ERCOT's Batch Rules Are Still in Draft. Your Invoices Are Not.

ERCOT's batch overhaul isn't drafted yet, but the $24 million surprise charges hitting developers with six days' notice confirm the reset's already underway. With 87% of the 410,000 MW queue tied to data centers, operators who can't fund their own generation or navigate rulemaking before 2027 won't recognize the interconnection terms they'll inherit.

Today's Lead

Texas is ground zero for the data center grid crisis. ERCOT CEO Pablo Vegas told the House Committee on State Affairs that incoming data center projects plan to draw 410,000 additional megawatts from the grid, roughly seven times the new demand ERCOT managed just two years ago. About 87% of the incoming queue is data centers, with submissions accelerating sharply in the past six weeks.

ERCOT is responding with a structural overhaul: a new "batch interconnection process" that will prioritize connections, require upfront capital for grid upgrades, and reserve transmission capacity for the first time. "That's a big change from what we do today," Vegas said. The rules should be finalized before the 2027 legislative session, and developers who engage during rulemaking will shape terms that govern Texas data center economics for a decade.

Power

ERCOT's batch process rewrites the interconnection playbook

The hearing surfaced immediate friction alongside the structural shift. State Reps. Charlie Geren and John McQueeney reported developers receiving surprise transmission utility charges reaching $24 million with just six days' notice. PUC Chair Thomas Gleeson committed to investigating. Meanwhile, ERCOT's application fee structure, authorized by legislation last year, is designed to filter speculative filers from serious developers by requiring upfront capital for feasibility studies. Ed Hirs, oil and gas expert, put it bluntly: data centers seeking grid access will need to fund their own generation or power supply.

Texas is tracking 140 planned data centers that would add 75,089 MW to the state's current 3,789 MW of operating data center capacity, per Cleanview's tracker. Bloomberg Energy projects Texas could exceed 40 GW of total capacity by 2028, representing roughly 30% of U.S. demand. The geographic spread stretches from San Antonio to Dallas, across the Panhandle, and into West Texas. Developers who assume today's pricing and timelines hold face the biggest risk: interconnection costs are unsettled, and ERCOT's batch process will reset expectations for every project in the queue.

Power

Developers bypass the grid with on-site generation

Oracle expanded its Bloom Energy fuel cell commitment from 1.2 GW to 2.8 GW of Solid Oxide Fuel Cell systems, with deployments already underway. Bloom has parallel deals with Equinix (exceeding 100 MW across 19 data centers) and a 1 GW commitment from American Electric Power for off-grid AI facilities. Brookfield invested up to $5 billion in Bloom last year. In Indiana County, Pennsylvania, Knighthead Capital is building a $10 billion, 4.4 GW natural gas plant with an attached hyperscale campus at the former Homer City coal site, with 1,200 Kiewit workers already on the ground.

These projects confirm the pattern: hyperscalers and capital-heavy developers are solving the power constraint themselves rather than waiting in grid queues. The Homer City model is especially instructive, feeding excess generation into PJM while powering its own campus. Risk sits in execution and permitting. Bloom's fuel cell manufacturing is unproven at hyperscale deployment speeds. Homer City's stormwater discharge permit faces a May 12 public hearing, and the 2028 online date has already slipped from 2027.

Water

Closed-loop cooling becomes the price of admission in Texas

Two Texas projects this week made water strategy their centerpiece. Aligned Data Centers broke ground on Project Caprock, a 540 MW campus in Hale County, deploying DeltaFlow liquid cooling with closed-loop, recirculated systems designed to protect the Ogallala Aquifer from drawdown. In Cameron County, Eneus Energy's proposed $14 billion, 2 GW facility near Harlingen prompted the Commissioners Court to unanimously pass a resolution opposing open-loop evaporative cooling and demanding transparent reporting of water and electricity usage. County Judge Eddie Trevino Jr. drew a hard line. Eneus responded by proposing a closed-cycle system using reclaimed wastewater.

Harlingen Mayor Norma Sepulveda said the City Commission began exploring a data center moratorium last week. Cameron County's resolution also calls on state lawmakers to grant local governments "meaningful participation" in data center permitting, an implicit acknowledgment that Texas law constrains county regulatory authority. Risk: if the legislature doesn't address local authority questions, counties will improvise, creating a patchwork of standards that slows permitting statewide.

