Gov. Abbott's Audit Leaves Batch Zero With No Restart Date
Developers keep carrying capital as Batch Zero sits frozen under Gov. Abbott's audit with no restart date and Sierra Club pushes a 25 MW cost floor. Operators who don't lock tenants, self-supplied power, and water files before studies resume will carry terms they didn't write.
Today's Lead
The operator is pausing the transitional large-load study process for data centers and other computational loads 25 MW or larger that have not energized, including virtual currency mining. Quarterly stability assessments that gate later interconnection stages can’t run on schedule, and ERCOT will brief the Commission on compliance plans at the August 14 open meeting. Developers already posted in Batch Zero now carry capital between filed requests and the first stability gate with no restart date on the filing.
NATIONAL CONTEXT
On the Eastern Interconnection, more than 3 GW of data center load dropped off PJM on July 22, 2026 after a single transmission fault near Ashburn, repeating a failure mode NERC investigated when 1.5 GW shed on July 10, 2024. Customer-side protection, static switches, UPS logic, and counting relays uncoordinated with utility reclosing, drove the trips. Standards drafting on those settings is coming; operators who file engineering-grade coordination testimony will shape the obligation, and those who don’t will inherit it.
Power
UPDATE: Batch Zero clock stops; private generation fills the gap
Projects already energized or deep in construction sit outside the freeze. Tesla’s Cortex 2 at Giga Texas, with a first 250 MW phase live in April 2026 and onsite AI compute more than doubling in the first half of 2026, keeps moving because it is not a speculative queue entry. Fermi Inc. reset its narrative with a binding $6.5B, 15-year lease to TensorWave for 222 MW at Project Matador in Carson County, phased from 2H 2027, with expansion rights toward 650-plus MW still uncommitted and still subject to project financing and third-party guarantees.
Behind-the-meter buildout is the bridge operators are buying while the queue is stuck. Amazon’s GW Ranch campus in Pecos County pairs the load with a dedicated 7.65 GW natural gas plant from Pacifico Energy, permitted to run disconnected from ERCOT at first and “designed to transition to grid-connected service as interconnection timelines allow,” with the company stating it will pay full power costs and not raise household bills. J.P. Morgan puts 2026 hyperscaler capex at $697 billion and already originated $9.6B across two construction loans for Project Stargate’s Abilene campus, proof capital is still clearing Texas when generation and tenants are real.
Bottom line: treat the pause as a planning window to lock anchor tenants, self-supplied power, and clean interconnection files before Batch Zero reopens; carrying cost compounds every quarter the QSA gate stays shut.
Politics
UPDATE: Cost shift and disclosure move while incentives stay contested
Governor Greg Abbott’s June 10 direction already told the PUCT and ERCOT to make data centers fully fund electric infrastructure serving them, and he pledged 2027 work on generation-addition rules, closed-loop or water-efficient cooling, annual power and water reporting, community-impact standards, and repeal of sales-tax exemptions on equipment, power gear, electricity, and fuel. KFDM cites a Comptroller-linked $3.2B two-year sales-tax shortfall tied to the 2013 exemption, with at least $1.3B forgone expected this year. OpenAI, Meta, Amazon, Google, QTS, Skybox, Digital Realty, and MARA have been cited as aligning with his standards; Diode withdrew near Cedar Creek Lake after it did not meet them.
Binding force still tracks ERCOT geography. Meta’s $14 billion Northeast El Paso project keeps its full 2023 package, valued locally at $550 million including an 80% property-tax break for 25 years plus $12.5M in city road funds, because El Paso Electric sits outside ERCOT and city-county deals were not amended. At least 34 Texas counties have petitioned for mandatory disclosure rules. Shell companies, NDAs, and post-land-acquisition outreach (Crusoe’s stated sequence in Abilene) are feeding county and resident pushback in Grayson, Hood, and elsewhere; Texas Tribune and San Antonio Current both flag early voluntary disclosure as the path that compresses permits instead of inviting process fights.
Bottom line: model full infrastructure funding, a possible 25 MW cost-allocation floor, and audit-ready community-impact files now; the operators who show up in 58000 and local hearings write the terms everyone else prices later.
