26 Cancellations Later, the Rules of Site Selection Have Changed

$98 billion in delayed or blocked projects in a single quarter, 26 cancellations in two months, and less than half of Americans willing to host a datacenter near them: community opposition has become a structural constraint, not a situational one. Every market from San Marcos to Pennsylvania to Ohio is repricing political risk in real time, and operators still treating this as a permitting problem are solving for the wrong variable.

Today's Lead

Community opposition has become the single biggest structural threat to datacenter expansion in the U.S., and the numbers are staggering. Data Center Watch research pegs $98 billion in projects delayed or blocked in a single quarter of 2025; The Guardian documented 26 project cancellations in just December 2025 and January 2026, up from one in October. Heatmap Pro polling shows less than 50% of Americans support datacenter development near them, with opposition cutting across party lines and strongest among voters aged 18-49, suggesting the problem deepens generationally. From San Marcos, Texas (where a $1.5 billion campus was killed by a 5-2 council vote) to Virginia (where voters elected a governor who campaigned on forcing the sector to pay more) to Ohio (where moratoriums are spreading), the pattern reflects a resource-driven political realignment that's rewriting the rules for every major market.

Politics

Pennsylvania Loads the Regulatory Gun While Other States Follow

Pennsylvania's General Assembly is moving multiple bills simultaneously that would reshape datacenter economics. HB 2150 (mandatory energy and water consumption reporting) and HB 2151 (model municipal zoning ordinance) both cleared the House Energy Committee 14-12 on party-line votes on March 2. More consequential: Sen. Katie Muth has circulated a memo for a three-year statewide moratorium on hyperscale development.

Meanwhile, Senate Bill 939, originally a fast-track permitting bill, was gutted: provisions accelerating approvals were stripped, and it now requires developers to secure their own power supply rather than tap existing grid capacity. HB 1834 would mandate datacenters source at least 25% of electricity from renewable or nuclear generation produced in Pennsylvania.

Pennsylvania is part of a broader wave. Ohio's Adams County is fighting a 1,300 MW project permitted by the Army Corps without public comment, with three citizen petitions demanding everything from county zoning restrictions to a constitutional ban on datacenters statewide. Lordstown, Ohio imposed a six-month moratorium. The regulatory patchwork is fragmenting fast. Developers who assumed permitting speed would carry them through 2026 need to reprice political risk in every jurisdiction.

Power

CyrusOne Tops Out in Bosque County as Texas Becomes the Integrated Power Play

CyrusOne topped out DFW10, a $750 million, 250,000 sq ft building at its new 400+ MW campus in Bosque County, Texas, adjacent to Calpine's 250 MW Thad Hill Energy Center. The co-location model is the story: dedicated natural gas generation anchoring a hyperscale campus, bypassing the interconnection queue bottleneck that plagues grid-dependent projects.

DFW11, a $400 million companion building, targets August 2027. At least three additional structures are planned. CyrusOne now operates 14+ facilities across Texas, with over half in DFW, and this campus extends its footprint into the I-35 corridor between DFW and Waco.

Separately, Stream Data Centers tripled its planned New York investment to $19.46 billion for a 500 MW, 2.2 million sq ft campus in Genesee County, repurposing a failed green hydrogen site with existing substation infrastructure. An unnamed AA-rated Fortune 50 tenant anchors the deal. A public hearing is set for March 19.

The integrated power model CyrusOne is deploying in Texas will become the template as grid interconnection timelines stretch. But Bosque County water sourcing for future phases remains undisclosed, and CyrusOne hasn't revealed power contracts beyond Calpine's initial 250 MW allocation. If the campus scales to 400+ MW, the gap between generation and demand is a watch item.

Power

Renewables Pipeline Stalls Just as Datacenter Demand Surges

U.S. renewable energy hit a record 50+ GW of additions in 2025, but the pipeline is cracking. The American Clean Power Association reports quarterly pipeline growth averaging just 1%, and utility/commercial power purchase announcements fell 36% year-over-year. Battery storage surged 16% (led by Arizona, California, and Texas), while offshore wind pipelines contracted 23%.

