Weekly recap · Oct 5 – 10, 2026
474 GW Queue Demands Firm Power Before December Audit
Capital only clears when generation, water offsets, and local permission land on one schedule. That's the week's filter as ERCOT's large-load queue hits 474 GW and the packages that still move pair load to firm megawatts before the next study clock.
The week in briefings
- Mon Oct 5OpenAI's $20B, 3.2 GW Hits Effingham as Texas Audits Run Through December
- Tue Oct 6Samsung's $1B Joins Helix's $10B Across Power, Wire, and Fiber
- Wed Oct 7AG Paxton Contests Water-Planning Seal as Planners Face 287 Silent Sites
- Thu Oct 8ERCOT Batches Large Loads After Queue Surges 650% to 474 GW
- Fri Oct 9Related's $22B Encinal Pairs 5 GW Load to Gas as 75 U.S. Projects Stall
- Sat Oct 10TensorWave's 222 MW Anchors Fermi; NRC Comments Close Nov. 23
Batch Timing and the December Audit
ERCOT's queue surged 650% from 63 GW at end-2024 to 474 GW by June 2025, with data centers roughly 90% of the backlog, and the operator shifted large customers into batch study after speculative multi-site filings left planners unable to separate real builds from placeholders Thu. Governor Greg Abbott's August 3 directive put ERCOT and the Public Utility Commission of Texas on a full interconnection audit; on September 21 he directed the Texas Commission on Environmental Quality to halt data center permit issuance until that work finishes, with ERCOT aiming to wrap by December 2026.
Projects that already held study slots before August 3 keep status. New applications face longer cycles, and TCEQ paths stay closed until the file lands. Cipher's Colchis holds conditional base-load status for 1 GW under Batch Zero, with final designations pending that December screen. Carrying cost between capacity availability and energization stacks every month acceptance criteria stay unpublished. Operators who don't lock anchor tenants, resource disclosure, and power procurement before the interconnection filing won't clear cleanly when the batch runs.
Private Generation Locks Delivery Dates
Related Companies and NextEra Energy Resources are advancing a $22B Encinal build in La Salle County: a 6.47 GW combined-cycle gas plant paired with a 5 GW data center, closed-loop cooling, and produced-water offtake, first phase aimed at 2029 Fri. Fermi America's Project Matador cleared an NRC draft EIS for four AP1000 reactors as campus plans stretch toward 17 GW, with TensorWave's binding lease at 222 MW and option room to 650 MW; comments on docket NRC-2026-0100 close November 23 Sat.
Samsung committed $1B to KKR-backed Helix Digital Infrastructure's $10B platform spanning campuses, generation, transmission, and fiber inside one capital structure Tue. Texas Energy Fund awards now total 5,446 MW after the Pecos 452 MW gas loan. Enverus projects 22.5 GW of datacenter behind-the-meter demand through 2030. Self-supplied power runs about $100 to $165/MWh versus grid near $90 to $95, yet four-to-seven-year interconnection waits make the premium the schedule buy. Sites that can't order modular kit, fuel, and signed offtake on the same calendar will book idle capital in quarters while peers energize.
Water Disclosure and Local Consent
The PUCT survey built with the Texas Water Development Board went to 377 facilities; only 90 had responded by August. Attorney General Ken Paxton is contesting release of county and regional water-planning fields while state planners still work incomplete returns Wed. Taylor City Council annexed the 664-acre Taylor Technology Campus after Big Watt Digital and PowerHouse Data Centers locked $28.2M in community spend and closed-loop terms capped near 1.6 million gallons initial fill.
Out-of-state capital still prices complete packages: OpenAI's $20B, 3.2 GW Effingham campus carries a closed-loop cap at 30,000 gallons per day while Texas operators write financing calendars against the December audit Mon. Operators who don't file verified offsets, cooling design, and survey answers before the next county packet carry hearing risk and renegotiated tenant COD dates measured in quarters.
What to Watch
- NRC public comments on Fermi docket NRC-2026-0100 close November 23
- ERCOT and TCEQ audit completion target through December 2026, plus any published acceptance criteria that restart permit paths
- Blue Energy's Port of Victoria gas-to-nuclear construction-permit part two, planned after a full year of site data into late 2027
- San Antonio zoning-rule follow-through after the October 15 council calendar