Water
NEW: Cooling and consumption move from preference to audit gate
Amazon’s Pecos plan uses brackish groundwater unsuitable for irrigation or drinking, a site-level offset to freshwater fight risk. Hood County drew a developer suit after rejecting a concept plan for insufficient water-source documentation, a live example of local process stopping a file when water proof is thin. Skybox’s PowerCampus Austin in Hutto, a 600 MW, 4-million-square-foot campus on 160 acres designed around an onsite privately owned Oncor substation, sits in the same policy window where cooling design and consumption disclosure will be checked against the new expectations before tax and interconnection assumptions hold.
Bottom line: lock closed-loop or brackish design, meter plans, and public water offsets before the next local hearing or audit notice; missing water proof is now a queue and permit stopper, not a design footnote.
Sources we cited
15 articles across 14 publishers · 5417 reviewed today
- PUCT Control No. 58317 Item 27: ERCOT LETTER REGARDING PROJECT NO. 59142 FILINGAug 10, 2026·Filed with the Public Utility Commission of Texas on 2026-08-10. Control Number: 58317 Item Number: 27 Item Type: LTRS Utility Type: O Filin…
- [2]KFDMWaste Watch: Texas faces $3.2 billion data center cash drainAug 11, 2026·Texas expects to forgo $3.2 billion in sales-tax revenue for data centers over the next two years — and the Texas Comptroller’s Office says …
- Texas Tightens Oversight of Data Center DevelopmentAug 10, 2026·Skybox Datacenters’ PowerCampus Austin in Hutto, Texas, is a 160-acre hyperscale campus designed for up to 600 MW of power capacity and as m…
- Texas Data Center Pause Won't Stop Cortex 2 at Giga Texas - BASENORAug 9, 2026·Texas Governor Greg Abbott's sweeping directive to pause new data center construction approvals is sending shockwaves through the state's en…
- Data Center Foes’ Newest Tack: Sue Locals Over Approval ProcessAug 10, 2026·Data center opponents aiming to delay or halt development of the hulking server warehouses are relying less on arguments over potential comm…
- 3 GW Off PJM, Again: What NERC’s 2024 Investigation Already Told UsAug 10, 2026·More than 3 GW of data center load left the PJM system on July 22, 2026, after a single transmission fault. The North American Electric Reli…
- [7]KVIIFermi signs $6.5 billion lease for 'world's largest data center' after months of turmoilAug 10, 2026·CARSON COUNTY, Texas (KVII) — Fermi Inc. said Monday it has signed a $6.5 billion lease with AI cloud provider TensorWave for part of its ma…
- Amazon Says New Texas Data Center Won't Raise Utility Bills—But It Will Supercharge PollutionAug 10, 2026·Daily news & progressive opinion—funded by the people, not the corporations—delivered straight to your inbox. Small town residents raise co…
- [9]AOL.comAmazon data center plant in Texas could become America’s biggest polluterAug 9, 2026·The Independent and Yahoo will earn a commission from purchases made via links in this article. Pricing and availability are subject to chan…
- [10]J.P. MorganPowering progress: Financing the infrastructure behind US data center growthAug 10, 2026·Putting our long-tenured investment teams on the line to earn the trust of institutional investors. Direct access to market leading liquidi…
- PUCT Control No. 58000 Item 20: Comments from 350 Texans about PUCT proposed rule 58000Aug 10, 2026·Filed with the Public Utility Commission of Texas on 2026-08-10. Control Number: 58000 Item Number: 20 Item Type: PC Utility Type: E Filing …
- [12]El Paso MattersMeta-Abbott agreement on data center guidelines appears to have no effect on El Paso plansAug 10, 2026·Meta’s agreement with Gov. Greg Abbott to a series of guidelines for data center operations in Texas – including paying for their electric i…
- [13]Texas TribuneHere’s how to find information about data centers in TexasAug 11, 2026·This story was supported by the Pulitzer Center. Data center proposals are sprouting up in neighborhoods all across the state. And Texans h…
- While data centers boom in Texas, their plans stay shrouded in secrecyAug 10, 2026·This story was supported by the Pulitzer Center. BELLS — Last year, Mason McCallister saw survey markers on a property near his home in a r…
- Are Greg Abbott's new data center restrictions enough to sway rural voters?Aug 11, 2026·Texas Governor Greg Abbott holds a press conference to share the latest information from flooding around Texas before providing an update to…