April 15, 2026
Subscribe for full access
Build Your Own Power Plant or Lose Your Place in Line
Microsoft is building 900 MW of off-grid natural gas capacity in Abilene through Crusoe Energy, and Brookfield has committed $5 billion to on-site power deployment.
April 13, 2026
Subscribe for full access
ERCOT's Queue Is Separating Real Developers From the Rest
Synergy's John Dinsdale noted the emergence of "gigawatt-scale campuses" in places like Abilene and Mount Pleasant.
April 11, 2026
Subscribe for full access
Developers Who Testify First Write the Standards Everyone Else Follows
Lancium revealed its Stargate Campus in Abilene consumed just 4 percent of its allocated water last month, with three of eight buildings operational and 8,500 workers on-site.
April 2, 2026
Subscribe for full access
West Texas Becomes the AI Corridor While the Rest of America Waits
Microsoft signed with Crusoe Energy for a 900 MW AI factory campus in Abilene, joining a regional build-out that now includes Meta's $10 billion El Paso expansion, the Stargate venture's 1.2 GW second phase, and Stream Data Centers' gigawatt-scale partnership with New Era Energy in Ector County.
March 31, 2026
Subscribe for full access
Texas's $25M Queue Fee Separates Serious Developers From Everyone Else
Microsoft is pursuing similarly mixed approaches in Abilene.
March 30, 2026
Subscribe for full access
Texas Writes the Rules While Google Writes the Check
Simultaneously, Microsoft is building two new AI buildings and a 900-megawatt power plant in Abilene after OpenAI backed away from further expansion there, consolidating Texas's position as the epicenter of American AI infrastructure.
March 29, 2026
Subscribe for full access
West Texas Is Building Its Own Grid, One Hyperscale Campus at a Time
Microsoft is absorbing OpenAI's abandoned expansion in Abilene, Texas, adding two new AI factory buildings and a 900-megawatt gas-fired power plant to what's becoming a 2.1-gigawatt computing complex.
March 28, 2026
Subscribe for full access
Texas Built the Datacenter Boom. Now It's Auditing the Deal.
Crusoe is expanding its Abilene campus to 2.1 GW with a 900 MW Microsoft-anchored facility.
March 26, 2026
Subscribe for full access
When Drones Target Power Lines, the Perimeter Is Everywhere
Crusoe co-founder Cully Cavness was blunt about the shift: the Abilene, Texas project launched when wind curtailment created negative pricing, but "today, these kinds of opportunities are fewer and farther between."
March 15, 2026
Subscribe for full access
Solve Water Before You Break Ground, or Else
A new academic study from UC Riverside, Caltech, and RIT documents that local water supply is a non-negotiable bottleneck for AI infrastructure siting, with OpenAI's scrapped Stargate expansion in Abilene, Texas cited as Exhibit A.
March 9, 2026
Texas's Next Gigawatt Cluster Depends on Fights No Developer ControlsOpenAI and Oracle have capped the Stargate datacenter in Abilene, Texas at **1.2 GW**, abandoning plans to expand to 2.0 GW after power grid delays exceeded one year and winter weather knocked liquid cooling systems offline for days.
March 7, 2026
Stargate Stalls at 1.2 GW While Iren Quietly Builds 2.75Oracle and OpenAI have killed expansion plans for their flagship Stargate campus in Abilene, Texas, capping the site at its original 1.2 GW footprint and abandoning the planned 2 GW second phase.
March 6, 2026
Seven Signatures, One Fed Model, and 0.13 Points of InflationLancium, lead developer of Project Stargate's Abilene campus, was Monarch's first investor.
March 1, 2026
Nine States Push Back as Hyperscalers Redraw America's Power MapBIC Magazine reports Texas is commanding nearly $90 billion in annual datacenter and advanced manufacturing construction, anchored by OpenAI's $100 billion Stargate project in Abilene and "Data City" near Laredo.
February 26, 2026
Turbines Ease the Power Bottleneck. 91 Billion Gallons Say Water Is Next.Aeroderivative gas turbines are crossing from niche peaking duty into core datacenter power strategy, with Boom Supersonic's 42 MW Boom Superpower unit landing Crusoe Energy as its first customer at the Stargate campus in Abilene, Texas.
February 24, 2026
35 GW Pre-Leased, 107-Week Lead Times, Zero Margin for ErrorHunterbrook identified IGSA Power, a Mexico-based manufacturer with a Laredo office, as a likely second supplier, with an IGSA representative referencing "Abilene DC3, DC4, DC8" in connection with Crusoe generator orders.
February 23, 2026
Texas Adds 58 GW of Gas in One Year. The Grid May Be the Last to Know.Meta's El Paso behind-the-meter approach and Oracle/OpenAI's Stargate facility in Abilene fit the same pattern: operators are building their own power because they can't wait for grid interconnection.
February 19, 2026
Water, Not Power, Will Decide Who Wins the Texas Data Center RaceA single midsized facility drinks 300,000 gallons daily; OpenAI's Stargate campus in Abilene will consume far more.
February 18, 2026
Texas Attracts Megawatts Faster Than It Can Write the Rules to Manage ThemCrusoe Energy Systems, developer of the 1.2 GW Stargate campus in Abilene backed by OpenAI, SoftBank, and Oracle, has filed arguments that a new ERCOT approval requirement for private power agreements could impose 180-day delays on developers with billions already committed.
February 13, 2026
Capital Keeps Pouring In. Communities Are Closing the Gate.In Abilene, roughly 6,000 Stargate construction workers have flooded a metro of just over 100,000, triggering a housing affordability crisis and rent spikes.
February 10, 2026
Behind the Fence: Texas Gigawatts Stack Up Faster Than Rules Can FollowAnd in Abilene, Crusoe Energy's 1.2-GW Stargate Phase 1 is already online.