$2.2B Anthropic Campus Carries Schedule Risk Against January 2028
Bastrop's forced hearing on Pacifico's 710 MW plant for the Anthropic campus lands beside Virginia's hardened entry terms and Governor Greg Abbott's large-load audit due around December 10. Developers who lock water terms, security deposits, and complete filings before those clocks keep Texas optionality others can't recover.
Today's Lead
The plant would supply more than three times Bastrop County’s 224 MW residential peak. Project Longhorn, the first data center phase, filed this month with the Texas Department of Licensing and Regulation at nearly 500,000 square feet and $366M, with construction targeted to start late November and finish January 2028; total project value is $2.2B-plus. Aqua Water Supply Corporation already approved service at 6,900 gallons of potable water per day, while the developers say they’ll use roughly 2,000 gallons daily across about 600 developed acres.
TCEQ rules no longer auto-trigger a hearing after the developers withdrew their tax-abatement request, so the county is asking executive director Steven Schar to use discretionary authority. The hearing won’t erase entitlements, but it will stretch the calendar and put air, water, and traffic mitigation on a formal public record while EdgeConneX builds a separate multibillion-dollar campus about three miles away. Operators who wait for testimony to force mitigation will carry schedule risk against a January 2028 completion.
NATIONAL CONTEXT
Michigan’s 2024 sales-and-use tax exemption for qualifying centers triggered 30-plus municipal moratoriums even as Oracle advances a 1.4 GW complex in Saline Township and Google evaluates a 282-acre campus in Van Buren Township. In New Jersey, DataOne USA’s Vineland campus (roughly 2.4 to 2.6 million square feet) faces a federal class-action noise suit seeking to cover about 1,013 households after Cumberland County’s Department of Health recorded nighttime levels above the 50-decibel limit on March 10. In North Wales, Gwelyfenai Ltd’s 450 MW outline application near Caernarfon drew more than 22,000 petition signatures and a street protest of roughly 300 people on October 14 before the planning committee has ruled.
Separately, a Senate Democratic investigation found Amazon, Google, Meta, and Microsoft are contesting “but-for” cost allocation and 80, 90% minimum-bill floors on contracted demand. FERC rejected most of PJM’s proposal that new loads of 50 MW or more bring their own capacity or face first-line curtailment. These are site-selection and sequencing signals. Capital still flows to markets that clear power, permits, and community terms early; projects that discover those terms after land close pay carrying cost in quarters, not weeks.
Power
Power certainty now prices land, deposits, and deal structure
Texas already prices that uncertainty into contracts. Plug Power’s Graham project sale to Stream Data Centers was structured at $50M plus up to $26.5M contingent on load capacity against a 164 MW reference, with an Oncor interconnection request, a $6.5M utility deposit, and a $7.75M letter of credit under ERCOT’s Batch Zero path; Stream later paid $40M for the high-voltage electrical package while land and remaining interconnection assets stayed conditioned. The Public Utility Commission of Texas issued its final interconnection rule on September 18 with a $50,000-per-MW financial-security deposit. A developer that withdraws before its study starts recovers the full amount; post-allocation withdrawal forfeits 20%. Cleanview counts roughly 12,800 MW of Texas data center projects under construction against an interconnection queue above 400,000 MW. Vistra CEO Jim Burke told investors he expects 12,000 to 15,000 MW to connect by 2030 and called the queue overstated by more than 20x; Wood Mackenzie rates only 23% of disclosed requests as high confidence.
OilPrice reports Brookfield Asset Management and NextEra Energy plan a $100B Paducah American Energy Hub on the former gaseous-diffusion site in western Kentucky: a 1.8 GW AI campus, 2 GW of gas-fired generation, and 2.6 GW of battery storage, phased toward 2032. Offshore Data Center LLC and Houston-based Riverway Group are pairing stranded Gulf gas with floating platforms sized up to a gigawatt for training loads, using closed-loop deep-ocean cooling and lighter semisubmersible hulls. Goldman expects behind-the-meter generation to supply a quarter of data centers by 2030. On July 22, 3 GW of Northern Virginia data center load disconnected from PJM after a transmission fault, the largest such event in PJM history; NERC had already issued a Level 3 alert in May, and Amperesand is shipping silicon-carbide solid-state transformers that convert 13.8 to 35 kV AC to 800 VDC in one step to meter transfer rates and hold load on batteries during disturbances. Nvidia, Google, and Microsoft published the open 800 VDC rack standard last year.
Developers without committed load, near-term substation delivery, and ride-through design will watch deposits sit, land premiums compound, and batch positions slip while power-ready peers clear first. The cost of inaction shows up as contingent consideration left on the table and queue positions that never convert.
