Tuesday, September 29, 2026
ALJs Condition Meta's 366 MW Gas on El Paso Electric Absorbing Every Dollar
Meta's $10B, 366 MW gas package advances only if El Paso Electric absorbs every dollar, even as Spokane and Colorado have paused datacenter permits. Developers who lock power, water, and ratepayer terms early still clear Texas capacity frozen markets can't offer.
Today's Lead
Without that condition they recommend denial, citing no competitive RFP, no cost-benefit work, and a $499 million, 813-unit Enchanted Rock fleet timed to a Meta subsidiary’s preferences. Commissioners have not set a vote; denial strands the dedicated gas Meta specified, while conditional approval puts the carrying cost back on the utility before energization.
The campus is a 1 GW Meta project. The McCloud package would serve that campus alone for five years, then tie into the wider grid. El Paso Electric told the proceeding it had looked at solar, then moved to gas in December. The judges wrote that the choice followed the timeline and preferences of Wurldwide, the Meta subsidiary named on the application. The City of El Paso intervened. A July hearing drew comments from the Sembrando Esperanza Coalition. Organizer Verónica Carbajal said the commission should have denied the application. Meta had already signed El Paso tax abatements and started construction before the statewide permit suspension.
NATIONAL CONTEXT
Virginia’s corridor is already power-tight: Dominion Energy Virginia sells 28 percent of its volume to data centers, and the state imports about a quarter of its electricity. Oregon is weighing limits on water-intensive cooling. These are site-selection filters, not templates; capital still clears faster in markets that keep permits moving for operators who engage early on power, water, and rates.
Power
Gigawatt deals now price hybrid supply and dedicated gas
Natural Gas Pipeline Company of America has asked FERC for a 550,000 Dth/d Texas Panhandle expansion tied to a planned Google campus, per early trade reporting, a rare named-load anchor on pipeline capital. Oracle’s force majeure notice to Stack on Project Jupiter, a 2.45 GW New Mexico build valued at $165B, delays rent if the site misses March 2028 and puts pressure on Oracle’s 4.5 GW OpenAI-linked slate across New Mexico, Texas, Wisconsin, and Michigan.
Watch FERC certificate timing and any Texas capacity Oracle restates in quarterly filings; a slip converts posted generation and interconnection capital into pure carrying cost.
Water
Cooling answers now decide county votes and audit risk
Immersion cooling is scaling with rack density, yet ChemSec reported in September 2026 that all ten largest PFAS producers are expanding specifically for AI infrastructure. Operators trading municipal gallons for fluorinated coolants gain efficiency scores near 1.01, 1.05 on site power above server load, and they also inherit leakage, maintenance, and disposal liability that has not been proven at fleet scale.
Fail the water narrative at county hearing or under the state audit and the MW position never reaches revenue.
Politics
Pause, protests, and labor set who still has a calendar
El Paso groups lodged over 1,000 comments against the Meta gas package on air, water, and rates, and a planned Cedar Creek Lake facility near Fort Worth was scrapped after neighborhood pushback. Trade demand is real at $75,000-$120,000 wages and 200-500 construction jobs per hyperscale site, yet HVAC and liquid-cooling certifications lag the build rate.
Projects that lock local workforce pipelines, publish cooling and ratepayer terms before the next hearing, and keep audit-ready load evidence on file hold their place; the ones waiting for the pause to lift without that package burn quarters of carrying cost.
Sources we cited
14 articles across 14 publishers · 509 reviewed today
- Texas electric utility only considered gas to power $10 billion Meta data centerSep 26, 2026·Administrative judges recommend approval of the gas power plant if the utility assures ratepayers won't pay the cost. The post Texas electri…
- Sponsored: Beyond power availability: What makes a data center project power-readySep 28, 2026·The question has evolved from "Is there power?" to "Is there a credible project behind the request, and can that power actually be delivered…
- Spokane-area data center proposals, explainedSep 25, 2026·The debate over data centers in Spokane County has heated up like an overloaded digital server rack buzzing — not with electricity, but with…
- [4]Daily KosColorado’s largest data center could rise next to homes—without a public hearingSep 26, 2026·The proposed campus would consume 11 times the power of Denver International Airport; as it has across the country, opposition mounts. By J…
- Where America First Meets the Digital Economy: Lessons from Virginia’s Data Center Alley – AFPISep 28, 2026·This document was prepared with the support of OFRA AI tools. This brief lays out eighteen policy options, at every level of government, th…
- AI Data Center Boom Creates Blue-Collar Job Surge Amid BacklashSep 26, 2026·The Tech Buzz may earn a commission when you buy through links on this page. This never affects which products we recommend or what we say a…
- The 200 GW Moment: Reinventing the Grid for the AI EconomySep 29, 2026·As AI pushes rack densities into unprecedented territory, utilities, hyperscalers, and developers are rethinking how to deliver reliable, af…
- Google Data Center Anchors 550,000 Dth/d NGPL Natural Gas Expansion in TexasSep 28, 2026·By …
- Oracle Notifies Delay in Rent Payments for New Mexico Data Center — A Warning Sign for AI Infrastructure FinancingSep 27, 2026·Oracle, a major computing infrastructure operator, has notified the developer of its New Mexico data center that it intends to delay the sta…
- The AI Data Center Boom Faces a New Reality CheckSep 27, 2026·Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Glo…
- [11]Dallas NewsAs data center wars intensify, a Dallas startup takes a different approachSep 26, 2026·Dallas startup Mousterian is planning to put its data centers on water to help with cooling and water usage. Data centers are blamed for be…
- Data Centers Are Swapping Water for PFAS Cooling. The Fix Has a CatchSep 28, 2026·Data centers have a water problem. The cooling systems that keep servers from melting have become the most politically explosive part of the…
- [13]White & Case LLPPUCT sets financial commitments for data center interconnection as governor pauses permit approvalsSep 25, 2026·On September 18, 2026, the Public Utility Commission of Texas (PUCT) issued a rule standardizing interconnection requirements, capital contr…
- AI’s data center problem could move to spaceSep 26, 2026·For years, the sprawling warehouses powering artificial intelligence have been built on Earth, consuming enormous amounts of electricity and…