Tuesday, October 6, 2026

Samsung's $1B Joins Helix's $10B Across Power, Wire, and Fiber

Samsung's $1B into Helix's $10B platform lands as PowerHouse takes Taylor annexation to Thursday's council with $1.4B tax revenue through 2046. Developers who lock generation, water offsets, and community packages before that vote and San Antonio's October 15 hearing keep windows others can't recover.

Today's Lead

The buildout has entered a control phase where capital only works when generation, transmission, water, and political permission move on one schedule. Samsung committed $1 billion to KKR-backed Helix Digital Infrastructure, a platform that already holds $10 billion from founding investors and invests across hyperscale campuses, power generation, transmission, and fiber inside a single capital structure.

Taylor's city council votes Thursday on annexation and zoning for the 664-acre Taylor Technology Campus, a 500 MW behind-the-meter proposal from Big Watt Digital and PowerHouse Data Centers with a tenant path to another 500 MW and $5B in projected Williamson County output over two decades. Operators who still fund land first and chase interconnection, cooling offsets, and council conditions later will carry cost between capacity availability and energization while batch positions age.

NATIONAL CONTEXT

Cost-recovery and approval rules outside Texas are hardening into site-selection filters. California's AB 1577, AB 2383, and SB 887 require datacenter developers to cover full incremental electric grid upgrade costs. Massachusetts Governor Maura Healey's Executive Order 658 requires large datacenters with peak demand above 25 MW to fund associated energy infrastructure costs and ratepayer protection mechanisms when stated power obligations aren't met directly.

Alabama's Public Service Commission opened generic proceedings so Alabama Power must show large-load contracts recover incremental costs before approval. Pennsylvania's Public Utility Commission is revisiting ratemaking and emergency load-control rules after PJM flagged severe capacity shortfall. Oregon's POWER Act already drives 29% rate increases for large energy users served by Portland General Electric. Virginia is tightening disclosure, approval, and community-acceptance requirements in the nation's largest datacenter market.

Nearly 400 U.S. cities and towns, plus at least 14 states, are weighing moratoriums or restrictions against more than 1,500 projects in active planning. Oracle's 1.3 GW Project Lighthouse in Port Washington, Wisconsin, needs more than $1 billion in new American Transmission Company infrastructure; regulators withdrew ATC's completeness determination and forced a refile, with Aterio now putting partial power in December 2027 and full capacity in October 2028 against Oracle's second-half 2027 target. TeraWulf took the opposite path in Kentucky, amending its electric service agreement with Kentucky Power on October 5 to double Muskie Data Campus from 500 MW to 1 GW and pull the second phase into the second half of 2029 on existing industrial wires.

Those out-of-state cost-shift statutes and transmission restarts are cautionary inputs for any developer still pricing socialized upgrades or greenfield wire as base case. Capital is already sorting toward jurisdictions and sites where full recovery, private generation timing, and community packages are designed in before study fees post.

Power

Private Generation and Queue Position Set 2028 Delivery

Enverus Intelligence Research projects 25.5 GW of behind-the-meter generation will power new industrial facilities through 2030, with datacenters taking 22.5 GW (88% of the forecast and roughly 36% of expected U.S. datacenter capacity additions). ERCOT is projected to see 5 GW of that BTM demand; PJM expects 7.5 GW.

Meeting industrial BTM load requires about 31.6 GW of new generation capacity, 29.6 GW of it gas-fired, with 62% (19.5 GW) tied to high-confidence projects expected online by 2030. Large-frame combined-cycle plants take up to 80 months to deliver. Reciprocating engines, small- and medium-frame turbines, and fuel cells reach commercial operation in 18 to 24 months and are expected to represent 61% of projected gas-fired BTM capacity, with overbuild factors as low as 1.1x versus 1.5x for large-frame plants.

Morgan Stanley's October 5 analysis forecasts a 32 GW power shortfall by 2028, equal to 34% of the additional electricity planned U.S. datacenters require, even after counting on-site generation and fuel cells. Goldman Sachs raised its year-end 2026 U.S. capacity forecast by 5 GW to 64 GW and cut 2027 by 5 GW to 90 GW, while still projecting 38% demand growth in both years (12 GW and 17 GW). Current installed capacity sits near 62.7 GW.

Self-supplied power costs about $100 to $165 per megawatt-hour versus $90 to $95 for grid supply, per RaboResearch. Meta's ten-year Williams contract for two 200 MW off-grid gas plants on campus is reported at $140 to $160 per megawatt-hour. About 2 GW of off-grid datacenter power is online today, with another 90 GW announced or planned; xAI reportedly brought a campus online in 122 days on self-supplied power while a grid connection takes four to seven years.

