Weekly recap · Sep 28 – Oct 3, 2026
$25 Million Security Sits Under Gov. Abbott's Undated Permit Freeze
A 500 MW site now posts $25 million before ERCOT studies begin, and that capital sits while Governor Greg Abbott's undated audits freeze air permits.
The week in briefings
- Mon Sep 28A 500 MW Site Posts $25 Million Before ERCOT Studies Begin
- Tue Sep 29ALJs Condition Meta's 366 MW Gas on El Paso Electric Absorbing Every Dollar
- Wed Sep 30Gov. Abbott Conditions Air Permits on Undated ERCOT and TWDB Audits
- Thu Oct 1Aligned Breaks Ground on $10B, 2 GW Private Power in Shippingport
- Fri Oct 2Petition Asks Texas PUC to Plan Grid and Water Around Measured Data Center Loads
- Sat Oct 3Amazon Locks 95M Gallons at Wharton Ahead of Gov. Abbott's TCEQ Audit
Security Posts and Undated Audits
The Public Utility Commission of Texas set $50,000 per MW of upfront financial security for every new ERCOT load 75 MW and above, due before interconnection studies start. A 200 MW site posts $10 million; twenty percent returns at energization, and exit after capacity allocation forfeits 20 percent tied to allocated MW. Mon. Miss the 24-month energization window and the TSP can apply remaining security to unpaid balances. That's millions in posted capital converting to pure carrying cost while the load waits.
Governor Greg Abbott directed TCEQ on Sept. 21 to halt data-center air permits until ERCOT grid and TWDB water audits finish, with no published end date. Wed. Amazon's Horizon Junction sits mid-cycle. Operators who don't file complete power and water packages now burn quarters of idle land carry and forfeited study security against a calendar they can't control.
Ratepayer Gates Meet Private Generation
Administrative law judges proposed approving El Paso Electric's 366 MW McCloud gas package for Meta's $10 billion, 1 GW campus only if the utility absorbs every dollar of the $499 million, 813-unit Enchanted Rock fleet. Tue. Commissioners haven't set a vote. Denial strands the dedicated feed Meta specified while security clocks still run; conditional approval puts the carrying cost on the utility before energization.
Private generation is clearing schedules that utility queues can't. Aligned broke ground on a $10 billion, 2 GW Shippingport campus on dedicated fuel cells that never enter a transmission queue. Thu. Crusoe's Armstrong County and Jayton filings lock adjacent generation and closed-loop cooling on the same Gantt chart. Developers who won't sequence behind-the-meter power with air and water paths will watch COD slip quarters while peers energize on private clocks.
Water Rights and Measured Loads
Amazon locked Coastal Bend groundwater permits totaling 95.1 million gallons for its Wharton County campus ahead of the TCEQ audit window, with projected annual draw near 7.1 million and cooling kept off the groundwater path. Sat. Sites without equivalent offsets face longer negotiation risk and later energization on the same corridor; that's multi-quarter delay between land control and permit finality.
By Friday, Green Recursive Utility Service petitioned under Control No. 58317 to bind interconnection and water reviews to measured workload and cooling architecture instead of self-reports alone. Fri. From Monday's security floor through Friday's measurement petition, incomplete packages now price as forfeited posts, missed batches, and carrying cost that stacks in quarters.
What to Watch
- PUCT commissioners' vote date on the Meta/El Paso Electric 366 MW package and whether the ratepayer-absorb condition holds
- Commission action on Control No. 58317 and any comment schedule for measured-load standards
- Project 58000 Item 70 weighting on TEBA's 75-80% MBD band versus a near-100% default
- Any published ERCOT or TWDB timeline on the audits conditioning TCEQ air permits