Agencies

ERCOT

ERCOT (Electric Reliability Council of Texas) operates the electric grid that serves approximately 90% of Texas and manages the wholesale electricity market for that region.

Referenced in 183 briefingsLast referenced: September 26, 2026

Mentions

September 26, 2026

Subscribe for full access

Google Puts BESS and LVDC on Record as the Gigawatt Campus Standard

September 25, 2026

Subscribe for full access

Oct. 14 TWDB Deadline Now Carries Class C Exposure in 18 Counties

September 23, 2026

Subscribe for full access

Vistra's 5% Stake and 207 MW Firm PPA Open New Era's 1.4 GW Midland Path

September 22, 2026

Subscribe for full access

Gov. Abbott Ties Noncompliance to Denial of Grid Connection

September 21, 2026

Subscribe for full access

Vegas Won't Sign the $6.4M ERCOT Deal After Lt. Gov. Patrick's Call

September 19, 2026

Subscribe for full access

PUCT Locks $50K/MW Study Bond Into 16 TAC 25.194, Effective Oct 8

September 17, 2026

Subscribe for full access

Documentary Survival Now Prices 266 GW Energization to Dec. 10

September 16, 2026

Subscribe for full access

DataBank CEO: Opposition Is Election-Tier as 24-Mo Texas Deals Still Ship

September 14, 2026

Subscribe for full access

Rowan's $4.2B Cleared Water and Power; One Zoning Vote Remains Sept. 17

September 12, 2026

Subscribe for full access

1,100 Acres Enter Site Work Before Cameron Names Load or Tenant

September 10, 2026

Subscribe for full access

Selene, Horizon Junction, and Hubbard Stack in One Multi-GW Texas Window

September 9, 2026

Subscribe for full access

Google's 25-Year Iowa Deal and 22-Year Fortum Contract Put Power Terms First

September 5, 2026

Subscribe for full access

North Richland Hills Seeks State-Funded Health Studies at Iron Horse

September 4, 2026

Subscribe for full access

Control No. 58481 Puts $50K/MW Floor Before ERCOT Models 1 GW

September 3, 2026

Subscribe for full access

Prosper Zoning Blocks White Rose's $580M on 1,600 Precinct Votes

September 2, 2026

Subscribe for full access

Fermi Cleared 6 GW Air in 205 Days; Denied ROW Still Cuts Jupiter's 2.45 GW

August 26, 2026

Tranche Power Gates Blackstone's Three AI Factory Campuses

She argues Oncor leans on ERCOT's Permian Basin Reliability Plan without ERCOT as a SOAH party, blocking cross-examination of the core study, and she puts uncompensated property-value exposure above $10 billion if both projects proceed.

August 22, 2026

Dec. 10 Community Impact Review Can Deny Grid Connection

ERCOT will complete Governor Greg Abbott's data center and large-load audit by December 2026, with the Batch Zero Eligibility Verification Report and Community Impact Review due December 10 and findings at the PUCT's December 17 open meeting.

August 12, 2026

SpaceX's $16.8B Terafab Puts Gas and Batteries on the Critical Path

Requirements that matter on a balance sheet: fund transmission and distribution, disclose on-site generation and grid-reduction measures, map water source and consumption, document taxpayer incentives, and address noise, lighting, setbacks, traffic, and emergency coordination, with PUCT and ERCOT audit before grid connection and denial for failure.

August 3, 2026

Meta's El Paso Campus Hits 1 GW Without Buying a Single Server

The PUCT and ERCOT are petitioning the Legislature for expanded authority over data centers, following Governor Greg Abbott's directive to manage grid and infrastructure impact, according to a podcast discussion flagged by the Texas Energy and Power Newsletter.

July 26, 2026

Sen. Huffman's January Bill Targets the Exemption That Built Fermi and Stargate

As of July 23 the company hasn't filed an interconnection request or local permits, which means the full sequencing timeline still sits ahead: study backlog, queue position behind hundreds of applications, and separate gas-siting permission if it repeats the Memphis hybrid model of grid-plus-on-site generation.

June 26, 2026

Five Tests Now Separate Real Load From Speculation in Texas

The Public Utility Commission of Texas approved ERCOT's "Batch Zero" study in June 2026, a centralized process that separates committed gigawatt-scale loads from speculative requests through readiness tests: site control, permits, financing, equipment orders, realistic demand forecasts.

May 20, 2026

Water Plan Skips the 400 GW Queue. Smart Developers Won't.

