Agencies

FERC

The Federal Energy Regulatory Commission (FERC) has jurisdiction over wholesale electricity rates and transmission planning in Texas, affecting datacenter operators' access to power markets through ERCOT.

Referenced in 23 briefingsLast referenced: July 8, 2026

Mentions

July 8, 2026

Subscribe for full access

Ratepayers Come Off the Hook. Developers Underwrite the Wires Themselves.

The teeth arrive with Project 2026-02's bridge standard, targeting a December 31, 2026 filing and FERC-binding penalties of up to $1 million per day per violation in 2027 or 2028.

July 2, 2026

Subscribe for full access

FERC Orders Six Grid Operators to Defend the Rules or Rewrite Them

And FERC just moved on it: the commission issued show-cause orders to the six largest U.S. grid operators, demanding they defend or rewrite the rules governing gigawatt-scale load connections, co-located generation, and cost allocation.

June 30, 2026

Subscribe for full access

Home-Rule Authority Faces Its First Real Test in San Marcos

FERC, ERCOT, PJM, and Southwest Power Pool are converging on commitment-first planning to strip speculative megawatts out of forecasts.

June 29, 2026

Subscribe for full access

Washington Set the Deadline. Texas Already Wrote the Playbook.

On June 27, the federal regulator ordered the nation's six major grid operators to propose reforms, or justify existing rules, governing how data centers and large customers connect, with a 60-day deadline and a 30-day report on how operators will ensure adequate generation for new large loads.

June 24, 2026

Subscribe for full access

Reeves County Banks 6,000 Jobs as the Behind-the-Meter Model Scales

PJM is now studying ERCOT's design, weighing a Path C energy-market tilt as it processes demand against capacity, and FERC voted unanimously to speed large-load interconnection while making data centers cover their own upgrade costs.

June 22, 2026

Subscribe for full access

ERCOT Studies Big Loads in Batches Now. The Queue Math Just Changed.

FERC's unanimous vote to speed large-load connections reinforces the federal appetite, but it doesn't reach ERCOT and it can't conjure generation that doesn't exist.

June 21, 2026

Subscribe for full access

Cost-Causation Is Here. Generation-First Siting Wins the 226 GW Queue.

Eight days later, FERC voted unanimously to bar the six interstate grid operators from socializing datacenter infrastructure costs to household ratepayers, putting the full burden on developers.

June 19, 2026

Subscribe for full access

Site Control Now Beats a Press Release in ERCOT's Queue

FERC issued six show-cause orders Thursday directing PJM, MISO, Southwest Power Pool, CAISO, ISO New England, and NYISO to justify or rewrite large-load tariffs within 60 days and file resource adequacy reports within 30.

June 5, 2026

Subscribe for full access

Meitner Sets the Panhandle Playbook: Own the Generation, Fund the Watershed

FERC Chair Laura Swett flagged a potential breakup at PJM's May 12 Baltimore meeting; a July 23 FERC meeting will weigh governance changes.

May 19, 2026

Subscribe for full access

NextEra Pays $67B for the Playbook Texas Has Run Since 2024

Registered entities must acknowledge by May 11, 2026 and report implementation by August 3, 2026, with revised Reliability Standards heading to FERC by December 31, 2026.

April 20, 2026

Hyperscalers Stop Waiting on the Grid as ERCOT Stares at 218 GW

Energy Transfer's $60 million Green Chile Project pipeline, 17 miles and 400,000 dekatherms/day from El Paso to Project Jupiter, drew a formal FERC staff protest April 13 over missing New Mexico State Historic Preservation Office documentation.

March 1, 2026

Nine States Push Back as Hyperscalers Redraw America's Power Map

In Spartanburg County, South Carolina, council killed TigerDC's tax incentive package for Project Spero after community opposition; FERC's December rejection of a 200 MW Duke Energy transmission line further complicates the project's grid access.

Frequently mentioned alongside