Google's $12B Power Platform Hits the Queue It Was Built to Skip

Google's $12B IPX platform, carrying 4.4 GW of solar and 8.8 GWh of storage, was built to sidestep ERCOT's 230 GW interconnection backlog entirely. ERCOT won't define which projects qualify for "batch zero" bypass until June, so Google's co-location strategy and its $40 billion Texas campus commitment both hang on a deadline it doesn't control.

Today's Lead

ERCOT is ripping out its decades-old interconnection model to break a 230 GW "doom loop" choking Texas datacenter and industrial growth. The grid operator presented its batch study framework to the Public Utility Commission on February 20, replacing serial project reviews with simultaneous cluster evaluations across a six-year reliability window. Up to 100 large load applications now arrive per quarter, compared to a historical baseline of 8-15, and ERCOT must define which projects qualify for "batch zero" by June. This is the single most consequential structural reform for datacenter developers operating in Texas right now.

Power

Google's $4.75B Intersect Acquisition Closes, Spawning $12B IPX Power Platform in Texas

Google completed its acquisition of Intersect Power this week, and TPG Rise Climate simultaneously spun Intersect's grid-tied assets into IPX Power, a new independent company with 4.4 GW of solar PV and 8.8 GWh of battery storage in construction or operation. The combined enterprise value across both transactions: $12 billion. IPX's development pipeline spans California and Texas, serving utilities and corporate customers.

This pairs directly with Google's November commitment of $40 billion through 2027 to build three new datacenter campuses in Texas. The sequencing is deliberate: secure co-located renewable generation, then build compute. Ed Beckley, managing partner of TPG Rise Climate, framed it as solving "hyperscalers' most significant challenge: readily available power at scale."

Can IPX execute a multi-GW solar and storage buildout across Texas permitting timelines fast enough to serve Google's campus schedule? If interconnection delays hit IPX projects the way they've hit the broader ERCOT queue, Google's co-location strategy faces the same bottleneck it was designed to avoid.

Politics

Texas Counties Can't Stop Datacenters, and Brazoria County Just Proved It

Brazoria County commissioners voted 5-0 Tuesday to deny tax abatements for Nightpeak Energy's $3 billion, 310 MW natural gas plant and dual AI datacenter complex near Sweeny. It didn't matter. County Judge Matt Sebesta said it plainly: "We cannot stop this project. We do not have the tools."

Texas State Rep. Cody Vasut (R-Angleton) confirmed the structural gap: "The state and the county have very few tools at our disposal to regulate these types of projects." Nightpeak's Oakland-based parent will proceed regardless, building on 154 acres outside a town of 3,500 residents. The denied abatements would have cost the county $10.5 million annually in lost tax revenue.

This pattern is replicating nationally. In Archbald, Pennsylvania, over 400 residents packed a hearing on Cornell Realty Management's Wildcat Ridge proposal: 14 datacenter buildings consuming 1.6 GW and 3.3 million gallons of water daily. Borough Councilman Louis Rapoch acknowledged the town "has to allow" data centers as conditional uses under state law.

The political pressure is unmistakable. Communities want veto authority they don't have. Whether Texas counties gain new regulatory tools depends on future legislative action, and right now no mechanism exists.

Power

Record Colo Revenue, but Digital Realty's Texas Divestiture Raises Questions

All four major colo operators posted record 2025 numbers. Digital Realty hit $6.112 billion in annual revenue with $3.34 billion adjusted EBITDA. Equinix topped $9.217 billion. Digital signed Q4 bookings of $400 million across 159.1 MW, mostly above-1MW US deals.

Digital sold its DFW14 facility on Alpha Road in the Dallas metro for $33 million while acquiring land near Hillsboro, Oregon — consolidating away from a Texas asset while expanding elsewhere. Digital's development pipeline stands at 769 MW under construction, but only 135 MW of new projects started in Q4, a slowdown relative to booking momentum.

If capacity delivery can't match booking velocity, pre-lease commitments start stacking against hard power constraints. Watch Q1 2026 delivery rates and whether DFW sees net capacity contraction from Digital.