Eric Goff of Goff Policy calls the queue "effectively infinite," and ERCOT's "Batch Zero" framework, plus the first PUCT-approved 765 kV lines and the ERCOT Board's $9.4 billion Eastern Backbone, are the mechanisms that convert queue position into construction schedule.

May 16, 2026

Beacon Point Sets the 1-GW Template While 300 GW Wait in Queue

Risk: with ERCOT's queue exceeding 300 GW and Deloitte projecting AI datacenter demand at 123 GW by 2035, developers without an executed interconnection agreement and a credible firm-generation path won't energize on the timelines their leases assume.

May 1, 2026

Fort Bliss Becomes the Borderland's Third Gigawatt Build in 18 Months

ERCOT's interconnection queue hit 432 GW against 85.5 GW peak demand, and Caprock Renewables founder Raina Hornaday describes the resulting shift as "the energization of land," with distributed generation and behind-the-meter resources outpacing transmission-dependent models.

April 25, 2026

PUCT Just Drew the Line on Which Grid Bypasses Count

The Public Utility Commission of Texas unanimously approved the first direct wind-farm-to-datacenter connection on the ERCOT grid, the same week ERCOT's high-side demand scenario, peak load above 367,000 MW by 2032, was sent back as unrealistic.

April 19, 2026

Anchored Offtake Wins the Queue. Speculation Gets Repriced.

ERCOT's preliminary Long-Term Load Forecast projects Texas peak demand reaching 367.8 GW by 2032, more than four times the August 2023 record of 85.5 GW, with non-crypto data center load climbing from 7.4 GW in 2026 to 228.4 GW.

April 10, 2026

Caprock Broke Ground. Projects That Can't Match It Won't.

Aligned Data Centers broke ground on Project Caprock, a 540MW, $5 billion campus near Abernathy in Hale County, while at the Capitol, lawmakers grilled ERCOT and PUC officials on who pays for the state's data center surge, and Google confirmed a 933MW natural gas plant under construction in Armstrong County.

April 9, 2026

Nine Months to Shape the Rules Texas Is About to Write

ERCOT's interconnection queue has ballooned to 410 gigawatts of requested capacity by 2030, nearly five times the grid's all-time peak of 85.5 GW, forcing the grid operator and the Public Utility Commission to improvise new rules in real time.

April 7, 2026

Medina County Told Microsoft No. Here's the Playbook It Used.

Gov. Abbott's press secretary stated facilities "are required to bring their own power and to disconnect if Texans don't have what they need," and regulators require large data centers to register with ERCOT and the PUC, provide backup power, and help fund grid upgrades.

March 23, 2026

NextEra Bets $16 Billion That Texas Demand Is Real

NextEra Energy secured federal approval to build 10GW of natural gas generation across Texas and Pennsylvania, anchored by a 5.2GW, $16 billion Project Anderson in Anderson County that will feed directly into ERCOT.

March 15, 2026

Solve Water Before You Break Ground, or Else

Early reports suggest these projects still face ERCOT's severe interconnection backlog; any queue delays push Google toward supplemental gas procurement, undermining the renewable supply strategy.

March 11, 2026

Texas Developers Need No Permission. Rural Counties Are Changing That.

The resolution, sent to Governor Abbott, Lt. Gov. Patrick, the PUCT, ERCOT, and the Texas Water Development Board, follows a public hearing that drew roughly 90 residents and reflects a pattern now visible across Hood County, Somervell County, and Jack County simultaneously.

March 3, 2026

Gigawatt Ambitions, County-Level Resistance: Who Blinks First?

The GW Ranch project in West Texas takes this to its logical extreme: an 8,000-acre facility generating its own electricity from on-site gas and solar, consuming more power than all of Chicago while avoiding ERCOT interconnection queues altogether.

February 20, 2026

Big Tech's Grid Bypass Meets a 14-State Backlash

In Texas, this trend compounds ERCOT's planning challenge: if the largest loads bypass the grid entirely, transmission investment assumptions and reliability models built around centralized dispatch become unreliable.

February 13, 2026

Capital Keeps Pouring In. Communities Are Closing the Gate.

Texas isn't named in this legislative wave, but the trend is directly relevant: ERCOT's deregulated market creates different cost-shifting dynamics, and Texas's competitive posture could attract developers fleeing states with new rate guardrails, concentrating even more load on the Texas grid.

Frequently mentioned alongside