Dona Ana County, New Mexico is located adjacent to Texas and has been considered as a potential alternative location for data center development due to its proximity to Texas power markets and lower land costs compared to major Texas metropolitan areas.
Referenced in 1 briefingLast referenced: September 26, 2026
Separately, Oracle invoked force majeure on Project Jupiter, the 2.4 GW STACK Infrastructure campus in Dona Ana County, New Mexico, tied to OpenAI and a Bloom Energy fuel-cell microgrid; Blue Owl put up $3B equity against an $18B debt facility, and pieces of that debt have traded below 90 cents on the dollar.