Georgetown's City Council, the City of Starbase Commission and ERCOT act on three straight days: Dec. 8, 9 and 10. The council takes up a 28-acre data center rezoning, the commission hears SpaceX's tax abatement request, and ERCOT files its Batch Zero and community impact reports with the PUCT.

Those are three of ten Texas dates between Tuesday, Dec. 1 and Thursday, Dec. 17. All ten are below, in date order.

On this Thanksgiving Day, we at Hyperscale News give thanks for you, our readers. Without you, we could not do the work we are so pleased and proud to deliver. As our thanks today, in place of a regular issue, we offer you a respite from the fast pace of change in the industry and a resource that should help you over the next several weeks.

Tuesday, Dec. 1. Parties in three Batch Zero complaints at the Public Utility Commission of Texas (Dockets 60356, 60396 and 60431) must file an agreed schedule, or competing schedules. An administrative law judge set the deadline on Nov. 23.

Thursday, Dec. 3. PUCT open meeting. Item 25 is Project 58000, the rule on how transmission costs are recovered. Commission Staff filed recommended changes to the proposed rule text on Nov. 24. Mesquite H2 has asked the Commission to reconsider, at this meeting, its Nov. 19 vote to dismiss the company's Batch Zero complaint.

Friday, Dec. 4. Prehearing conference in the three Batch Zero complaints, 1 p.m., by videoconference. The Texas Dispatch reports that Dec. 4 is also the last day for developers to authorize the release of 23 data points from their answers to ERCOT's community impact survey.

Tuesday, Dec. 8. Georgetown City Council takes up a rezoning of about 28 acres for a data center. The Planning and Zoning Commission voted unanimously on Nov. 17 to recommend denial. CBS Austin reports that the council needs a 6-1 vote to approve the rezoning over that recommendation.

Wednesday, Dec. 9. The City of Starbase Commission holds a public hearing on a property tax abatement for SpaceX's data center and gas plant project.

Thursday, Dec. 10. ERCOT files two reports with the PUCT. The first is the Batch Zero eligibility verification report. ERCOT asked for the documents behind each large load's sworn eligibility claim and checked them against its Planning Guide criteria. As of ERCOT's Sept. 11 filing, the conditional Batch Zero list held 191.8 GW across 362 projects, and ERCOT said the numbers could change. The second is the community impact review report. It draws on a survey of about 130 questions on financial assistance, power, water and cooling, community impact and ownership. ERCOT sent the survey to 465 data center loads, and 433 responded.

Monday, Dec. 14. Comments are due in PUCT Project 59999, the proposed standard interconnection agreement for all large loads in the ERCOT region. Requests for a public hearing are due the same day.

Tuesday, Dec. 15. Transmission and distribution utilities return ERCOT's backup generation workbook. It lists each energized facility of 25 MW or more that has at least 1 MW of on-site backup generation. ERCOT says it may use the data to direct backup generation under a future federal emergency order.

Wednesday, Dec. 16. Cleanview reports that TCEQ commissioners are scheduled to vote on the Kilby Power Plant permit, which would supply Microsoft. We did not find a posted agenda yet.

Thursday, Dec. 17. PUCT open meeting, 9:30 a.m. The Texas Tribune reports that the Commission will discuss ERCOT's findings.

Not on the calendar. Cameron County commissioners voted 3-2 on Nov. 17 against sending SpaceX's abatement request to a public hearing, so no county hearing is set.

Regular issues return Friday.

James Dickey, Publisher

Sources: PUCT 60356 Order No. 6, PUCT 58000 Staff memo, PUCT 60410 Mesquite motion, The Texas Dispatch, CBS Austin, ERCOT Sept. 11 PUCT presentation, ERCOT Nov. 5 survey update, PUCT 59999 request for comments, ERCOT notice M-B111026-01, Cleanview, ERCOT calendar, Dec. 17 PUCT meeting