The policy overhang is real: a new 10% global import tariff (with threatened increases to 15%), and Interior Department executive order 14315 requiring Secretary Burgum's office to review all solar and wind leases and permits. ACP's John Hensley told Latitude Media the result isn't a clear shutdown but a permitting fog: "It's not like we're seeing systemic adjustments."

For Texas datacenter operators, this accelerates the pivot toward gas-backed hybrid systems and behind-the-meter generation. Texas already leads in battery storage deployment. But if new generation of any type slows while datacenter load doubles through the decade, the timing mismatch could force ERCOT into tighter reserve margins. Watch DOI permit processing timelines and the tariff implementation window ending late July.

Power/Politics

Transmission Lines Are the Next Battlefront, and Texas Is Already in the Fight

Datacenters aren't the only infrastructure drawing opposition; the power lines feeding them are too. Transmission spending is projected to nearly double to $50 billion annually from 2019 to 2028. In Pennsylvania, the proposed Sugarloaf line demands 240-foot steel towers and 200-foot corridors spanning hundreds of miles, displacing landowners.

In Texas, the Hill Country Preservation Coalition formed specifically to oppose three 765-kilovolt "superhighway" transmission corridors crossing the state east-west. Coalition founder Jada Jo Smith calls it "Goliath." The group is lobbying state regulators to reroute lines along existing highway corridors.

The scale of what's happening in Texas creates an unprecedented challenge: the state needs massive new transmission capacity to serve datacenter load, but the very communities that would host these lines are organizing against them. Congressional proposals to exempt transmission from state and environmental review could accelerate timelines but would strip local oversight. Whether Texas regulators prioritize routing efficiency or community accommodation on the 765 kV corridors will set precedent nationally.

Sources we cited

10 articles across 9 publishers · 179 reviewed today

  • Community Opposition Emerges as New Gatekeeper for AI Data Center Expansion
    Mar 9, 2026·The rapid global buildout of AI infrastructure is colliding with a new constraint that hyperscalers cannot solve with capital or GPUs: local
  • The Data Center Backlash Is Swallowing American Politics
    Nov 6, 2025·Activists on both the left and the right are pushing back against AI development. The techlash over data center development is becoming a p
  • It's not just data centers. New power lines for AI are also stirring local anger
    Mar 8, 2026·For John Zola, the 40 acres were like a paradise: apple orchards tucked into northern Pennsylvania’s rolling hills, a barn, meadows and more
  • Pennsylvania AI Data Center Legislation in 2026: What Companies Need to Know
    Mar 9, 2026·Pennsylvania has quietly become a key battleground for AI data center legislation. With about $90 billion in announced AI, energy, and data
  • Can tech companies bring electricity to power data centers in Pa.? - Erie Times-News
    Mar 9, 2026·A pledge by President Donald Trump that would make tech companies provide their own electricity came with fanfare at the State of the Union
  • Adams County data center gets federal permit, as voters sign petitions to block it
    Mar 9, 2026·ADAMS COUNTY, Ohio — The U.S. Army Corps of Engineers issued a permit last month to enable a data center project near the former Stuart powe
  • Is Northeast Ohio ready for AI data centers? Sustainability's a factor
    Feb 10, 2026·At the corner of East 40th Street and Chester Avenue in Cleveland sits a small, quiet brick building that blends in with many others Downtow
  • CyrusOne tops out latest Texas data center
    Mar 9, 2026·Company completes structure of first building at Bosque County campus CyrusOne has topped out its latest data center in Texas. The company
  • Stream ups planned investment in New York campus to $19.46 billion
    Mar 9, 2026·Company working with unnamed Fortune 50 company on project Stream Data Centers is expanding the scope of a planned development in the town
  • Is a renewables slowdown coming?
    Mar 9, 2026·U.S. renewables hit a 50 GW milestone in 2025, but the project pipeline is plateauing. The post Is a renewables slowdown coming?   appeared