedicated onsite natural-gas fuel-cell generation, so it never enters a regional transmission queue.

Sixty miles east, Homer City Energy Campus flips the sequence: 4.4 GW of new gas generation first, with a proposed Amazon Web Services campus of as many as 39 buildings sized to the power. Texas already concentrates capital on the same private-generation and behind-the-meter logic; queue timing, not nameplate scarcity, is what separates energization dates from carrying cost.

NATIONAL CONTEXT

Out-of-state policy is hardening around cost allocation, disclosure, and local pauses. Sen. Mark Warner (D-VA) pressed the Senate for enforceable datacenter guardrails and called the Ratepayer Protection Act (H.R. 9340), which the House passed 417-3 on September 16, 2026, a starting point that still leaves state adoption optional and unenforced. He is pushing his Data Center Tax Accountability and Disclosure Act to condition accelerated depreciation on binding standards for energy use, water use, setbacks, and community disclosure, and to end NDAs that hide operational data.

Maryland is pricing capital differently. Governor Wes Moore’s September 2026 executive order created the Maryland Data Center Task Force for environmental and ratepayer protections plus mandated community participation; he also committed to work with the Maryland General Assembly in the 2027 session to repeal the 2020 Data Center Sales & Use Tax Exemption. Fourteen moratoriums are already in place across Maryland, and Harford County has an outright ban. Amazon withdrew from Calvert Cliffs after local timelines proved prohibitive, and brokers report capital redirecting to southern and southwestern states where power access and permitting move faster.

Broader opposition is measurable. A Pew Research Center survey published September 22 found 54% of Americans now call data centers bad for the environment (up from 39% in January), 50% cite energy-cost concerns (up from 38%), and 49% worry about local quality of life (up from 30%). Tracking cited in national coverage counts at least 120 projects worth $198B blocked or delayed in the first half of 2026. In Lowndes County, Alabama, Houston-based Cloverleaf Infrastructure is racing a December 31, 2026 clock to lock a 30-year tax abatement for Project Red Clay, a $1.5B hyperscale site, before Alabama's cap falls to 20 years on January 1, 2027; Alabama Power and the Pintlala Water System have not publicly committed, and county politics remain contested.

Husch Blackwell partners flag the moratorium pattern as the wireless-tower era without a federal preemption statute on the horizon. Some pauses rewrite zoning into workable standards; others mask permanent resistance and convert into multi-year carrying-cost traps. Site-selection rigor and early municipal engagement are the difference between a pause that produces a path and a pause that strands posted capital.

Power

Private generation and battery siting now price interconnection speed

Crusoe is developing Google's multi-building AI campus at 10001 Lima Road in Claude, Armstrong County, with construction underway since June 2025 and Crusoe named developer on September 28, 2026. Texas Department of Licensing and Regulation filings show at least six buildings from roughly 485,000 to 805,000 sf; aggregate estimated cost across five tracked buildings exceeds $2.08B, with Building 4 targeting March 2027 and Building 6 July 2027.

Power is locked to Serena’s Goodnight 1 (265.5 MW, operational) and Goodnight 2 (265.5 MW, under construction) for 531 MW of adjacent generation, with surplus returned to the grid when campus load dips. Crusoe says the campus catalyzed Goodnight 2. Capacity and site-power intensity above server draw remain undisclosed, which keeps ERCOT impact opaque until leases and studies catch up.

North American math is the same constraint in different clothes. Mid-2026 capacity sits near 70 GW operating plus 17 GW under construction and more than 200 GW in planning; vacancy has fallen from 6% in 2021 to 1% in 2026. NERC’s latest long-term assessment forecasts 224 GW of summer and 245 GW of winter peak-load growth over the next decade. FTI’s read is blunt: developers without behind-the-meter generation face five- to ten-year schedules while operators who sequence private generation early compress timelines.

A Base Power and Piq Energy case study shows 80 MW of batteries clearing every transmission constraint created by a 100 MW data center near Burleson on Oncor’s system. Chase Dowling, head of market operations at Base Power, puts the reach at 80 to 85 percent of constraints when batteries sit near the strained line; distant curtailment buys roughly half the relief. The blocker is modeling: ERCOT does not yet treat distributed battery fleets at the transmission-substation level, so planners cannot credit the relief or advance interconnection on that basis.

Soltage's Dirk van Ouwerkerk frames the bottleneck as delivery and power quality, not nameplate megawatts, and warns that "you can't build an off-grid grid." Private assets still lean on a century of grid contingency design. New Jersey's $1.07M penalty against DataOne in Vineland on September 22, for 62 natural-gas generators run without required air permits, shows what happens when on-site generation outruns local air process. DataOne disputed the finding and committed to apply; the exposure still lands on the operator, not the utility.

Prepared developers treat battery siting, air permits, and private-generation financing as interconnection inputs, not afterthoughts. Miss the modeling window or the air filing and the carrying cost between capacity availability and energization compounds in quarters, not weeks.

Water

Cooling design and source disclosure are now siting gates

Crusoe designed the Armstrong County campus around closed-loop, non-evaporative liquid cooling so the water footprint stays limited to domestic uses. That choice matters in the Texas Panhandle, where aquifer stress already shapes permitting speed and neighbor acceptance.

Jonathan P. Saunders of Saunders Consigliere PLLC filed an executive brief in PUCT Control No. 58317, Item 92, on September 30, 2026, arguing water consumption carries equal or greater weight than electricity in Texas reviews that face limited supplies, drought, and competing demand. His community-protection framework asks developers to state resources required, quantities, sources, duration, operating conditions, and who bears cost and risk across ownership changes, expansion, and decommissioning.

