Monday, September 28, 2026
A 500 MW Site Posts $25 Million Before ERCOT Studies Begin
Oregon's city pauses raise the cost of late community work as Texas requires $50K/MW before ERCOT studies and Meta's 366 MW El Paso path faces a ratepayer gate. Developers who file complete packages into Texas’s power and water audits keep schedule optionality while capital is already posted.
Today's Lead
The structure replaces the March draft’s non-refundable fee and applies to first-time 75 MW sites, 75 MW expansions, and existing large loads adding another 75 MW. Collateral sits on gross contracted peak, with no carve-out for on-site generation or net imports. Exit before study start recovers the full post (minus utility charges); exit after capacity allocation forfeits 20 percent tied to allocated MW. Miss the 24-month energization window after the scheduled date and the TSP or DSP can apply remaining security to unpaid balances.
Governor Greg Abbott’s TCEQ permit hold still runs in parallel with ERCOT power audits and Texas Water Development Board water audits, so capital sits posted while environmental approvals stay frozen. Queue position now has a hard carrying cost either way.
NATIONAL CONTEXT
Colorado is the inverse signal. Vantage Data Centers’ proposed Trident campus near Aurora targets 500 MW full build as a permitted industrial use, so city staff can approve it without a planning-commission hearing. Denver already imposed a moratorium on new data center applications in May while a working group drafts rules; roughly one-third of the state’s population now sits in jurisdictions with paused applications. Spokane County approved a four-month pause on August 18, 2024 that expired December 15, 2024. The City of Spokane’s separate moratorium, effective June 22, 2024, expires in June 2027. Filing into unstable zoning still prices as political risk, not speed.
Power
El Paso gas path hits a ratepayer gate
Judges found no cost-benefit study, no RFP before vendor selection, and a process driven by Meta subsidiary Wurldwide on timeline preference. Commissioners have not set a vote date. Separately, early reports flag Oracle’s force majeure notice on Stack’s 2.45 GW Project Jupiter in New Mexico, tying delayed rent to a missed March 2028 power target and putting CDS pricing at record highs. Texas operators need generation paths that survive alternatives review and state permitting on the same clock as the new $50,000/MW security post. A denial or ratepayer-only condition leaves Meta short of a committed feed while security and audit clocks still run.
Water
Cooling design is now the political filter
Immersion cooling is the other path operators are buying. It can hold extra power for cooling and the building to about 1 to 5 percent above what the servers draw, against about 56 percent at a typical site, and it uses less cooling-tower water. Nearly all commercial immersion fluids are PFAS-class chemistries, and producers are expanding capacity for AI loads. Closed-loop marketing does not erase maintenance-cycle release risk or long-run groundwater liability. Sites that still plan large potable draws into the TWDB audit window carry longer holds; sites that swap water risk for unmodeled chemistry risk may trade one denial path for another.
Politics
Local cost frames are professionalizing the fight
Google’s Project Suncatcher, SpaceX concepts, and Starcloud’s FCC filing for large satellite counts keep orbital compute in the conversation, with Sens. Ted Cruz (R-TX) and John Hickenlooper (D-CO) having teed up a Pentagon pilot. Heat rejection in vacuum still scales radiator area with megawatts, so orbit is a pressure gauge on terrestrial politics, not a near-term substitute in the ERCOT queue. Developers who treat community benefit, water offsets, and audit-ready disclosure as optional will meet the same professionalized local opposition that is already writing moratoria elsewhere. The ones who file complete packages into Texas’s power and water audits keep schedule optionality while capital is already posted.
Sources we cited
15 articles across 15 publishers · 424 reviewed today
- PUCT sets financial commitments for data center interconnection as governor pauses permit approvalsSep 25, 2026·On September 18, 2026, the Public Utility Commission of Texas (PUCT) issued a rule standardizing interconnection requirements, capital contr…
- Sponsored: Beyond power availability: What makes a data center project power-readySep 28, 2026·The question has evolved from "Is there power?" to "Is there a credible project behind the request, and can that power actually be delivered…
- The AI Data Center Boom Faces a New Reality CheckSep 27, 2026·Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Glo…
- Why does Oregon have so many data centers? And why do we need more? - Tri-City HeraldSep 27, 2026·Tech companies have built gigantic data centers in Oregon for over 20 years. Now, even the rumor of a new data center coming to a community …
- [5]Daily KosColorado’s largest data center could rise next to homes—without a public hearingSep 26, 2026·The proposed campus would consume 11 times the power of Denver International Airport; as it has across the country, opposition mounts. By J…
- Spokane-area data center proposals, explainedSep 25, 2026·The debate over data centers in Spokane County has heated up like an overloaded digital server rack buzzing — not with electricity, but with…
- Texas electric utility only considered gas to power $10 billion Meta data centerSep 26, 2026·Administrative judges recommend approval of the gas power plant if the utility assures ratepayers won't pay the cost. The post Texas electri…
- Oracle Notifies Delay in Rent Payments for New Mexico Data Center — A Warning Sign for AI Infrastructure FinancingSep 27, 2026·Oracle, a major computing infrastructure operator, has notified the developer of its New Mexico data center that it intends to delay the sta…
- [9]Dallas NewsAs data center wars intensify, a Dallas startup takes a different approachSep 26, 2026·Dallas startup Mousterian is planning to put its data centers on water to help with cooling and water usage. Data centers are blamed for be…
- Data Centers Are Swapping Water for PFAS Cooling. The Fix Has a CatchSep 28, 2026·Data centers have a water problem. The cooling systems that keep servers from melting have become the most politically explosive part of the…
- [11]The Tech BuzzAI Data Center Boom Creates Blue-Collar Job Surge Amid BacklashSep 26, 2026·The Tech Buzz may earn a commission when you buy through links on this page. This never affects which products we recommend or what we say a…
- AI’s data center problem could move to spaceSep 26, 2026·For years, the sprawling warehouses powering artificial intelligence have been built on Earth, consuming enormous amounts of electricity and…
- [13]WIREDThe Data Center Backlash Should Also Be a Climate Reckoning. It Isn’t YetSep 27, 2026·Welcome to the latest edition of Power Play! From now until the midterms, senior writer Molly Taft will be sharing their thoughts every Sund…
- 5 Notable Data Center Links, Sept 26Sep 26, 2026·Each week I curate 5 links from the data center sector that I find particularly interesting, with my commentary on why they merit your atten…
- [15]NOLA.comNuclear reactors, data center campuses, gas-powered plants proposed in Iberville, AscensionSep 28, 2026·A AI-generated rendering shows One Nuclear Energy's three projects proposed for Louisiana, with Amberjack, a pair of small modular nuclear r…