September 17, 2026
Subscribe for full access
Documentary Survival Now Prices 266 GW Energization to Dec. 10
Agencies
The Public Utility Commission of Texas regulates electric, telecommunications, and water utility services across the state and has authority over aspects of datacenter power consumption and grid reliability.
September 17, 2026
Subscribe for full access
Documentary Survival Now Prices 266 GW Energization to Dec. 10
September 5, 2026
Subscribe for full access
North Richland Hills Seeks State-Funded Health Studies at Iron Horse
September 4, 2026
Subscribe for full access
Control No. 58481 Puts $50K/MW Floor Before ERCOT Models 1 GW
September 1, 2026
Subscribe for full access
Only 22 GW Clear Section 9.5 Under Senate Bill 6 Batch Zero
August 29, 2026
Subscribe for full access
Gov. Abbott's Audit Spares Self-Supply as Amazon Stages 35 Turbines
August 11, 2026
Subscribe for full access
Gov. Abbott's Audit Leaves Batch Zero With No Restart Date
August 8, 2026
Subscribe for full access
Skybox, Digital Realty, Mara, Montera Sign Binding Pledges to Gov. Abbott
August 7, 2026
Subscribe for full access
Gov. Abbott Guardrails Win First QTS Commitment on Grid Upgrades
August 6, 2026
Self-Supplied Sites Move Ahead While Grid Projects WaitGovernor Greg Abbott directed the Public Utility Commission of Texas and ERCOT to conduct a full review and audit of all data center projects advancing through the interconnection process.
August 5, 2026
One Keller Comment Filing Shows How the Statewide Audit Reaches Each ProjectGovernor Greg Abbott ordered the Public Utility Commission of Texas and ERCOT to stop approving new data center grid connections until a full audit verifies each project's power draw, water use, tax incentives, ownership, and community impacts.
August 4, 2026
Every Queued Project Must Now Prove Water and Generation, With No End Date SetGovernor Greg Abbott ordered the Public Utility Commission of Texas and ERCOT to audit every datacenter project in the interconnection queue before any new grid connections advance, freezing forward movement on a queue that now holds more than 1,800 projects representing 474 GW.
August 1, 2026
The Same $50K Fee That Screens Datacenters Now Applies to Chevron and SamsungThe Public Utility Commission of Texas and ERCOT approved the batch rules in June; more than 90% of the 474,000 MW in the current queue are datacenters, but the same fee applies to Samsung, Chevron expansions, and the next SpaceX.
July 28, 2026
Post Security Before the Study, or Watch Your 2027 Slot Go to a Buildable ProjectFollowing Gov. Greg Abbott's June 10 directive, the Public Utility Commission of Texas outlined a rulebook that requires large loads to pay transmission charges once capacity becomes available (operating or not), post financial security before entering planning studies, and cover direct interconnection costs.
July 9, 2026
89% of New Power Requests Are Datacenters. Abbott Wants Guardrails.He's directed the Public Utility Commission of Texas and ERCOT to make sure datacenter interconnections don't raise residential power costs or strain local water.
July 8, 2026
Ratepayers Come Off the Hook. Developers Underwrite the Wires Themselves.On June 10, the governor directed the Public Utility Commission of Texas and ERCOT to require data centers to fund their own electric infrastructure and to "safeguard Texans, their property, and resources."
July 7, 2026
The Permian Gets Texas's First 765 kV Backbone, and CREZ Wrote the PlaybookIn April 2025, the Public Utility Commission of Texas approved a $13.8 billion, 765-kilovolt transmission strategy for the Permian Basin, ERCOT's first extra-high-voltage backbone, betting deliberately that transmission corridors drive site selection the way CREZ accidentally did for wind and later data centers.
July 3, 2026
Shared Interconnection Buys Speed. Disciplined Developers Already Underwrite the Curtailment.The Public Utility Commission of Texas staff has endorsed ERCOT's operating conditions for Crusoe Energy and Ensign Infrastructure's AI campus behind the Goodnight 1 wind farm in Armstrong County, one of the first tests of Texas's framework for colocating large loads with existing generation.
June 26, 2026
Five Tests Now Separate Real Load From Speculation in TexasThe Public Utility Commission of Texas approved ERCOT's "Batch Zero" study in June 2026, a centralized process that separates committed gigawatt-scale loads from speculative requests through readiness tests: site control, permits, financing, equipment orders, realistic demand forecasts.
June 25, 2026
The PUC Just Made Your Interconnection Agreement the Only Thing That MattersThe Public Utility Commission of Texas approved ERCOT's Batch Zero framework, a one-time systemwide study that consolidates evaluation of new large loads of 75 MW or more, replacing the utility-by-utility reviews that buckled under AI demand.