ERCOT's interconnection backlog already stretches past 300 GW of pending applications. Crusoe's Google campus in Armstrong County sits adjacent to wind under energy-first siting. TeraWulf's Muskie site on 285 acres in EastPark Industrial Park is a former strip mine, and the added supply uses existing wires rather than new transmission, while Oracle's Project Jupiter in Doña Ana County, New Mexico, still waits on a gas pipeline that is six months behind and has drawn a force majeure notice tied to the related Stargate campus.

Texas Stargate in Abilene is operating but loaded slower than first cuts: Samaritan once projected 600 MW early 2025, Oracle disclosed roughly 200 MW online in April, and by September OpenAI had taken delivery of about 75% of allocated capacity toward 1.2 GW. Nearly 40% of U.S. data center projects scheduled for 2025 completion could miss targets by more than three months, per SynMax. Manufacturers have sold out many major units into 2030; anyone who didn't order large-frame kit in 2024 or early 2025 is already on modular lead times.

Bottom line: firm queue position plus modular private generation on order is the delivery path; vertical building without those two inputs posts capital against energization dates the wire and the factory can't hit.

Water

Cooling Design and Offsets Decide Local Calendars

Taylor's developers say the campus will run closed-loop cooling with 1.6 million gallons of reclaimed water for initial fill and zero potable water permitted. That package is on the table with annexation, setbacks, noise, and community benefits after the team withdrew its original request in early September to renegotiate standards.

Bank of America estimates 75% of a data center's total water consumption happens off-site at power plants rather than in visible cooling towers. Data center water use reached 0.4% of Texas's total in 2025; the Houston Advanced Research Center projects that share could rise to 0.5% to 2.7% by 2030. Datacenter Knowledge flags space cooling as up to 2.9 times more energy-intensive than non-datacenter floor space per EIA figures, which is why evaporative load has become a statutory trigger in local fights.

Microsoft is restoring wetlands and native gardens at 20-plus sites across the U.S. and Germany, including 100 acres of prairie and forest restoration at Mount Pleasant, Wisconsin, tied to stormwater ponds with forebays. The company says it is investing in more than 400 acres of woodland and pollinator prairie restoration in San Antonio. LG Electronics plans its first U.S. chiller manufacturing plant on 43 acres near Windsor, Virginia: a 350,000-square-foot facility slated for first-half 2027 production and more than 150 jobs, part of more than $100 million aimed at North American cooling demand.

Governor Greg Abbott directed TCEQ to pause new datacenter permitting decisions until ERCOT clarifies grid impacts. Separate reporting states the Governor ordered the PUCT to halt approval of new data center grid connections pending a full audit of every project in the interconnection queue. Goldman tied part of its 5 GW 2027 capacity trim to the same directive's ERCOT and Texas Water Development Board audit work. The audit scope, per Linklaters, includes water sourcing and cooling methodology beside tax incentives, generation mix, community commitments, and ownership.

Operators who arrive at council with verified reclaimed-water contracts, closed-loop design, and offset math keep the hearing on jobs and tax base. Operators still shopping cooling after land is under contract watch the calendar slip while posted capital and tenant PCAs burn.

Politics

Taylor votes Thursday, San Antonio's zoning vote is set, and the March pledge still has no dollar figure

Taylor's council will decide annexation and zoning for the campus at 3301 Farm to Market Road 112. Economic projections show $1.4B in gross tax revenue to Taylor between 2027 and 2046, 320 full-time jobs, and 19,350 temporary construction positions. Big Watt and PowerHouse don't own the site yet; they've committed to utility improvements, landscaping buffers, and light, sound, and air-quality standards after pulling the first annexation filing to renegotiate.

Opposition is organized. Locals protested KDC's 220-acre campus approved in March and Blueprint Projects' $1B campus last summer. A citywide ban petition failed, and residents sued in July seeking an election on a temporary moratorium. Fort Worth began planning a data center moratorium set to start early 2027 even as it approved a $10B campus in the same month.

San Antonio's city council rejected a blanket pause and is instead weighing zoning rule changes, with a vote scheduled for October 15. San Antonio District 6 Councilmember Ric Galvan proposed a moratorium in August with Public Citizen backing and flagged more than a dozen existing data centers in his district plus pending proposals. An NBC News poll finds 64% of voters would be less likely to support a candidate backing a local data center, versus 11% more likely.

