TigerDC's withdrawal of a **$3 billion project** from Spartanburg County, South Carolina, after the county council denied a PILOT agreement, puts a price tag on political uncertainty.
In Spartanburg County, South Carolina, council killed TigerDC's tax incentive package for Project Spero after community opposition; FERC's December rejection of a 200 MW Duke Energy transmission line further complicates the project's grid access.
TigerDC's $3 billion Project Spero in Spartanburg County, South Carolina plans 550 MW of on-site natural gas generation across three phases, with Phase I targeting 100 MW by 2027.