ERCOT Batches Large Loads After Queue Surges 650% to 474 GW

Data centers drive 90% of ERCOT's 474 GW queue into batch studies as California, Nevada, and Virginia stack disclosure rules and Hood County weighs unnamed tax waivers. Developers who secure private generation and county packets before the next window keep interconnection timing others can't recover.

Today's Lead

ERCOT's large-load queue hit 474 GW by June 2025, up from 63 GW at end-2024, a 650% surge in six months with data centers roughly 90% of the backlog. The grid operator paused new permits and moved large customers into batch study because speculative multi-site filings and missing generation experience left planners unable to separate real builds from placeholders. Prepared developers treat Batch Zero as a planning calendar: anchor tenants first, disclose resource use to host counties, and sequence power procurement before the interconnection filing, or carry capital against capacity that never clears.

NATIONAL CONTEXT

Google and Constellation Energy signed a 20-year PPA backing a $4.3B uprate program that adds 890 MW across 11 nuclear units at six PJM sites in Illinois, Pennsylvania, and New Jersey, with first output targeted by 2028 and full additions by end-2032. A separate 15-year supply contract covers 2,700 MW from Constellation's current PJM fleet. Limerick in Pottstown stands to gain 348 MW; Salem in South Jersey adds 97 MW on Constellation's 43% share. Combined with Amazon's 690 MW Calvert Cliffs deal (including a 190 MW uprate), hyperscaler contracts now back roughly 1,080 MW of planned Constellation nuclear uprates through 2032. Watch NRC licensing cadence on the 2028-2032 window; Google's load arrives faster than several of those MW.

Out-of-state governors are writing data-center rules ahead of midterms. California Governor Newsom signed seven data-center bills on September 21 covering special electricity rates plus mandatory energy and water reporting. Nevada Governor Joe Lombardo issued Executive Order EO-2026-005 requiring developers to cover project costs and execute binding Community Support Commitments. Virginia Governor Abigail Spanberger signed an order implementing the Virginia Data Center Accountability Framework, banning nondisclosure agreements and expediting energy and noise rules. New York remains the only state with a full moratorium on state permitting of hyperscale facilities. Virginia State Corporation Commission Commissioner Jehmal Hudson, incoming president of NARUC, is pressing four system questions on who pays, who bears risk, who decides, and when. Capital still prices Texas interconnection speed and private generation optionality against those constraints.

Power

Firm supply is the binding constraint, and private generation is the bridge

McKinsey's Global Energy Perspective 2026 puts data-center electricity demand compounding at 24% annually through 2030, with power supply below IT compute demand in every base case. More than 60% of operators now pair on-site generation with grid access rather than waiting on utility build schedules alone.

At Yotta, the installed mix is already firm-heavy. Goldman lifted its 2026 U.S. data-center capacity forecast to 64 GW and trimmed 2027 to 90 GW; McKinsey sees 17 GW in average annual additions through 2030. 62% of signed utility load sits under approved data-center tariffs, and 19 of 24 tariff classes require customers to pay 80% of contracted demand whether used or not.

Inside ERCOT, 27 GW of contracted load exists, with only 2.8 GW on solar or wind. Outside ERCOT, 33 projects plan 72 GW of on-site generation, and at least 39 GW is gas-named. Kinder Morgan and Williams are siting campuses on their networks to lock fuel. Land math favors density: a solar farm needs about 20 times the acreage of an equivalent gas plant; wind can run past 100 times.

A Better Data Center Project and Earthjustice report tallies 177 GW of proposed gas capacity tied to AI buildout, with 80% aimed at the next five years, much of it marketed as behind-the-meter or self-supplied power. Most of those deals still retain grid ties for cost and reliability, so the private-generation path still collides with interconnection studies, pipeline competition, and equipment queues.

Edge players are testing a different cut of the same constraint. Katie Clasen at Prelude Ventures counts 35-plus companies placing inference loads at curtailed renewables, EV hubs, and commercial sites in 1 to 5 MW stacks, arguing inference can reach 60% of AI demand by 2030. Crusoe is shifting toward smaller distributed inference after Stargate Abilene. Tesla filed Megapod hardware in June. Nscale's 2 GW Monarch campus in West Virginia, with Caterpillar sets supplying 1.4 GW to Microsoft, is the mega-gas foil Clasen rejects for inference.

Model labs are writing power first. OpenAI anchored an 8 GW, twenty-year lease at SB Energy's PORTS-Pike campus in Pike County, Ohio, with the first 800 MW on existing AEP gear and the rest needing new generation and transmission; NVIDIA wrapped a residual-value guarantee capped at $105B on the initial 4.25 GW. Six top-tier U.S. deals paired campuses with dedicated on-site generation. Four transactions bought power infrastructure instead of the buildings. Three mining conversions turned approved interconnections into AI capacity.

For Texas developers, queue position and secured fuel beat press-release megawatts. Carrying cost between land close and energization is the line item that shows up when batch allocation slips a quarter.

Water

Disclosure gaps are already a siting filter

As of June 2025, only 28 of 377 surveyed companies had disclosed resource consumption, including water, in the community-alignment gap a16z flags beside the queue freeze. Hood County commissioners were asked to approve a tax waiver for an unnamed "Project Patriot" without knowing the applicant's identity. That transparency miss fuels local backlash even when the engineering is sound.

