Weekly recap · Jun 15 – 20, 2026
ERCOT's Batch Zero Sorts 418 GW of Datacenter Demand
Texas spent the week turning a flood of power demand into a sorting problem, and the winners are already clear: projects with site control, secured generation, and water plans ready before the hearing.
The week in briefings
- Mon Jun 15Texas's June 23 Hearing Opens the Water Rulebook Before It Hardens
- Tue Jun 16Developers Foot 100% of the Wire. Ratepayers Get the Discount.
- Wed Jun 17Sid Miller Backs a Moratorium. Abbott Rewrites the Rules Instead.
- Thu Jun 18225 Interconnection Requests, One Filter: ERCOT Sorts Real From Paper
- Fri Jun 19Site Control Now Beats a Press Release in ERCOT's Queue
- Sat Jun 20Behind-the-Meter Buys a Speed Premium: Why Google Runs Its Own Power
ERCOT Rewrites the Queue
The structural shift landed June 18, when the Public Utility Commission of Texas approved Batch Zero, a solvency screen forcing projects above 75 MW to prove site control, post nonrefundable fees, and show credible financing before holding a queue position. The numbers behind the move are stark: more than 480 large datacenters have applied to connect through 2032, requesting 418 GW, nearly five times the state's all-time peak of 85.5 GW. As Thu, applicants learn their status in August 2026.
The market read it instantly. Meta signed a reported 1.6 GW capacity agreement with Crusoe across Childress, Texas and Warrenton, Missouri, with the Childress interconnect tied to Lancium's ERCOT-approved 1 GW position. Fri: Crusoe's contracted capacity hit 4.9 GW against a 40 GW-plus pipeline, and the premium sits on a cleared interconnect, not a paperwork date.
Power-First Sequencing Becomes the Model
With grid delays stretching as long as 12 years, the biggest names are routing around the queue entirely. Sat: Google's new Texas datacenter is designed to run off-grid on wind, solar, batteries, and gas.
- Circe Energy's West Texas campus locked long-term gas generation from Cummins, with energization starting 2027.
- Crusoe's Abilene Stargate site won a 360 MW permit in six days, then ordered 29 GE Vernova turbines toward 1 GW.
- Bitzero locked over 1 GW across Norway, Finland, and North Dakota, signing a binding tenant letter worth up to $2.6 billion.
The catch: supply-chain risk replaces queue risk. GE Vernova is sold out through 2028, and combined-cycle lead times now run seven years. Source early, build what's available now.
Abbott Prices, Other States Pause
While 833 opposition groups across 49 states push moratoriums, Texas chose a different path. Governor Abbott directed regulators to make datacenters fund 100% of their own infrastructure while structuring interconnections so residential bills decline, with a joint PUC-ERCOT memo due July 17. As Wed of backing the moratorium Sid Miller endorsed, the framing is workable where New York's freeze offers no path. The legal wall is real: per Foley & Lardner's Scott Ellis, only the Legislature can rewrite cost-allocation authority, which is why the Mon matters now.
On water, the Tue and dedicated cooling lines win permits. Google's $10 million Lincoln, Nebraska line and Amazon's Missouri infrastructure transfer show the playbook. In El Paso, the water math held at 400,000 gallons daily; the benefit-sharing case didn't.
What to Watch
- June 23: Texas House Natural Resources Committee hearing on datacenter water use, with public testimony open.
- July 17 and July 31: PUC-ERCOT joint memo, then PUC transmission-cost action deadlines.
- August 2026: Batch Zero status notifications, the first real stress test for site control and financing.
- August 11: Fort Worth council vote on new development rules after tabling the Edged tax incentive.