Texas Adds 58 GW of Gas in One Year. The Grid May Be the Last to Know.

Behind-the-meter power isn't a workaround anymore; it's becoming the default. Meta's 813 modular gas generators in El Paso, Pacifico Energy's 7.65 GW complex in Pecos County, Chevron's 5 GW West Texas plant: hyperscalers aren't waiting for grid interconnection, and ERCOT can't forecast load it can't see. That's the real risk buried in Texas's 58 GW gas buildout this year, roughly 40 GW of it dedicated to data centers. As the White House floats a voluntary compact on cost allocation and South Carolina debates whether to regulate siting through a new commission, Texas's light-touch approach is pulling investment at a pace that's outrunning the infrastructure meant to support it.

Today's Lead

Meta is deploying 813 modular natural gas generators totaling 366MW of behind-the-meter power to fuel a 1GW data center under construction in El Paso, Texas, at a $473 million capital cost, bypassing grid connection entirely and drawing unanimous opposition from El Paso City Council and local community groups. The campus, which broke ground in October with $1.5 billion in phase-one investment, is the first of up to five phases across 1,000+ acres. Council voted to intervene in regulatory proceedings, and the Sembrando Esperanza Coalition is demanding contract termination, accusing Meta of misleading the community about renewable energy reliance. This is the sharpest collision yet between hyperscaler behind-the-meter strategy and local political resistance in Texas.

Power

Texas Gas Buildout Reaches Unprecedented Scale

Texas's gas power pipeline grew by nearly 58 GW of capacity during 2025 alone, per Global Energy Monitor data, with roughly 40 GW designated to directly power data centers. Pacifico Energy's GW Ranch in Pecos County secured the largest air pollution permit ever issued in the U.S. for a 7.65 GW gas and data center complex, authorized to emit up to 33 million tons per year of greenhouse gases. Fermi America's Project Matador near Amarillo is permitted for 6 GW; Chevron announced its first-ever power plant at up to 5 GW for AI workloads in West Texas. TCEQ is processing permits for gas projects up to 500 MW within a month, a velocity that raises questions about whether adequate review is occurring.

Meta's El Paso behind-the-meter approach and Oracle/OpenAI's Stargate facility in Abilene fit the same pattern: operators are building their own power because they can't wait for grid interconnection. Soluna CEO John Belizaire adds another dimension, noting that 30 to 40 percent of Texas renewable generation goes unused due to transmission bottlenecks, and his company is siting data centers at those curtailment points, operating three facilities totaling 123 MW across Kentucky and Texas with 800 MW more in development.

The risk bifurcates: if hyperscalers lock in onsite power en masse, they reduce demand visibility for ERCOT load forecasting while potentially deferring the transmission investment Texas needs long-term. Meanwhile, permitting speed that satisfies developers may prove politically unsustainable as cumulative emissions and water demands in arid West Texas compound.

Politics

White House Drafts Voluntary Compact, States Race to Regulate

The Trump administration is circulating a draft voluntary agreement asking hyperscalers to cover 100 percent of new generation and transmission costs tied to their facilities and sign long-term electricity contracts to shield ratepayers. A White House official told POLITICO the draft "is outdated and no longer accurate" without clarifying what changed. Energy Secretary Chris Wright acknowledged the administration is in dialogue with developers about preventing electricity price spikes. The critical gap: without state-level regulatory buy-in, voluntary commitments lack enforcement.

South Carolina is testing that gap in real time. Two competing bills would establish first-ever state data center regulation, splitting on whether a new environmental commission (Sen. Tom Davis's approach) or the Public Service Commission (Sen. Luke Rankin's proposal) should control siting, permitting, and cost allocation. John Brooker of Conservation Voters of South Carolina cited utility projections that data centers could account for 60 to 70 percent of the state's new power demand. DC BLOX's Chris Gatch warned that additional permitting layers will push investment to less regulated states.

For Texas, this thread matters directly: the White House compact's language about cost responsibility mirrors debates already happening around ERCOT interconnection and behind-the-meter generation frameworks. If the federal compact collapses and states adopt divergent regulatory regimes, operators face a patchwork that favors jurisdictions with the lightest touch, which currently means Texas.