California's September package now mandates water reporting alongside energy disclosure. Nevada's EO ties Community Support Commitments to full cost coverage. Operators who put closed-loop design, source rights, and gallon accounting in the county packet before the hearing keep control of the narrative. Operators who treat water as a later MEP detail inherit contested hearings and schedule slip measured in quarters.

Politics

Affordability season skips the grid, while permit gates stack

Texas midterm platforms are heavy on groceries, property taxes, and insurance. Attorney General Ken Paxton targets food-supply monopolies and meatpackers. James Talarico proposes tariff relief on produce that can't be grown domestically. Gina Hinojosa calls out surveillance pricing. Vikki Goodwin backs the Texas Food System Security and Resiliency Planning Council. Governor Greg Abbott and Lieutenant Governor Dan Patrick point to broader economic management and have not tabled specific grocery plans.

Drought and wildfire losses in the cattle herd, avian influenza in poultry, diesel at $6 a gallon in Texas, and tariffs on more than half of U.S. food imports as of February sit outside state control. None of the surveyed platforms ties household costs to grid stability, interconnection delays, or the power bill inside food processing and cold chain. Load growth still shows up in those operating expenses whether candidates name it or not.

On the permit track, ERCOT paused new large-load permits as the queue hit 474 GW. Separately, JDSupra's October roundup states Governor Greg Abbott moved from pausing data-center approvals in August to halting all data-center-related permits. House Democrats' 253-page Thriving Economy Project shifts federal energy rhetoric toward affordability and security, with chapters on nuclear licensing, geothermal permitting, critical minerals, and transmission on existing lines, and with permitting-reform language notably absent.

SpaceX, Blue Origin, and Google have FCC filings for large LEO compute constellations pitched as a way around terrestrial power queues; Cowboy Space claims a 20,000-satellite Stampede design would skip the ground grid. Feasibility and spectrum timing remain open, and Sam Altman, Gartner, and Jim Chanos have questioned the economics. Terrestrial developers still live on ERCOT batch timing, county disclosure, and secured generation. Miss the political and interconnection calendar together and the balance sheet holds land, posted security, and no energization date.

Sources we cited

13 articles across 11 publishers · 410 reviewed today

  • Why Texas Is Making Data Centers Wait
    Oct 7, 2026·At the end of 2024, Texas’ grid operator had 63 GW of large new customers in its queue. By this June, that figure reached 474 GW, more than …
  • At Yotta, not a word on slowing down the AI infrastructure build-out
    Oct 7, 2026·But outside of the AI boom, utilities are deploying renewables and storage at pace. The post At Yotta, not a word on slowing down the AI inf…
  • Data Center Power Demand to Grow 24% Annually by 2030: McKinsey
    Oct 7, 2026·Power constraints are pushing operators toward on-site generation, but uncertainty beyond 2030 raises questions about how much infrastructur…
  • Google Deal Backs 890 MW of Constellation Nuclear Uprates at 11 PJM Reactors
    Oct 7, 2026·Hyperscaler Google and Constellation Energy, the largest nuclear operator in the U.S., have signed a 20-year power purchase agreement (PPA) …
  • Two Philly-area nuclear plants are increasing power generation as part of a deal with Google
    Oct 6, 2026·Two Philly-area nuclear plants will be able to produce more power in the coming years as part of a deal between Google and Constellation Ene…
  • Big tech's nuclear energy plans continue with Google's new deal talks
    Oct 6, 2026·Major technology giants are aggressively securing nuclear capacity to meet their expanding infrastructure demands. Can nuclear energy satis…
  • Washington Update: Sustainable Energy & Infrastructure — October 2026
    Oct 6, 2026·September brought significant developments across congressional energy policy, data center regulation, infrastructure investment, and federa…
  • Getting It Right Together: The State Regulatory Lens on America’s Large-Load Future
    Oct 7, 2026·Who pays, who bears the risk, who decides, and when? Virginia Commissioner Jehmal Hudson makes a forceful case that serving large-load growt…
  • The AI Gas Rush: How “Bring Your Own Power” Evades Regulation and Drives Deadly Pollution
    Oct 8, 2026·A new report examines the risks and consequences of “Bring Your Own Power” for AI data centers. The race to scale artificial intelligence (…
  • Can edge compute undercut demand for mega gas plants?
    Oct 7, 2026·Prelude Ventures’ Katie Clasen says distributed computing for AI inference is a better solution than massive off-grid gas plants. The post C…
  • The Global AI Buildout in 125 Deals
    Oct 8, 2026·Welcome to Global Data Center Hub. Join investors, operators, and innovators reading to stay ahead of the latest trends in the data center s…
  • What to know about Texas’ affordability crisis and how candidates want to fix it
    Oct 8, 2026·As Texas voters fret about the high cost of living, candidates running in this year’s midterm elections are trying to claim the mantle of af…
  • Orbital data centers? Or just distributed LEO compute?
    Oct 6, 2026·As the marketing pageantry around new space innovation pervades, strategic priorities may be cementing demand The year is star-date 2026. A…