June 22, 2026
ERCOT Studies Big Loads in Batches Now. The Queue Math Just Changed.The Public Utility Commission of Texas approved ERCOT's new batch-study process for projects 75MW and larger, the first time an independent system operator has adopted batch rules at that scale.
June 19, 2026
Site Control Now Beats a Press Release in ERCOT's QueueOn June 18, the Public Utility Commission of Texas approved the Batch Zero framework, a solvency screen forcing projects above 75 MW to prove site control, post nonrefundable fees, and show credible financing before they hold a queue position.
June 18, 2026
225 Interconnection Requests, One Filter: ERCOT Sorts Real From PaperThe board voted June 2 to launch "Batch Zero," a tiered process that isolates financed, land-secured projects from speculative paper, and the Public Utility Commission of Texas reviews the framework Thursday.
June 14, 2026
Five Mandates, One Deadline: Abbott Hands PUCT the 2027 BlueprintGovernor Abbott directed the Public Utility Commission of Texas and ERCOT on Wednesday to submit recommendations by July 17 on data center water efficiency, ratepayer cost impacts, and community safeguards, with legislative proposals targeting the 2027 session.
June 10, 2026
418 GW Knock on Texas Doors. Behind-the-Meter Builders Skip the Line.The Public Utility Commission of Texas is building the screen that separates real load from speculative load before ratepayers eat the cost of phantom transmission.
June 2, 2026
Ride-Through Becomes the New Phase I Discipline for Texas SitesERCOT's board votes Tuesday on ride-through rules that would require data centers to stay online during grid disturbances or face disconnection penalties, with the Public Utility Commission of Texas likely to finalize later this year.
June 1, 2026
Tax Abatements Lose the Room. Power, Water, and Cost Causation Take Over.ERCOT and the Public Utility Commission of Texas haven't taken up separate rate-class mechanics, but the question is coming.
May 30, 2026
Reclaimed Water Cleared QTS's $10B Campus. Texas Developers Should Take Notes.ERCOT doesn't yet separate data centers into a distinct customer class. Developers who negotiate cost-sharing terms now, while the regulatory frame is still forming, will shape what the Public Utility Commission of Texas eventually codifies.
May 28, 2026
Helios Hits 1.6 GW on CREZ Lines Built for Wind a Decade AgoTexas operates under different institutions, with ERCOT and the Public Utility Commission of Texas as the primary actors, but the national direction is set.
May 16, 2026
Beacon Point Sets the 1-GW Template While 300 GW Wait in QueueTexas's advantage is structural: ERCOT publishes the queue, the Public Utility Commission of Texas runs the interconnection framework, and AEP Texas can execute on a 1-GW campus while peer states debate whether to let municipalities veto projects.
May 14, 2026
Hill County Draws the Line. Eight Projects Now Wait a Year.The vote lands the same week ERCOT warned the Public Utility Commission of Texas it has "concerns" with its own 368 GW load forecast for 2032.
May 11, 2026
Recycled Water Is the Texas Permit Edge. San Antonio Just Proved It.Texas operates under ERCOT and the Public Utility Commission of Texas with different mechanics, but the political template is portable.
April 27, 2026
Wisconsin Makes Hyperscalers Pay 100% of Their Own Generation BuildThe risk runs the other way too: if the Public Utility Commission of Texas treats private SMRs and gas self-supply as competitive threat rather than demand relief, permitting friction lands on the developers who moved earliest.
April 25, 2026
PUCT Just Drew the Line on Which Grid Bypasses CountThe Public Utility Commission of Texas unanimously approved the first direct wind-farm-to-datacenter connection on the ERCOT grid, the same week ERCOT's high-side demand scenario, peak load above 367,000 MW by 2032, was sent back as unrealistic.
April 24, 2026
Cancellations Quadrupled. Abilene's 2.1 GW Answer Is Off the Grid.ERCOT and the Public Utility Commission of Texas operate transparent dockets with defined queues, though PUCT has flagged demand forecasting uncertainty that developers should price in.
April 18, 2026
Self-Supply Developers Set Their Own Clock. The Rest Wait 128 Weeks.ERCOT filed a preliminary 2032 peak demand forecast of 367,790 megawatts with the Public Utility Commission of Texas this week, more than four times the August 2023 record of 85,508 MW.
Agencies
ERCOT
35 co-occurrences
People
Greg Abbott
24 co-occurrences
Companies
Microsoft
18 co-occurrences
Companies
Meta
16 co-occurrences
Companies
13 co-occurrences
Companies
OpenAI
12 co-occurrences
Companies
Amazon
12 co-occurrences
Places
Abilene, TX
10 co-occurrences
Companies
Crusoe
9 co-occurrences
Companies
QTS
9 co-occurrences