National coverage is running the same vector. Alabama’s Project Red Clay still lacks a public commitment from the Pintlala Water System. Design coverage notes visual and hydrologic landscaping, including Microsoft’s biomimicry plantings, as tools that cut both viewshed fights and stormwater friction. IDC’s operator survey ranked water-usage reduction near the bottom of resilience priorities, which leaves a gap communities now fill with their own questions.

Developers who arrive with verified offsets, closed-loop specs, and source letters clear hearings faster than those who treat gallons as a later slide. The cost of silence is a conditioned approval, a delayed bond post, or a moratorium clock that keeps capital idle.

Politics

Community screening is moving from pitch decks to dockets

Saunders’s PUCT brief does not approve or reject projects; it hands officials a diagnostic so communities can condition, modify, or deny with a full record. It lands beside federal cost-allocation debate and the House passage of H.R. 9340, and it widens the file past rates into water, noise, backup generation, incentives, cumulative load, and decommissioning security.

Local trust is the binding constraint Latitude Media and national opposition tracking both describe. Jobs-and-taxes pitches are failing in hearings that draw hundreds; Windsor, Colorado’s mayor faced a 300-person room on a project sited just outside municipal control, a boundary pattern Texas county-line deals know well. Sparkfund’s Pier LaFarge, working distributed batteries with Xcel and Google in Minnesota and a deeper playbook in Alabama, argues grid utilization and visible local benefit have to come first.

Design is now a political instrument. Underground and brownfield profiles reduce the “windowless box” attack line; operators who skip aesthetics inherit longer notice-and-comment cycles. Husch Blackwell’s read for developers is operational: engage early on the regulatory pathway, because a moratorium you help write into standards is survivable and a moratorium you ignore becomes a multi-year cash drain with no federal rescue statute coming.

Who files complete answers on ownership, water, power, and closure shapes the questions the next applicant inherits. Capital that waits for the docket to settle will find the standard written without it.

Sources we cited

14 articles across 13 publishers · 592 reviewed today

  • From Coal to Compute: How Pennsylvania Is Rebuilding Power for AI Data Centers
    Sep 30, 2026·Rendering of Aligned Data Centers’ planned 2-GW Project Phoenix campus in Shippingport, Pennsylvania, which will redevelop a legacy industri…
  • The Race for Power: How BTM Solutions are Accelerating Data Center Deployment
    Sep 29, 2026·As hyperscalers, neoclouds and AI-native companies race to deploy increasingly large graphics processing unit (“GPU”) clusters, reliable pow…
  • Crusoe Named Developer of Google AI Data Center Campus in Armstrong County, Texas
    Sep 29, 2026·Construction is advancing on a major Google AI data center campus in Armstrong County, Texas, with Crusoe serving as developer and connectin…
  • Video: On Senate Floor, Sen. Mark Warner Calls for Data Center Guardrails, Urgent Need to Pass AI Security Legislation
    Sep 30, 2026·Earlier today on the US Senate floor, Sen. Mark Warner” called on Congress to enact meaningful protections for communities facing the rapid …
  • What do data centers mean for MD commercial real estate?
    Sep 29, 2026·What do data centers mean for MD commercial real estate? The TierPoint data center, built as a result of the relocation of Baltimore's firs…
  • Across the US, local revolts grow as AI data center boom expands
    Oct 1, 2026·WINDSOR, CO ‒ Julie Cline remembers the moment her small town's data center debate got personal: A longtime friend stopped speaking to her. …
  • ‘I Know I Couldn’t Live Here’: Standing Up to a Data Center in Alabama’s Black Belt
    Oct 1, 2026·This article was featured in the Daily Prospect newsletter. Sign up for it here. Lowndes County is rural and impoverished, and its scars ar…
  • Data Centers Reach the Moratorium Moment
    Sep 29, 2026·The surge in data center development is running into a new constraint: communities that are putting projects on hold while they decide how t…
  • PUCT Control No. 58317 Item 92: Executive Brief — Texas Data Center and Large-Load Development: Community Protection, Siting and Lifecycle Framework
    Sep 30, 2026·Filed with the Public Utility Commission of Texas on 2026-09-30. Control Number: 58317 Item Number: 92 Item Type: PC Utility Type: O Filing …
  • How far can batteries stretch Texas transmission?
    Sep 30, 2026·Chase Dowling, founding power systems engineer at Base Power, on why siting matters more than volume for Texas's data center boom, and what …
  • Grid Capacity Is Becoming the Data Center Bottleneck: Inside Digital Infrastructure
    Sep 30, 2026·In this installment of Inside Digital Infrastructure, Mintz Digital Infrastructure Practice Co-chair Josh Rudin speaks with Dirk van Ouwerke…
  • Data Center On-Site Power Brings Pollution Risks Closer to Home
    Sep 30, 2026·The data center industry’s shift to on-site power generation to overcome grid constraints is creating new environmental compliance challenge…
  • Can Data Center Design Choices Change Public Acceptance?
    Oct 1, 2026·Operators use biomimicry, community co-design, and brownfield redevelopment to reduce the visual impact of data centers and improve local ac…
  • Utilities and Big Tech lost trust. How can they earn it back?
    Sep 30, 2026·From grid utilization to distributed batteries, a look at the new playbook for energy and data centers. The post Utilities and Big Tech lost…