Power

Ratepayer Cost-Shifting Becomes the National Flashpoint

Entergy announced $5 billion in cumulative customer savings over 20 years across Arkansas, Louisiana, and Mississippi from datacenter power purchase agreements. CEO Drew Marsh framed the deals as protecting existing customers while recruiting high-demand load.

Illinois offers a contrasting model. A December 2025 analysis from the Illinois Commerce Commission, Illinois EPA, and Illinois Power Agency warned of chronic electricity shortages and escalating bills within five years if AI-driven datacenter demand continues unchecked. ComEd customers already absorbed a $10.60/month rate increase in June 2025. In Frankfort, Illinois, a community forum exposed that the proposed Joliet complex, developed by Dallas-based Hillwood Investment Properties and Virginia-based PowerHouse Data Centers, would demand 1.8 GW, equivalent to powering every Chicago household.

Entergy's savings-sharing structure is a potential regulatory playbook for Texas utilities navigating datacenter PPAs. The question: does ERCOT's market structure allow the same ratepayer protection mechanisms, or do Texas customers face Illinois-style cost pass-throughs? Bottom line: how datacenter power costs get allocated will shape public acceptance of every project in the pipeline.

Power

Municipal Grids Hit the Wall Before Hyperscalers Even Arrive

Pasadena Water and Power told the Municipal Services Committee this week it can't serve a single hyperscale facility. The utility imports a maximum 280 MW from the regional grid, but peak demand already hits 330 MW. A 50 MW datacenter would consume 36% of total system load. The most recent large new customer? A 2.5 MW EV charging station.

Pasadena's zoning code doesn't even contain a datacenter category. Principal Planner Martin Potter: "If one were to be submitted, we would have to look at it on an individual basis." General Manager David Reyes was blunter: "If we don't have the capacity, we do not have the capacity."

Note: this is Pasadena, California, not Pasadena, Texas. But the lesson translates directly. Smaller Texas municipalities with constrained grid connections face identical exposure. If developers target second-tier cities without existing substation capacity, projects stall before permits are even filed.

Sources we cited

8 articles across 8 publishers · 228 reviewed today

  • ERCOT takes aim at ‘doom loop’ for big power users seeking to join Texas’ grid - San Antonio Express-News
    Mar 11, 2026·Construction workers earlier this month wire electricity lines in Dallas TX4 data center’s mechanical galley under construction at the NTT D
  • TPG Rise Climate Completes $4.75B Sale of Intersect to Google, Launches IPX Power
    Mar 11, 2026·Fort Worth- and San Francisco-based TPG Rise Climate has completed the sale of its stake in Intersect Power, which was acquired by Google fo
  • Houston suburb pushes back against $3 billion data-center project
    Mar 11, 2026·A Waco-area woman protested the development of a data center in her community last month at the Texas State Capitol. Sweeny, a town of arou
  • Wildcat Ridge Data Center Campus faces major opposition in Archbald - Scranton Times-Tribune
    Mar 11, 2026·ARCHBALD — A raucous crowd drowned out testimony from data center representatives Tuesday night, vocalizing their opposition to more than a
  • Data center colo results Q4 2025: Digital Realty, Equinix, Iron Mountain, American Tower
    Mar 10, 2026·Good times continue for big colo firms The major publicly-listed data center colocation providers have posted their latest quarterly result
  • Entergy announces $5B in customer savings delivered by data center agreements; issues 'Fair Share Plus' pledge
    Mar 11, 2026·NEW ORLEANS — Entergy has announced approximately $5 billion in total savings for 2.3 million customers in Arkansas, Louisiana and Mississip
  • Frankfort forum urges residents to study data center plans, raises environmental concerns
    Mar 11, 2026·About two dozen south and southwest suburban residents, along with environmental advocates and two Naperville residents, gathered Monday to
  • Pasadena Lacks Zoning Rules and Grid Capacity for Data Centers, Committee Learns
    Mar 11, 2026·[Updated]   A single hyperscale data center could consume more than a third of Pasadena’s entire current electrical load, and the city has n