Water
Cooling and supply terms are moving into the first permit cut
Cross-border campuses add another layer. Meta is building in El Paso, Oracle’s Project Jupiter is under construction in Doña Ana County, New Mexico, and a larger facility is planned on Fort Bliss in East El Paso; New Mexico State Representative Sarah Silva noted her state can regulate air and noise on its side of the line but has no authority over a Texas site hundreds of yards away. The Texas Tribune counts 596 data centers operational or planned statewide. Operators who treat water offsets, discharge verification, and dual-state coordination as post-permit cleanups will face hearing records, petition campaigns, and neighbor litigation that reprice the same gallons after capital is posted. The prepared path locks supply agreements, closed-loop design, and measurable community terms before the first public docket.
Politics
Audit clocks and ROE math are rewriting who stays in the Texas queue
The Texas Senate Business and Commerce Committee heard cost-of-capital testimony on September 30. Barksdale English, PUCT deputy executive director, confirmed average allowed return on equity at 9.6%, or closer to 12% once federal corporate income tax is layered on. Ellis applies a capital asset pricing model, puts the market-justified range at 6 to 6.5%, and estimates national excess returns near $60B a year. He proposes an auction that lets competitive bids clear the equity return the way ERCOT stacks generator offers. Compressed ROE would reweight utility incentives away from pure rate-base growth and toward throughput and alternatives such as storage and demand management, which can either accelerate interconnection or create new bottlenecks if performance metrics never tie to queue velocity.
Brazil’s secondary markets show the same sequencing test abroad: São Paulo still holds 76% of live capacity, yet transmission reinforcement and environmental licensing that can run 18 months decide whether Rio, Fortaleza, or the south actually absorb hyperscale load. Texas developers who treat the December 10 audit window, the October 19 TCEQ report, and the next PUCT cost-of-capital proceeding as spectator events will find deposit capital tied up, permit calendars paused, and transmission investment paced to someone else’s ROE case. The operators filing complete load, water, and community packages before those dates keep optionality; the ones holding speculative queue slots fund the screen.
Sources we cited
15 articles across 12 publishers · 558 reviewed today
- Why a controversial Bastrop gas plant tied to Claude is facing pressure - Austin American-StatesmanOct 14, 2026·A sign opposing the proposed Pacifico Power Plant stands in a yard on North Gaines Road in Cedar Creek on Sept. 18. The proposed power plant…
- Your Power Bill Backs Data Centers. Texas Made the Deposit RefundableOct 14, 2026·Utilities finally put a price on a place in the power queue. The number that matters is not what a developer posts. It is what the developer…
- Virginia’s New Data Center Bargain: Power, Permits and the Right to BuildOct 14, 2026·Virginia is reshaping data center development through new executive directives, utility policies and proposed regulatory reforms addressing …
- Fact check: What’s true and what’s not in Michigan’s data center debateOct 14, 2026·Few issues are as controversial today as data centers, which polls show are overwhelmingly opposed by Michigan residents. Amid the debates, …
- NJ AI Data Center Sued Again: 1,013 Homes in Class [2026] - https://tech-insider.org/Oct 15, 2026·A second group of New Jersey residents has sued the operator of what’s described as one of the East Coast’s largest data center campuses, ar…
- North Wales Data Center Protest: 24K Sign Petition - https://tech-insider.org/Oct 14, 2026·A derelict factory site on the shores of the Menai Strait has become the latest flashpoint in Britain’s AI infrastructure boom. Plans for a …
- Big Tech Pushes Back Against Paying for America's Aging Power GridOct 14, 2026·Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Glo…
- AI Data Center Land Buying Hits $6B as Power Premiums RiseOct 14, 2026·US data center land spending hit roughly $6 billion in the first half of 2026, as power access now drives land value and pricing more than l…
- Brookfield, NextEra to Build $100 Billion AI Hub on Cold War Nuclear SiteOct 15, 2026·Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Glo…
- [10]World OilOffshore Data Center taps Riverway to build stranded-gas data center platformsOct 14, 2026·(WO) – Offshore Data Center LLC has partnered with Houston-based Riverway Group to design and build offshore platforms that use stranded or …
- [11]Latitude MediaThe AI doom debate is missing the grid’s real cyber problemsOct 14, 2026·As AI makes attacks easier, companies from data centers to utilities are changing how they secure their operational technology. The post The…
- [12]EE TimesAmperesand Aims to Smooth AI Data Center Power SpikesOct 13, 2026·Singapore-based solid-state transformer (SST) startup Amperesand aims to help AI data centers smooth the spikes in their electrical demand t…
- [13]El Paso MattersEl Paso and New Mexico set ambitious climate goals. Their plans didn’t account for massive new data centersOct 14, 2026·This article is co-published with ProPublica and The Texas Tribune as part of an initiative to report on local control of government. Last …
- The case for lower utility profitsOct 14, 2026·Mark Ellis puts excess U.S. utility returns at about $60 billion a year, and lays out why commissions keep approving higher returns and how …
- Brazil’s Data Center Growth Pushes Beyond São PauloOct 14, 2026·Brazil’s data center growth is spreading beyond São Paulo to Rio, Fortaleza, and the south, but power grid delays and lengthy permitting wil…