Politics

Community opposition is now a material development risk

Organized opposition groups surged from 142 in 24 states to 188 in 40 states in one year. Halted or delayed project value jumped from $64 billion to $162 billion, per Data Center Watch. The conflicts are escalating: Festus, Missouri voters recalled four council members over a $60 billion AI data center approval. Indianapolis councilmember Ron Gibson's home was shot at 13 times with a note reading "No data centers allowed." Port Washington, Wisconsin became the first jurisdiction to hold a referendum targeting data centers, with 66% voting to require public approval of large TIF subsidies.

In Texas, the pattern is emerging. Hays County/San Marcos rejected a $1.5 billion project 5-2. Black Mountain Energy's Fort Worth project cleared the Zoning Commission but faces sustained Echo Heights neighborhood opposition over pollution, noise, water, and the absence of municipal data center regulations before a June City Council vote. Nationally, eight states have submitted or passed development pauses, including Maine, which passed its moratorium through the House 82-62. Illinois is holding three hearings on data center standards, with Aurora already enacting noise, water, and energy study requirements. The risk is straightforward: developers who skip community engagement upfront will lose months or years to opposition, recalls, and referendums downstream.

Sources we cited

13 articles across 13 publishers · 291 reviewed today

  • Texas lawmakers held a hearing on data centers. Here are 4 key takeaways
    Apr 13, 2026·The boom in data centers, many to support artificial intelligence, could strain the Texas power grid and increase energy costs. Data center
  • Texas lawmakers held a hearing on data centers. Here are 4 key takeaways
    Apr 13, 2026·The boom in data centers, many to support artificial intelligence, could strain the Texas power grid and increase energy costs. By Mose Buc
  • Texas lawmakers held a hearing on data centers. Here are 4 key takeaways
    Apr 14, 2026·The control room at the Electric Reliability Council of Texas, shown in 2018. Data centers are popping up around Texas like fire ant hills
  • Maps highlight 140 planned data centers in Texas
    Apr 13, 2026·Photo: İsmail Enes Ayhan / Unsplash (The Center Square) – Texas appears to be ground zero for a large number of data centers, at least 140,
  • Oracle expands fuel cell supply deal with Bloom Energy to 2.8GW
    Apr 14, 2026·Builds on intial 1.2GW deal inked last year Oracle has expanded its partnership with fuel cell developer Bloom Energy, agreeing to procure
  • Construction begins on $10B natural gas power plant and data center in Indiana County
    Apr 14, 2026·Site development work continues on April 7 at the former Homer City Generating Station, where a natural gas-powered data center is under dev
  • Project Caprock: Aligned Data Centers breaks ground on 540 MW DC campus in Texas
    Apr 13, 2026·Aligned Data Centers, a developer and operator of data centers for hyperscale, cloud, and AI workloads, has announced an expansion of its No
  • [9]MySA
    Massive controversial data center eyes South TX. What to know
    Apr 14, 2026·A massive 2 gigawatt data center proposed to be built outside Harlingen, in the Rio Grande Valley, has drawn criticism from residents, and q
  • [10]KuCoin
    Residents of U.S. Town Oppose AI Data Centers Amid Rising Protests and Legal Actions
    Apr 14, 2026·On April 7, voters in the city of Festus, Missouri, removed four of the eight city council members in a single vote. The action followed the
  • Data center moves forward after Fort Worth Zoning Commission vote
    Apr 13, 2026·Black Mountain Energy is changing some elements of its proposed data center off Lon Stephenson Road in southeast Fort Worth.
  • Mills pushes for Jay exemption in data center bill
    Apr 13, 2026·AUGUSTA — With final votes pending on a bill to temporarily ban data centers, Gov. Janet Mills emphasized on Friday that she wants to see an
  • Illinoisans rally for data center regulations. Here's what they said
    Apr 13, 2026·SPRINGFIELD —Illinois lawmakers are digging deep on data centers, with a House committee hearing from mayors, labor groups, and agriculture