Tuesday, February 24, 2026
35 GW Pre-Leased, 107-Week Lead Times, Zero Margin for Error
JLL's latest numbers frame the scale of what's coming: 35 GW under construction across North America, 92% already pre-leased, and Texas accounting for 6.5 GW of that pipeline. Enough, potentially, to dethrone Northern Virginia as the continent's top datacenter market by 2030. But the delivery window is 2027-2028, and the bottlenecks aren't theoretical. Stargate's air permits reveal a supply chain running through Chinese-owned Baudouin engines with 107-week lead times from alternative manufacturers. Hood County commissioners vote Tuesday on whether to defy their own county attorney and pursue a datacenter moratorium that state lawmakers have already signaled won't survive legal challenge. And Sam Altman's dismissal of water concerns as "completely untrue, totally insane" lands the same week Houston Advanced Research Center projections show Texas datacenter water consumption could hit 161 billion gallons annually by 2030. The gap between what's been pre-leased and what can actually be built, powered, cooled, and permitted is where the real story lives.
Today's Lead
Politics
Hood County's Moratorium Fight Tests the Limits of Rural Texas Authority
Meanwhile, rural residents bused into Austin Monday to demand Gov. Abbott convene a special session for a statewide moratorium or grant counties explicit siting authority. The flashpoint is a 2,600-acre campus planned for Hood County's Paluxy Valley near Dinosaur Valley State Park, featuring dozens of buildings and gas-fired power plants. SMU professor Matthew Wilson confirmed the core constraint: counties are "entirely subservient to state government."
If Hood County proceeds anyway, it faces near-certain state litigation that would drain county resources and likely establish precedent foreclosing rural land-use controls statewide. Watch Tuesday's vote, any AG opinion request, and whether Abbott signals any appetite for a special session.
Power
Powered Land Is the New Bottleneck, and Consolidation Is Accelerating
Jefferies analysts project behind-the-meter capacity will grow 17% annually to 25 GW by 2030. Google's new Wilbarger County deal with AES exemplifies this model: air-cooled, co-located with AES-developed generation, construction-ready with land and interconnection already under contract. Google has now contracted over 7,800 MW of net-new generation capacity in Texas via PPAs, part of a $40 billion investment commitment through 2027.
The risk: if grid queues shorten faster than expected, BTM cost advantages erode and pipeline assets get stranded. And natural gas supply chains face their own bottlenecks as BTM proliferates.
Power/Politics
Stargate's Generator Permits Expose a Baudouin Chokehold
Politics
Over 200 State Bills Signal a Regulatory Reckoning for Datacenter Economics
Meta's $437 million gas plant in El Paso illustrates the friction: El Paso City Council voted unanimously to intervene in the regulatory process over concerns the plant could eventually roll into the utility rate base. The Sembrando Esperanza Coalition's organizer Verónica Carbajal said the community was told "Meta is going green" but "when we looked at the contracts ourselves, we realized that was an illusion."
WilmerHale flags that constitutional commerce-clause challenges and rate-discrimination claims are likely as datacenter-specific tariffs proliferate. The legal fault line: industry-funded analysis claims large datacenters cover full service costs and may even reduce retail rates, but states are legislating without consensus on that question.
Sources we cited
9 articles across 9 publishers · 229 reviewed today
- JLL: Hyperscale and AI Demand Push North American Data Centers Toward Industrial ScaleFeb 23, 2026·JLL’s North America Data Center Report Year-End 2025 makes a clear argument that the sector is no longer merely expanding but has shifted in…
- Rural residents call for statewide data center moratorium - Austin American-StatesmanFeb 23, 2026·Advocacy groups and community members protest laws surrounding data centers while outside the Texas Capitol in Austin on Monday. Protestors …
- [3]KERA NewsHood County to consider another data center moratorium despite potential legal concernsFeb 24, 2026·Hood County leaders will once again weigh whether to hit pause on large-scale data center development. But even if they move forward, state…
- Scale buys Reload as the hunt for powered land heats upFeb 23, 2026·The microgrid developer is betting on hyperscalers' bringing their own power to sidestep grid delays The post Scale buys Reload as the hunt …
- Google announces new “clean energy” data center agreement with Wilbarger CountyFeb 24, 2026·WICHITA FALLS, Texas (KAUZ) - A new air-cooled data center will be making its way to Wilbarger County in a “power-first” initiative between …
- [6]HunterbrookBuried in Stargate’s Permits: A Generator Engine Almost No One Sells. Except Generac.Feb 23, 2026·Based on Hunterbrook Media’s reporting, Hunterbrook Capital is long $GNRC and short a basket of comparable securities at the time of publica…
- [7]WilmerHaleState Regulation of Data Centers: Emerging Trends and Potential Legal ComplexitiesFeb 23, 2026·Data centers are proliferating across the United States—and across the legislative and regulatory agendas of state and local governments. In…
- Mark McNees: Sam Altman just made the case for SB 484Feb 23, 2026·OpenAI CEO Sam Altman told an audience at the India AI Impact Forum last week that concerns about data center water consumption are “totally…
- Meta Tables Plans for $437M Gas-fired Power Plant to Run its Data Center in El Paso, TexasFeb 24, 2026·Meta is making plans for a $437 million gas-fired power plant to run its data center in El Paso, Texas despite significant pushback. The 1GW…
Search across 25,000+ tracked articles → coming with paid