Subscribers already knew this. Get real-time access →

Tuesday, September 29, 2026

ALJs Condition Meta's 366 MW Gas on El Paso Electric Absorbing Every Dollar

Meta's $10B, 366 MW gas package advances only if El Paso Electric absorbs every dollar, even as Spokane and Colorado have paused datacenter permits. Developers who lock power, water, and ratepayer terms early still clear Texas capacity frozen markets can't offer.

Today's Lead

Administrative law judges at the Public Utility Commission of Texas proposed approving El Paso Electric’s 366 MW modular gas package for Meta’s $10 billion northeast El Paso campus only if the utility absorbs every capital and operating dollar.

Without that condition they recommend denial, citing no competitive RFP, no cost-benefit work, and a $499 million, 813-unit Enchanted Rock fleet timed to a Meta subsidiary’s preferences. Commissioners have not set a vote; denial strands the dedicated gas Meta specified, while conditional approval puts the carrying cost back on the utility before energization.

The campus is a 1 GW Meta project. The McCloud package would serve that campus alone for five years, then tie into the wider grid. El Paso Electric told the proceeding it had looked at solar, then moved to gas in December. The judges wrote that the choice followed the timeline and preferences of Wurldwide, the Meta subsidiary named on the application. The City of El Paso intervened. A July hearing drew comments from the Sembrando Esperanza Coalition. Organizer Verónica Carbajal said the commission should have denied the application. Meta had already signed El Paso tax abatements and started construction before the statewide permit suspension.

NATIONAL CONTEXT

Spokane County approved a four-month datacenter permit pause effective August 18 and expiring December 15. The City of Spokane began a separate one-year pause the same day, with expiration in June 2027. In Colorado, jurisdictions representing roughly one third of the state’s population have paused applications after Denver City Council voted in May for a datacenter moratorium of at least a year, even as Vantage advances a 500 MW Trident campus near Aurora under industrial-zone staff approval before local rules harden.

Virginia’s corridor is already power-tight: Dominion Energy Virginia sells 28 percent of its volume to data centers, and the state imports about a quarter of its electricity. Oregon is weighing limits on water-intensive cooling. These are site-selection filters, not templates; capital still clears faster in markets that keep permits moving for operators who engage early on power, water, and rates.

Power

Gigawatt deals now price hybrid supply and dedicated gas

At Data Center World Power in Dallas, NRG Business executive vice president Scott Hart said customer talks now run to a gigawatt and beyond, against utility planning built on 15-year offtake. Hybrid grid supply, on-site generation, storage, and demand response is the structure sponsors will finance; Hart said most projects his team touches are open to curtailment incentives.

Natural Gas Pipeline Company of America has asked FERC for a 550,000 Dth/d Texas Panhandle expansion tied to a planned Google campus, per early trade reporting, a rare named-load anchor on pipeline capital. Oracle’s force majeure notice to Stack on Project Jupiter, a 2.45 GW New Mexico build valued at $165B, delays rent if the site misses March 2028 and puts pressure on Oracle’s 4.5 GW OpenAI-linked slate across New Mexico, Texas, Wisconsin, and Michigan.

Watch FERC certificate timing and any Texas capacity Oracle restates in quarterly filings; a slip converts posted generation and interconnection capital into pure carrying cost.

Water

Cooling answers now decide county votes and audit risk

Mousterian, a Dallas startup, is designing floating campuses that use surrounding water for closed-loop cooling, skip municipal supply, and site near power plants instead of residential edges. On September 21, Governor Greg Abbott directed the Texas Commission on Environmental Quality to suspend issuance of datacenter permits. White & Case’s account of that order says the TCEQ suspension waits on an ERCOT grid review. The same alert names a separate TWDB review of water adequacy, and it states no end date.

Immersion cooling is scaling with rack density, yet ChemSec reported in September 2026 that all ten largest PFAS producers are expanding specifically for AI infrastructure. Operators trading municipal gallons for fluorinated coolants gain efficiency scores near 1.01, 1.05 on site power above server load, and they also inherit leakage, maintenance, and disposal liability that has not been proven at fleet scale.

Fail the water narrative at county hearing or under the state audit and the MW position never reaches revenue.

