April 12, 2026
Subscribe for full access
400 Projects, Two Unanswered Questions, One Legislative Clock
Skybox Data Centers told legislators a typical 150,000 to 300,000 square foot facility needs only 25,000 to 30,000 gallons of initial water charge at a 2% loss rate.
February 16, 2026
States Race to Write the Rules Before the Next Megawatt Comes OnlineIn Texas, operators like Skybox claim closed-loop systems equivalent to 15 homes' consumption, but the aggregate impact of eight approved data centers in Round Rock alone, with six not yet operational, remains unquantified.