Google, Meta, Microsoft, Amazon, OpenAI, Oracle, and xAI pledged on March 4, 2026 to procure or build the electricity their campuses need, fund substation and transmission upgrades, and negotiate dedicated utility rates. A White House fact sheet the next day added coverage of reserved generation capacity whether used or not. As of October 5, 2026, none of the seven have disclosed a dollar figure, contract term, or percentage attached to those commitments. Hut 8 CEO Asher Genoot is answering the politics track with campus tours, school-district access, and upfront aesthetic design framed as community assets.

Governor Greg Abbott's audit directive, as described in the Linklaters note, requires documentation of tax incentives and public financial assistance, reliance on grid power versus on-site generation, water sourcing and cooling, community-impact commitments, and ownership structure. The halt does not apply to operating facilities, but it stops forward motion on pending applications while that file is built. Every day positions sit, study capital ages and signed tenant energization windows slip by quarters.

Texas is writing the next round of large-load rules in public view. Developers who show up to Taylor on Thursday and San Antonio on October 15 with complete generation, water, and benefit packages shape the conditions; developers who treat those hearings as someone else's calendar inherit the baseline others file.

Sources we cited

15 articles across 14 publishers · 640 reviewed today

  • AI Infrastructure’s Next Phase: Capital, Power and the Right to Build
    Oct 5, 2026·Crusoe’s Google data center campus under construction in Armstrong County, Texas. The project, directly connected to adjacent wind generatio…
  • Taylor Set To Decide On Annexation, Zoning For Data Center
    Oct 5, 2026·The city of Taylor in metro Austin is gearing up to decide on a 664-acre data center project. The Taylor Technology Campus, proposed for 33…
  • America’s data center boom is running into a grid-sized problem
    Oct 5, 2026·America’s data center boom is moving fast, but the infrastructure needed to power it isn’t always keeping pace. From transmission and fuel c…
  • Beyond the Megawatt: Why Data Center Site Selection Is Now a Three-Front Battle
    Oct 5, 2026·Insight and analysis on the data center space from industry thought leaders. Data center development now requires addressing grid costs, wa…
  • TeraWulf doubles Kentucky data center power deal to a full gigawatt
    Oct 5, 2026·A Bitcoin miner just out-maneuvered Oracle in the race for AI power. TeraWulf locked in a full gigawatt of grid capacity in Kentucky while O…
  • News | Data center growth expected to hold steady in face of project protests
    Oct 6, 2026·U.S. data center capacity growth projections appear to be on track for 2026 and 2027 despite mounting opposition to projects that support th…
  • Data centers are skipping the grid queue — and turning to on-site power
    Oct 5, 2026·Data centers are tired of waiting for the grid. A new forecast shows developers increasingly turning to behind-the-meter generation to get p…
  • AI data center growth won't be slowed down by angry neighbors: Goldman Sachs
    Oct 5, 2026·Your band of angry neighbors is unlikely to stop that data center from going live in 2027, or so posits Goldman Sachs. "While US data cente…
  • Buying Time, Burning Gas
    Oct 5, 2026·Why AI companies are paying a premium to go off the grid (and what this costs the rest of us). The race is on to train the next generation …
  • Power Becomes the Biggest Bottleneck for Data Center Expansion: Which Power Stocks Are Worth Watching?
    Oct 6, 2026·Nvidia’s "five-layer cake" framework highlights energy as the fundamental constraint for artificial intelligence expansion, shifting market …
  • Microsoft using wetlands and native gardens to 'camouflage' 20-plus data center sites by blending them into nature — critics blast the 'biomimicry' effort as 'lipstick on a pig' amid a 20-year gas power deal
    Oct 4, 2026·Critics question motives and advocate for residents’ needs. Microsoft’s “biomimicry” program is reshaping the land around its data centers …
  • USA: Texas Hits Pause on New Data Center Grid Connections, Lauren Bachtel, Nteboheng Mokuena - Linklaters
    Aug 10, 2026·Texas Governor Greg Abbott ordered state utility regulators to stop approving new data center connections to the Texas grid until every proj…
  • Data Center Energy Costs: 7 Signed, $0 Disclosed [2026] - tech-insider.org
    Oct 5, 2026·Seven months after Google, Meta, Microsoft, Amazon, OpenAI, Oracle, and xAI stood behind a White House pledge to keep AI data center costs o…
  • The AI Boom Is Running Out of Earth. Here’s Who Benefits.
    Oct 5, 2026·For the past two years, we’ve spent a lot of time talking about the AI Boom as a semiconductor story. First, the world needed more GPUs. A…