Politics

Pause, protests, and labor set who still has a calendar

The TCEQ suspension covers datacenter sites still in environmental permitting. Under the September 18 PUCT rule, a single-site load of 75 MW or more posts $50,000 per MW as financial security before an interconnection study begins. The rule returns that security in 20 percent steps as billing-demand milestones are met. A customer that exits before the study begins receives the posting back, minus outstanding costs. A flat $100,000 study fee is a separate charge. Community opposition has blocked, withdrawn, or stalled more than $170 billion in proposed U.S. datacenter capacity since January 2024, according to advisory firm Relae, a thin-source rollup that still matches the protest volume showing up in Texas filings.

El Paso groups lodged over 1,000 comments against the Meta gas package on air, water, and rates, and a planned Cedar Creek Lake facility near Fort Worth was scrapped after neighborhood pushback. Trade demand is real at $75,000-$120,000 wages and 200-500 construction jobs per hyperscale site, yet HVAC and liquid-cooling certifications lag the build rate.

Projects that lock local workforce pipelines, publish cooling and ratepayer terms before the next hearing, and keep audit-ready load evidence on file hold their place; the ones waiting for the pause to lift without that package burn quarters of carrying cost.

Sources we cited

14 articles across 14 publishers · 509 reviewed today

  • Texas electric utility only considered gas to power $10 billion Meta data center
    Sep 26, 2026·Administrative judges recommend approval of the gas power plant if the utility assures ratepayers won't pay the cost. The post Texas electri…
  • Sponsored: Beyond power availability: What makes a data center project power-ready
    Sep 28, 2026·The question has evolved from "Is there power?" to "Is there a credible project behind the request, and can that power actually be delivered…
  • Spokane-area data center proposals, explained
    Sep 25, 2026·The debate over data centers in Spokane County has heated up like an overloaded digital server rack buzzing — not with electricity, but with…
  • Colorado’s largest data center could rise next to homes—without a public hearing
    Sep 26, 2026·The proposed campus would consume 11 times the power of Denver International Airport; as it has across the country, opposition mounts. By J…
  • Where America First Meets the Digital Economy: Lessons from Virginia’s Data Center Alley – AFPI
    Sep 28, 2026·This document was prepared with the support of OFRA AI tools. This brief lays out eighteen policy options, at every level of government, th…
  • AI Data Center Boom Creates Blue-Collar Job Surge Amid Backlash
    Sep 26, 2026·The Tech Buzz may earn a commission when you buy through links on this page. This never affects which products we recommend or what we say a…
  • The 200 GW Moment: Reinventing the Grid for the AI Economy
    Sep 29, 2026·As AI pushes rack densities into unprecedented territory, utilities, hyperscalers, and developers are rethinking how to deliver reliable, af…
  • Google Data Center Anchors 550,000 Dth/d NGPL Natural Gas Expansion in Texas
    Sep 28, 2026·By …
  • Oracle Notifies Delay in Rent Payments for New Mexico Data Center — A Warning Sign for AI Infrastructure Financing
    Sep 27, 2026·Oracle, a major computing infrastructure operator, has notified the developer of its New Mexico data center that it intends to delay the sta…
  • The AI Data Center Boom Faces a New Reality Check
    Sep 27, 2026·Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Global Oil Prices Click Here for 150+ Glo…
  • As data center wars intensify, a Dallas startup takes a different approach
    Sep 26, 2026·Dallas startup Mousterian is planning to put its data centers on water to help with cooling and water usage. Data centers are blamed for be…
  • Data Centers Are Swapping Water for PFAS Cooling. The Fix Has a Catch
    Sep 28, 2026·Data centers have a water problem. The cooling systems that keep servers from melting have become the most politically explosive part of the…
  • PUCT sets financial commitments for data center interconnection as governor pauses permit approvals
    Sep 25, 2026·On September 18, 2026, the Public Utility Commission of Texas (PUCT) issued a rule standardizing interconnection requirements, capital contr…
  • AI’s data center problem could move to space
    Sep 26, 2026·For years, the sprawling warehouses powering artificial intelligence have been built on Earth, consuming enormous amounts of electricity and…