July 4, 2026
Subscribe for full access
Abbott Hardens His Terms. The 2027 Legislature Holds the Pen.
Red Oak (population 15,000) already hosts or has approved six campuses, including DataBank's 300-acre site and Compass Datacenters' 830-acre complex, and Wise County officials have asked lawmakers for guardrails or veto power.
June 24, 2026
Subscribe for full access
Reeves County Banks 6,000 Jobs as the Behind-the-Meter Model Scales
DataBank's nearly 300-acre Red Oak campus south of Dallas brings DFW9 online in August, the first of eight bu
April 24, 2026
Cancellations Quadrupled. Abilene's 2.1 GW Answer Is Off the Grid.DataBank's $2 billion MUFG-led loan for 180 MW at Red Oak south of Dallas shows the other side: institutional capital flows to developers with signed anchor tenants and proven power procurement.
April 23, 2026
Capital Front-Runs the Forecast: $2B Lands Before ERCOT Hits 367 GWDataBank just closed a $2 billion construction loan, its largest ever, to accelerate its 300-acre Red Oak campus 20 miles south of Dallas by 18 months.
April 22, 2026
Moratoriums, Referendums, and Ultimatums: The New Permit MathDataBank closed $2 billion from MUFG for its Red Oak campus in DFW, three fully-leased buildings totaling 180 MW