Water

The Resource Nobody Wants to Talk About Honestly

OpenAI CEO Sam Altman called water consumption concerns at AI data centers "fake" and "completely untrue" at India's AI Impact summit. That claim sits awkwardly against a Xylem and Global Water Intelligence report projecting data center cooling water demand will more than triple over the next 25 years. In Wilson County, Texas, Misea's 2,700-acre Mojo Ranch project requires up to 2 million gallons per day from an already stressed aquifer; over 140 residents packed a Stockdale community meeting to oppose it, and local rancher Matthew Dean described liquidating half his cattle herd during last year's drought. In Osawatomie, Kansas, Alcove Development's $1 billion campus contract mandates 1 million gallons per day, and residents are demanding to know how a city of 4,000 supplies that volume.

Deep Green's 24 MW Lansing, Michigan project tries a different approach: a closed-loop water-glycol system consuming under 500,000 gallons annually with zero river discharge. Meta's El Paso campus claims zero water consumption for cooling "most of the year," though the basis for that claim isn't detailed.

Altman's dismissal risks becoming a rallying cry for opponents. When the CEO of the world's most prominent AI company tells communities their water concerns are fabricated, it hands organizers a perfect soundbite. The more consequential question is whether aggregate demand in water-stressed regions like West Texas and the Edwards Aquifer system exceeds sustainable yield before anyone's tracking cumulative drawdown — not whether individual facilities can engineer around the constraints.

Sources we cited

11 articles across 10 publishers · 108 reviewed today

  • Meta to deploy 366MW of modular gas units to power 1GW data center in El Paso, Texas
    Feb 23, 2026·Facing opposition from the local council and community groups Meta’s under-construction data center in El Paso, Texas, is set to be powered
  • Texas Could Surpass Northern Virginia as World’s Largest Data Center Market by 2030
    Feb 22, 2026·Gift a Payroll Tax Calendar to your Payroll Admins this holiday season. → Texas is positioning itself to become the world’s largest data ce
  • Developer Calls GW Ranch in Pecos County, Texas, the ‘Largest Power Project’ in U.S.
    Jan 29, 2026·Texas’ environmental regulator this week issued the largest air pollution permit in the country to an enormous planned complex of gas power
  • How a Data Center Company Uses Stranded Renewable Energy
    Jun 19, 2025·John Belizaire says he has a secret hiding in plain sight. But before revealing it, the CEO of Soluna, a green data center development firm
  • White House eyes data center agreements amid energy price spikes
    Feb 10, 2026·The Trump administration wants some of the world’s largest technology companies to publicly commit to a new compact governing the rapid expa
  • The data center industry is seeking a bigger footprint in SC. Question is, who should regulate them?
    Feb 22, 2026·Nick Reynolds covers politics for the Post and Courier. A native of Central New York, he spent three-and-a-half years covering politics in W
  • [7]KABB
    Wilson County residents fight proposed AI data center
    Feb 20, 2026·This 18-day extravaganza is one of San Antonio's biggest events, drawing approximately 1.5 million visitors each year. WILSON COUNTY, Texas
  • [8]WLTX
    South Carolina weighs data center regulation as power bill, water use concerns arise
    Feb 22, 2026·To stream WLTX 19 on your phone, you need the WLTX 19 app. Example video title will go here for this video Example video title will go her
  • [9]CNBC
    Sam Altman defends AI resource usage: Water concerns 'fake,' and 'humans use energy too'
    Feb 23, 2026·OpenAI CEO Sam Altman on Friday defended the resource demands of artificial intelligence, calling concerns about data centers' water use "fa
  • Marais Des Cygnes River at center of debate over proposed Miami County $1B data center deal
    Feb 23, 2026·KSHB 41 reporter Ryan Gamboa covers Miami County in Kansas and Cass County in Missouri. He is committed to telling stories in your community
  • Demystifying Deep Green’s proposed data center near downtown Lansing